Rules for the Calculation of the Over or Under Recovery in the Implementation of Transmission Rates by Distribution Utilities ( ERC Resolution No. 09-09 )
March 16, 2009
March 16, 2009
ERC RESOLUTION NO. 09-09
RESOLUTION ADOPTING THE RULES FOR THE CALCULATION OF THE OVER OR UNDER RECOVERY IN THE IMPLEMENTATION OF TRANSMISSION RATES BY DISTRIBUTION UTILITIES (DUs)
WHEREAS, Section 43 (f) of Republic Act No. 9136, otherwise known as the Electric Power Industry Reform Act of 2001 (EPIRA), and its Implementing Rules and Regulations (IRR), provide that the Energy Regulatory Commission (ERC) shall determine, fix and approve, among others, the retail rates to be imposed by Distribution Utilities (DUs) through an established and enforced methodologies; aIcDCH
WHEREAS, to facilitate the evaluation and resolution of all applications for refund of over recoveries or collection of under recoveries, the Commission formulated a draft "Rules for the Calculation of the Over or Under Recovery in the Implementation of Transmission Rates by Distribution Utilities (DUs)", which was subjected to public consultations on various dates;
WHEREAS, after a thorough evaluation of the comments and views submitted by the participants, the Commission deems it necessary to formulate and adopt a set of rules that would govern the calculation of the over or under recovery in the implementation of transmission rates by DUs;
NOW, THEREFORE, be it RESOLVED, as the Commission hereby RESOLVES to ADOPT the "Rules for the Calculation of the Over or Under Recovery in the Implementation of Transmission Rates by Distribution Utilities (DUs)". cCSDTI
This Resolution shall take effect after fifteen (15) days following the completion of its publication in a newspaper of general circulation in the Philippines.
Let copies of this Resolution be furnished the University of the Philippines Law Center-Office of the National Administrative Register (UPLC-ONAR) and all Distribution Utilities (DUs).
Pasig City, March 16, 2009. AEIHaS
(SGD.) ZENAIDA G. CRUZ-DUCUTChairperson
(SGD.) RAUF A. TANCommissioner
(SGD.) ALEJANDRO Z. BARINCommissioner
(SGD.) MARIA TERESA A.R. CASTAÑEDACommissioner
(SGD.) JOSE C. REYESCommissioner
ATTACHMENT
List of Distribution Utilities: | |
1. | ANGELES ELECTRIC CORPORATION |
1903 Robinsons Equitable Tower | |
ADB Avenue corner Poveda Street, Pasig City | |
2. | FIRST BAY POWER CORPORATION |
4201 Bauan, Batangas | |
3. | CABANATUAN ELECTRIC CORPORATION |
Daang Maharlika, Bitas Road, | |
3100 Cabanatuan City, Nueva Ecija | |
4. | PUBLIC UTILITIES DEPARTMENT (PUD-Olongapo) |
2200 Olongapo City, Zambales | |
5. | DAGUPAN ELECTRIC CORPORATION |
3rd floor, Veria I Building | |
West Avenue, Quezon City | |
6. | IBAAN ELECTRIC AND ENGINEERING CORPORATION |
212 Mercado Street | |
4230 Ibaan, Batangas | |
7. | LA UNION ELECTRIC COMPANY, INC. |
Quezon Avenue | |
