Implementation of the Document Tracking System (DoTS) for the Procurement of Goods
The Department of Public Works and Highways (DPWH) issued Department Order No. 008-12 on February 21, 2012, to implement a Document Tracking System (DoTS) aimed at enhancing transparency and efficiency in the procurement of goods. This system mandates the registration of several key procurement documents, such as the Project Procurement Management Plan and Purchase Orders, ensuring that all requesting offices follow the established procedures. The order emphasizes strict compliance with the DoTS, stating that documents lacking the DoTS header will be returned unprocessed. Additionally, it highlights the accountability of officials involved in project implementation, reinforcing existing administrative sanctions for non-compliance or delays. The order supersedes previous guidelines and is effective immediately.
Law Information
- Reference Number
- DPWH Department Order No. 008-12
- Date Enacted
- Category
- Other Rules and Procedures
- Subcategory
- Department of Public Works and Highways
- Jurisdiction
- Philippines
- Enacting Body
- Congress of the Philippines
Full Law Text
February 21, 2012
DPWH DEPARTMENT ORDER NO. 008-12
| SUBJECT | : | Implementation of the Document Tracking System (DoTS) for the Procurement of Goods |
In line with the Department's thrust to fast track the procurement of goods and to be more transparent in its operations, all offices involved in the processing of documents in the procurement of goods, intended for the different offices of the Department, shall utilize the Document Tracking System (DoTS). aCHDST
The following documents shall be covered by the System:
1. Project Procurement Management Plan (PPMP)
2. Annual Procurement Plan (APP)
3. Purchase Request (PR) TEAcCD
4. Agency Purchase Request (APR)
5. Resolution of Award (ROA)
6. Purchase Order (PO)/Contract
7. Notice of Award (NOA)/Notice to Proceed (NTP) DTEAHI
8. Disbursement Voucher (DV) for Regular Procurement
9. Disbursement Voucher (DV) for Reimbursement
10. Payment of Essential Services
Goods shall refer to all items, supplies, materials and general support services, except civil works projects and consulting services, which may be needed in the transaction of public business. cTaDHS
All documents covered shall be registered in the DoTS. Consequently, all requesting offices shall submit their DoTS documents to the DoTS Center which shall register the document into the DoTS and forward the same to the concerned processing office. All Services/Bureaus/PMOs shall inform their Supply Officers of this procedure and documents without the DoTS header will be returned to the requesting office without action. In the flow of documents from one implementing/processing office to another, the one sending the document is responsible in ensuring that the said document is received by the concerned receiving office.
The processing of documents shall be undertaken by the concerned offices in accordance with the activity and prescribed time contained in Annex A. The implementing guidelines are contained in Annex B and the checklists of required supporting documents and attachments are contained in Annex C.
The Memorandum dated 19 January 2004 which provides for "Additional Guidelines on the Imposition of Administrative Sanctions on Erring DPWH Officials and Employees Involved in Project Implementation and Processing of Project Documents" (Annex D) shall be strictly observed in the implementation of the DoTS.
The DoTS Evaluation Committee created under Special Order No. 70, Series of 2007, is hereby authorized to make necessary changes in the annexes hereof in coordination with the implementing offices. cHTCaI
This Order supersedes Department Order No. 56 Series of 2008 and takes effect immediately.
(SGD.) ROGELIO L. SINGSONSecretaryDepartment of Public Works and Highways
ATTACHMENT
POLICY IMPACT ANALYSIS
This analysis assists policy-makers in assessing whether:
a) the risk or value of the proposed policy is sufficient to warrant the dedication of resources needed to implement and maintain compliance with the proposed policy; and,
b) the intended objective and goal will be accomplished more effectively and efficiently through this policy relative to other means. EScAID
| a) | Proposed Title of Department Order (DO) | |||||||
| Implementation of the Document Tracking System (DoTS) for the Procurement of Goods | ||||||||
| b) | Rationale and Purpose of the proposed DO | |||||||
| Incorporate payment of essential services (e.g., Maynilad, Meralco) and the Authorities delegated to the | ||||||||
| Assistant Secretary for Support Services. | ||||||||
| c) | Nature of proposed DO | new | [ ] | modification | [X] | elimination | [ ] | |
| d) | If new: State the related laws or executive or administrative orders that trigger the formulation of this | |||||||
| policy. | ||||||||
| e) | If modification: State the existing policies and the specific section to be modified. | |||||||
| D.O. No. 56 Series of 2008, Implementation of the Document Tracking System (DoTS) for the | ||||||||
| Procurement of Goods | ||||||||
| Annex A : DoTS Goods System Prescribed Time | ||||||||
| f) | If elimination: State the existing policies to be eliminated. | |||||||
|
Risk Assessment
|
||||||||
| g) | Is there a law that requires the formulation, | yes | [ ] | no | [x] | |||
| modification and elimination of this DO? | ||||||||
| h) | Does this DO help us implement the law? | yes | [ ] | no | [x] | |||
| i) | In the absence of the proposed policy: | |||||||
| • | What is the likelihood that unwanted behavior will occur? | high | [ ] | medium | [x] | low | [ ] | |
| • | What is the severity of financial consequences? | high | [ ] | medium | [x] | low | [ ] | |
| • | What is the severity of consequences vis-à-vis gender, | high | [ ] | medium | [x] | low | [ ] | |
| environment, social) | ||||||||
| • | What is the severity of health and safety consequences? | high | [ ] | medium | [ ] | low | [x] | |
| • | What is the severity of management and operational | high | [x] | medium | [ ] | low | [ ] | |
| consequences? | ||||||||
| • | What is the overall risk if this policy did not exist? | high | [x] | medium | [ ] | low | [ ] | |
| j) | If answered high or medium to any of the above questions, please provide explanation supported with | |||||||
| analysis such as shadow pricing, Pareto, SWOT, etc. | ||||||||
| Affects processing of documents in the department, by tracking down slow moving documents and | ||||||||
| pinpoint who is responsible for the delay. This will result to transparency and expedite document | ||||||||
| processing. | ||||||||
| k) | Other factors driving the need for this policy (cite recent incidents that prompted the request for this | |||||||
| proposed policy) | ||||||||
| Complaints were received with regards to the processing of billing in the department. | ||||||||
| l) | Does the proposed policy (indicate Yes or No) | |||||||
| a. | Comply with related DPWH policies? | yes | [x] | no | [ ] | |||
| b. | Comply with related Executive Orders/Administrative Orders? | yes | [ ] | no | [x] | |||
| c. | Impact existing policies? | yes | [x] | no | [ ] | |||
| d. | Impact other relevant areas/sectors? | yes | [x] | no | [ ] | |||
| m) | Keywords: DoTS, Goods, Document, Tracking | |||||||
| n) | Category: Procurement, Billing | |||||||
| Note: Please use additional sheet(s) if needed. |
ANNEX A
DoTS GOODS SYSTEM PRESCRIBED TIME
|
Project Procurement Management Plan (PPMP)
|
|