2500 San Fernando, La Union | |
8. | SAN FERNANDO ELECTRIC LIGHT AND POWER COMPANY, INC. |
2000 San Fernando, Pampanga | |
9. | TARLAC ELECTRIC INC. |
Mabini Street, | |
2300 Tarlac, Tarlac | |
10. | MACTAN ELECTRIC COMPANY, INC. |
6015 Lapu-lapu City, Cebu | |
11. | PANAY ELECTRIC COMPANY, INC. |
Cacho Building, J.M. Basa Street | |
5000 Iloilo City | |
12. | BOHOL LIGHT COMPANY, INC. |
6300 Tagbilaran City, Bohol | |
13. | CAGAYAN ELECTRIC POWER AND LIGHT COMPANY, INC. |
8th Floor Strata 100 Bldg., | |
Emerald Avenue, Ortigas Complex, Pasig City | |
14. | ILIGAN LIGHT AND POWER, INC. |
Bro. Raymund Jeffrey Road, | |
La Salle Road, Pala-O | |
9200 Iligan City, Lanao del Norte | |
15. | MANILA ELECTRIC COMPANY |
Ortigas Avenue, Pasig City | |
16. | VISAYAN ELECTRIC COMPANY (VECO) |
52 D. Jakosalem Street | |
6000 Cebu City | |
17. | DAVAO LIGHT AND POWER COMPANY |
Aboitiz Complex, Banilad | |
6000 Cebu City | |
18. | COTABATO LIGHT AND POWER COMPANY |
Aboitiz Complex, Banilad | |
6000 Cebu City | |
19. | ILOCOS NORTE ELECTRIC COOPERATIVE, INC. |
2913 Dingras, Ilocos Norte | |
20. | ILOCOS SUR ELECTRIC COOPERATIVE, INC. |
2707 Santiago, Ilocos Sur | |
21. | LA UNION ELECTRIC COOPERATIVE, INC. |
2503 Aringay, La Union | |
22. | PANGASINAN I ELECTRIC COOPERATIVE, INC. |
2470 Bani, Pangasinan | |
23. | CENTRAL PANGASINAN ELECTRIC COOPERATIVE, INC. |
2420 San Carlos City, Pangasinan | |
24. | PANGASINAN III ELECTRIC COOPERATIVE, INC. |
2428 Urdaneta, Pangasinan | |
25. | BATANES ELECTRIC COOPERATIVE, INC. |
3900 Basco, Batanes | |
26. | CAGAYAN I ELECTRIC COOPERATIVE, INC. |
3503 Maddarulug, Solana, Cagayan | |
27. | CAGAYAN II ELECTRIC COOPERATIVE, INC. |
Concepcion Building, Centro Appari | |
3515 Cagayan | |
28. | ISABELA I ELECTRIC COOPERATIVE, INC. |
3306 Alicia, Isabela | |
29. | ISABELA II ELECTRIC COOPERATIVE, INC. |
3300 Ilagan, Isabela | |
30. | NUEVA VIZCAYA ELECTRIC COOPERATIVE, INC. |
3707 Dupax del Sur, Nueva Vizcaya | |
31. | QUIRINO ELECTRIC COOPERATIVE, INC. |
3401 Diffun, Quirino | |
32. | ABRA ELECTRIC COOPERATIVE, INC. |
2800 Bangued, Abra | |
33. | BENGUET ELECTRIC COOPERATIVE, INC. |
2601 Alapang, La Trinidad, Benguet | |
34. | IFUGAO ELECTRIC COOPERATIVE, INC. |
3600 Lagawe, Ifugao | |
35. | KALINGA APAYAO ELECTRIC COOPERATIVE, INC. |
3800 Magsaysay, Tabuk, Kalinga-Apayao | |
36. | MOUNTAIN PROVINCE ELECTRIC COOPERATIVE, INC. |
2616 Bontoc, Mt. Province | |
37. | PENINSULA ELECTRIC COOPERATIVE, INC. |
2100 Balanga, Bataan | |
38. | NUEVA ECIJA I ELECTRIC COOPERATIVE, INC. |
3106 Malapit, San Isidro, Nueva Ecija | |
39. | NUEVA ECIJA II ELECTRIC COOPERATIVE, INC. — Area 1 |
3114 Talavera, Nueva Ecija | |
40. | NUEVA ECIJA II ELECTRIC COOPERATIVE, INC. — Area 2 |
3102 San Leonardo, Nueva Ecija | |
41. | PAMPANGA I ELECTRIC COOPERATIVE, INC. |
2021 Sto. Domingo, Mexico, Pampanga | |
42. | PAMPANGA II ELECTRIC COOPERATIVE, INC. |
2003 Guagua, Pampanga | |
43. | PAMPANGA III ELECTRIC COOPERATIVE, INC. |
2016 Apalit, Pampanga | |
44. | PAMPANGA RURAL ELECTRIC SERVICE COOPERATIVE, INC. |
2021 Anao, Mexico, Pampanga | |
45. | SAN JOSE CITY ELECTRIC COOPERATIVE, INC. |
3121 San Jose City, Nueva Ecija | |
46. | TARLAC I ELECTRIC COOPERATIVE, INC. |
2302 Gerona, Tarlac | |
47. | TARLAC II ELECTRIC COOPERATIVE, INC. |
2316 Concepcion, Tarlac | |
48. | ZAMBALES I ELECTRIC COOPERATIVE, INC. |
2210 Palauig, Zambales | |
49. | ZAMBALES II ELECTRIC COOPERATIVE, INC. |
2208 Castillejos, Zambales | |
50. | AURORA ELECTRIC COOPERATIVE, INC. |
3200 Baler, Aurora | |
51. | BATANGAS I ELECTRIC COOPERATIVE, INC. |
4212 Calaca, Batangas ESIcaC | |
52. | BATANGAS II ELECTRIC COOPERATIVE, INC. |
Kapitan Simeon Luz Street, Antipolo Del Norte | |
4217 Lipa City, Batangas | |
53. | BUSUANGA ISLAND ELECTRIC COOPERATIVE, INC. |
5316 Coron, Palawan | |
54. | FIRST LAGUNA ELECTRIC COOPERATIVE, INC. |
4014 Lumban, Laguna | |
55. | LUBANG ELECTRIC COOPERATIVE, INC. |
5109 Tilik, Lubang, Occidental Mindoro | |
56. | MARINDUQUE ELECTRIC COOPERATIVE, INC. |
4900 Ihatub, Boac, Marinduque | |
57. | OCCIDENTAL MINDORO ELECTRIC COOPERATIVE, INC. |
5100 San Jose, Occidental Mindoro | |
58. | ORIENTAL MINDORO ELECTRIC COOPERATIVE, INC. |
5200 Simaron, Calapan, Oriental Mindoro | |
59. | PALAWAN ELECTRIC COOPERATIVE, INC. |
5300 Puerto Princesa City, Palawan | |
60. | QUEZON I ELECTRIC COOPERATIVE, INC. |
4308 Pitogo, Quezon | |
61. | QUEZON II ELECTRIC COOPERATIVE, INC. |
4336 Gomez Street, Infanta, Quezon | |
62. | ROMBLON ELECTRIC COOPERATIVE, INC. |
5500 Romblon, Romblon | |
63. | TABLAS ISLAND ELECTRIC COOPERATIVE, INC. |
5505 Odiongan, Romblon | |
64. | ALBAY ELECTRIC COOPERATIVE, INC. |
4500 Legazpi City, Albay | |
65. | CAMARINES NORTE ELECTRIC COOPERATIVE, INC. |
Magallanes Ilaod, Daet, Camarines Norte 4600 | |
66. | CAMARINES SUR I ELECTRIC COOPERATIVE, INC. |
4407 Libmanan, Camarines Sur | |
67. | CAMARINES SUR II ELECTRIC COOPERATIVE, INC. |
4400 Naga City, Camarines Sur | |
68. | CAMARINES SUR III ELECTRIC COOPERATIVE, INC. |
4431 San Jose, Iriga City Camarines Sur | |
69. | CAMARINES SUR IV ELECTRIC COOPERATIVE, INC. |
4420 Tigaon, Camarines Sur | |
70. | FIRST CATANDUANES ELECTRIC COOPERATIVE, INC. |
4801 Bato, Catanduanes | |
71. | MASBATE ELECTRIC COOPERATIVE, INC. |
5400 Masbate, Masbate | |
72. | SORSOGON I ELECTRIC COOPERATIVE, INC. |
4707 Irosin, Sorsogon | |
73. | SORSOGON II ELECTRIC COOPERATIVE, INC. |
4700 Sorsogon, Sorsogon | |
74. | TICAO ISLAND ELECTRIC COOPERATIVE, INC. |
5417 San Jacinto, Masbate | |
75. | AKLAN ELECTRIC COOPERATIVE, INC. |
5600 Kalibo, Aklan | |
76. | ANTIQUE ELECTRIC COOPERATIVE, INC. |
5700 San Jose, Antique | |
77. | CAPIZ ELECTRIC COOPERATIVE, INC. |
Timpas, Panitan, Capiz 5815 | |
78. | GUIMARAS ELECTRIC COOPERATIVE, INC. |
5045 San Miguel, Jordan, Guimaras | |
79. | ILOILO I ELECTRIC COOPERATIVE, INC. |
5021 Tigbauan, Iloilo | |
80. | ILOILO II ELECTRIC COOPERATIVE, INC. |
5008 Brgy. Cauayan, Pototan, Iloilo | |
81. | ILOILO III ELECTRIC COOPERATIVE, INC. |
5014 Sara, Iloilo | |
82. | CENTRAL NEGROS ELECTRIC COOPERATIVE, INC. |
6100 Bacolod City, Negros Occidental | |
83. | NEGROS OCCIDENTAL ELECTRIC COOPERATIVE, INC. |
6111 Kabangkalan, Negros Occidental | |
84. | VMC RURAL ELECTRIC SERVICE COOPERATIVE, INC. |
6120 Torlosa, Manapla, Negros Occidental | |
85. | BANTAYAN ISLAND ELECTRIC COOPERATIVE, INC. |
6052 Bantayan, Cebu | |
86. | BOHOL I ELECTRIC COOPERATIVE, INC. |
6329 Mac-as, Tubigon, Bohol | |
87. | BOHOL II ELECTRIC COOPERATIVE, INC. |
6308 Jagna, Bohol | |
88. | CAMOTES ISLAND ELECTRIC COOPERATIVE, INC. |
6049 Poro, Camotes Island, Cebu | |
89. | CEBU I ELECTRIC COOPERATIVE, INC. |
6035 Dumanjug, Cebu | |
90. | CEBU II ELECTRIC COOPERATIVE, INC. |
6010 Malingin, Bogo, Cebu | |
91. | CEBU III ELECTRIC COOPERATIVE, INC. |
6038 Toledo City, Cebu | |
92. | NEGROS ORIENTAL I ELECTRIC COOPERATIVE, INC. |
6209 Bindoy, Negros Oriental | |
93. | NEGROS ORIENTAL II ELECTRIC COOPERATIVE, INC. |
6200 Dumaguete City, Negros Oriental | |
94. | PROVINCE OF SIQUIJOR ELECTRIC COOPERATIVE, INC. |
6226 Larena, Siquijor | |
95. | BILIRAN ISLAND ELECTRIC COOPERATIVE, INC. |
4543 Corvera Street, Naval, Biliran | |
96. | EASTERN SAMAR ELECTRIC COOPERATIVE, INC. |
6800 Borongan, Eastern Samar | |
97. | NORTHERN SAMAR ELECTRIC COOPERATIVE, INC. |
6400 Del Pilar Street, Catarman, Northern Samar | |
98. | SAMAR I ELECTRIC COOPERATIVE, INC. |
6710 Carayman, Calbayog City, Western Samar | |
99. | SAMAR II ELECTRIC COOPERATIVE, INC. |
6700 Catbalogan, Western Samar | |
100. | LEYTE I ELECTRIC COOPERATIVE, INC. |
6503 Tolosa, Leyte | |
101. | LEYTE II ELECTRIC COOPERATIVE, INC. |
6500 Tacloban City, Leyte | |
102. | LEYTE III ELECTRIC COOPERATIVE, INC. |
6528 Tunga, Leyte | |
103. | LEYTE IV ELECTRIC COOPERATIVE, INC. |
6524 Hilongos, Leyte | |
104. | LEYTE V ELECTRIC COOPERATIVE, INC. |
6541, Ormoc City, Leyte | |
105. | SOUTHERN LEYTE ELECTRIC COOPERATIVE, INC. |
6000 Nasaug, Maasin, Southern Leyte | |
106. | BASILAN ELECTRIC COOPERATIVE, INC. |
7300 Isabela, Basilan | |
107. | SULU ELECTRIC COOPERATIVE, INC. |
7400 Bus-Bus, Jolo, Sulu | |
108. | CAGAYAN DE SULU ELECTRIC COOPERATIVE, INC. |
7508 Cagayan de Sulu, Mapun, Tawi-tawi | |
109. | SIASI ELECTRIC COOPERATIVE, INC. |
7412 Poblacion Siasi, Sulu | |
110. | TAWI-TAWI ELECTRIC COOPERATIVE, INC. |
7500 Tubig-Boh, Bongao, Tawi-tawi | |
111. | ZAMBOANGA CITY ELECTRIC COOPERATIVE, INC. |
7000 Zamboanga City, Zamboanga del Sur | |
112. | ZAMBOANGA DEL NORTE ELECTRIC COOPERATIVE, INC. |
7100 Dipolog City, Zamboanga del Norte | |
113. | ZAMBOANGA DEL SUR I ELECTRIC COOPERATIVE, INC. |
7016 Pagadian City, Zamboanga del Sur | |
114. | ZAMBOANGA DEL SUR II ELECTRIC COOPERATIVE, INC. |
7001 Ipil, Zamboanga del Sur | |
115. | AGUSAN DEL NORTE ELECTRIC COOPERATIVE, INC. |
8600 Butuan City, Agusan del Norte | |
116. | AGUSAN DEL SUR ELECTRIC COOPERATIVE, INC. |
8501 San Francisco, Agusan del Sur | |
117. | FIRST BUKIDNON ELECTRIC COOPERATIVE, INC. |
8714 Anahawon, Maramag, Bukidnon | |
118. | BUKIDNON II ELECTRIC COOPERATIVE, INC. |
8703 Manolo Fortich, Bukidnon | |
119. | CAMIGUIN ELECTRIC COOPERATIVE, INC. |
9100 Mambajao, Camiguin | |
120. | DINAGAT ISLAND ELECTRIC COOPERATIVE, INC. |
8427 San Jose Dinagat Island, Surigao del Norte | |
121. | MISAMIS OCCIDENTAL I ELECTRIC COOPERATIVE, INC. |
7210 Calamba, Misamis Occidental | |
122. | MISAMIS OCCIDENTAL II ELECTRIC COOPERATIVE, INC. |
7202 Tudela, Misamis Occidental | |
123. | MISAMIS ORIENTAL I ELECTRIC COOPERATIVE, INC. |
9019 Laguidingan, Misamis Oriental | |
124. | MISAMIS ORIENTAL II ELECTRIC COOPERATIVE, INC. |
9013 Medina, Misamis Oriental | |
125. | SIARGAO ELECTRIC COOPERATIVE, INC. |
8417 Dapa, Surigao del Norte | |
126. | SURIGAO DEL NORTE ELECTRIC COOPERATIVE, INC. |
Narciso Street cor. Espina Street, | |
8400 Surigao City, Surigao del Norte | |
127. | DAVAO DEL NORTE ELECTRIC COOPERATIVE, INC. |
8801 Montevista, Davao del Norte | |
128. | DAVAO ORIENTAL ELECTRIC COOPERATIVE, INC. |
8200 Mati, Davao Oriental | |
129. | DAVAO DEL SUR ELECTRIC COOPERATIVE, INC. |
8002 Digos, Davao del Sur | |
130. | SOUTHERN COTABATO I ELECTRIC COOPERATIVE, INC. |
9506 Koronadal, Southern Cotabato AECcTS | |
131. | SOUTHERN COTABATO II ELECTRIC COOPERATIVE, INC. |
9500 Lagao, General Santos City, Southern Cotabato | |
132. | SURIGAO DEL SUR I ELECTRIC COOPERATIVE, INC. |
8311 Bislig, Surigao del Sur | |
133. | SURIGAO DEL SUR II ELECTRIC COOPERATIVE, INC. |
8300 Tandag, Surigao del Sur | |
134. | LANAO DEL NORTE ELECTRIC COOPERATIVE, INC. |
9209 Tubod, Lanao del Norte | |
135. | LANAO DEL SUR ELECTRIC COOPERATIVE, INC. |
9700 Maliwanag Islamic City of Marawi, Lanao del Sur | |
136. | MAGUINDANAO ELECTRIC COOPERATIVE, INC. |
9601 Datu Odin Sinsuat, Maguindanao | |
137. | NORTH COTABATO ELECTRIC COOPERATIVE, INC. |
9406 Matalan, North Cotabato | |
138. | SULTAN KUDARAT ELECTRIC COOPERATIVE, INC. |
Bernardo Building, National Highway | |
9800 Takurong, Sultan Kudarat | |
139. | MARIPIPI MULTI-PURPOSE COOPERATIVE (MMPC) |
6546 Maripipi Island, Province of Biliran |
RULES FOR THE CALCULATION OF THE OVER OR UNDER RECOVERY IN THE IMPLEMENTATION OF TRANSMISSION RATES BY DISTRIBUTION UTILITIES
Pursuant to Section 43 (f) of Republic Act No. 9136, otherwise known as the "Electric Power Industry Reform Act of 2001 (EPIRA)", the Energy Regulatory Commission (ERC) hereby adopts and promulgates these Rules to establish a process for the calculation of the over or under recovery in the Transmission Rates by Distribution Utilities (DUs).
ARTICLE I
General Provisions
1.1 Objectives
1.1.1 To ensure transparent and reasonable prices of electric power service in a regime of free and fair competition and to achieve greater operational and economic efficiency; CDHSac
1.1.2 To ensure full recovery of the allowable cost of Transmission;
1.1.3 To protect the public interest as it is affected by the rates and services of DUs; and
1.1.4 To ensure and maintain the quality, reliability, security and affordability of the supply of electric power.
1.2 Scope
1.2.1 These Rules shall apply to all DUs that are connected to the Grid.
1.3 Definition of Terms
Act | — | unless otherwise stated, shall refer to |
Republic Act No. 9136, otherwise known as | ||
the "Electric Power Industry Reform Act of | ||
2001; | ||
Distribution Utility | — | shall refer to any electric cooperative (EC), |
(DU) | private corporation, government-owned | |
utility or existing local government unit | ||
which has an exclusive franchise to operate | ||
a distribution system in accordance with the | ||
Act; | ||
Energy Regulatory | — | shall refer to the independent, quasi-judicial |
Commission or ERC | regulatory agency created under Section 38 of the | |
Act; | ||
Net Transmission | — | shall refer to the total charges of National |
Cost | Transmission Corporation (TRANSCO), or its | |
buyer or concessionaire, including, but not | ||
limited to, transmission and sub-transmission | ||
costs, ancillary service, connection service and | ||
power cost delivery service net of any imbalance | ||
charges, cost associated with the availment of the | ||
One-Day Power Sales (ODPS), and value added | ||
tax associated with the transmission service. Net | ||
transmission costs shall include only those costs | ||
that are prudently incurred, actually paid for, | ||
verifiable, reasonable, and are eligible for | ||
recovery in accordance with the ERC's Rules and | ||
Regulations. | ||
Transmission Rates | — | for the purpose of these Rules, shall refer to the |
charges associated with the transmission cost | ||
incurred by the DU which have been determined | ||
by the ERC in the DU's Unbundling of Rates | ||
Application. |
ARTICLE II
Calculation of Over or Under Recovery in Transmission
2.1 One-Time Determination
The transmission rates paid by the DUs prior to the effectivity of these Rules were fixed annually for four (4) years which incorporated the removal of the intra-grid cross subsidies of TRANSCO as provided in the approved unbundled rates of the DUs. The Commission shall allow the one-time determination of the over or under recovery on the DU's transmission charges from the time the DUs implemented their unbundled rates up to the effectivity of the "Guidelines for the Adjustment of the Transmission Rates by Distribution Utilities" (TRAM Guidelines).
2.2 Adjustment Formula
The calculation of the over or under recovery in the implementation of the transmission rates to effect the "refund" or "collect" thereof from the time the DUs first implemented their unbundled rates up to April 2006 or the month before the DUs were able to implement new transmission rates in accordance with the TRAM Guidelines, shall be based on the following formula per customer class:
Transmission | = | Total Over or Under RecoveryN | |
Over or | –––––––––––––––––––––––– | ||
Under RecoveryN | ƩkWh SalesNi | ||
(PhP/kWh) | i = 1 ...n | ||
where: | |||
Total Over or | = | Ʃi [(Allowable Transmission CostNi- | |
Under | i = 1 ...n Transmission RecoveryNi)] | ||
RecoveryN | |||
(PhP) | |||
Allowable | = | Allowable Transmission Cost of SalesNi | |
Transmission | |||
CostNi | |||
Allowable | = | (Transmission Costi — NPFD x 50%) | |
Transmission | ––––––––––––––––––––––––––––– | ||
Cost of SalesNi | Total Purchased kWhi | ||
x Total kWh Salesi x CPN | |||
I | = | refers to month 1, month 2 until month n, where | |
month 1 refers to the month the DU | |||
implemented its unbundled rates and month n | |||
refers to the month prior to the implementation | |||
of the TRAM Guidelines | |||
N | = | refers to a specific customer class (ex. N=1,2, | |
. . ., where 1= Residential, 2= Commercial, etc.) | |||
Transmission | = | (Transmission Charge in PhP/kWh x kWh | |
Recovery Ni | SalesNi) + (Transmission Charge in PhP/kW x | ||
KW billing demandNi) | |||
Transmission | = | the actual net transmission cost in PhP | |
Costi | for the month i | ||
NPFD | = | Where: | |
Gross Power Factor Discount availed | |||
by the DU from TransCo | PhPXXX | ||
Less: (1) Power Factor Discount | |||
Granted by the DU | XXX | ||
(2) The amount paid by the DU | |||
under a business agreement with a | |||
third party for the improvement of its | |||
power factor * | XXX | ||
––––– | |||
Net Power Factor Discount (NPFD) | XXX | ||
Multiplied by (percentage share) | 50% | ||
NPFD to be passed on by the | –––––––– | ||
DUs to its customers | PhPXXX | ||
======= | |||
Note: * shall not exceed 50% of Gross PFD | |||
Total Purchased | = | kWh purchases from all suppliers that | |
kWhi | correspond to the kWh sales billed the | ||
transmission charge for the monthi less | |||
ODPS | |||
Total KWh Salesi | = | Total kWh sales of the DU for the monthi | |
CPN | = | Coincident Peak allocation factor for customer | |
class N as reflected in the last approved | |||
unbundled rates of the DU | |||
Transmission | = | Transmission charge in PhP/kWh and/or | |
Charge in | PhP/kW as applicable to customer class N | ||
PhP/kWh and | and provided in the Unbundling Decision | ||
PhP/kW | of the DU. If the transmission charge for | ||
customer N is expressed in PhP/kWh only, then | |||
the Transmission Charge in PhP/kW in the | |||
formula should be equal to zero (0) | |||
KWh SalesNi | = | Total kWh sales for customer class N for the | |
month i | |||
KW SalesNi | = | Total kW billing demand for customer class N | |
for the monthi |
The calculation of the over or under recovery in the Transmission Rate per customer class shall be expressed in PhP/kWh for customers billed on a per kWh basis or a combination of per kWh and per kW and PhP/kW for customers billed on a per kW basis in accordance with the formula provided in 2.3 hereof.
2.3. Billing of the Over or Under Recovery in Transmission Rates
Any over or under recovery as may be approved by the ERC shall be implemented by the DU by incorporating the rate in the existing transmission rates component (in PhP/kWh) of the DU's customer bills. However, if the existing transmission rate component of a DU to its specific customer class is in PhP/kW, the calculated PhP/kWh can be converted to PhP/kW using the following formula:
Calculated PhP/kWh | |
PhP/kW = | ––––––––––––––––––––––––––––––––––––––––––––– |
1/[ load factor x {(365 days/yr x 24 hrs/day)/12 mos/yr}] |
ARTICLE III
Filing Requirements
3.1 Filing
The filing for any over or under recovery in the implementation of Transmission Rates shall be made in accordance with Section 1 of Article 6 of the Rules Governing the Automatic Cost Adjustment and True-Up Mechanisms for Distribution Utilities.
3.2 Supporting Documents
The application referred to in 3.1 shall be accompanied by the following documents:
3.1.1 Invoices from TRANSCO;
3.1.2 Vouchers and Official receipts of payment of TRANSCO's invoices;
3.1.3 ERC Forms DU-M-01 and DU-M-02;
3.1.4 Monthly Financial and Statistical Report (MFSR) for ECs and M-001 and M-002 for PUs (prior to the effectivity of the above forms);
3.1.5 Summary of Monthly Purchased kWh from all suppliers that corresponds to the monthly kWh sales billed the transmission charge by the DU; and
3.1.6 Other documents deemed relevant by the ERC.
3.3 Provisional Authority
Upon filing of the application, the ERC may, upon motion, issue a Provisional Authority (PA) based on the allegations in the application, the supporting documents attached thereto as well as the submissions in compliance with the reportorial requirements and on such comments or pleadings filed by any interested party within thirty (30) days from receipt of a copy of the application by the local legislative body of the local government unit where applicant principally operates or from the publication thereof, as the case may be. aSADIC
ARTICLE IV
Monitoring of the Implementation of the
Upon evaluation and approval by the ERC of any over or under recovery in the implementation of the transmission and corresponding system loss charges filed by the DUs, the DUs shall be required to submit to the ERC, after six (6) months from their implementation, and every six (6) months thereafter, a report on the status of their monthly implementation of the approved rate and the corresponding balance of the over or under recovery until such time that the total amount of the said over or under recovery shall have been fully refunded or collected.
ARTICLE V
Fines and Penalties
Violation of any provision of these Rules shall be subject to the imposition of fines and penalties in accordance with the Guidelines to Govern the Imposition of Administrative Sanctions in the Form of Fines and Penalties Pursuant to Section 46 of Republic Act No. 9136.
ARTICLE VI
Exception
Where good cause appears, the ERC may allow an exception from any provision of these Rules, if such exception is found to be in the public interest and is not contrary to any law, rules and regulations. aDHCEA
ARTICLE VII
Separability
If, for any reason, any part or section of these Rules is declared unconstitutional or invalid, the other parts or sections hereof which are not affected thereby shall continue to be in full force and effect.
ARTICLE VIII
Effectivity
These Rules shall take effect fifteen (15) days following its publication in a newspaper of general circulation.
Pasig City, March 16, 2009.
(SGD.) ZENAIDA G. CRUZ-DUCUTChairperson
(SGD.) RAUF A. TANCommissioner
(SGD.) ALEJANDRO Z. BARINCommissioner
(SGD.) MARIA TERESA A.R. CASTAÑEDACommissioner
(SGD.) JOSE C. REYESCommissioner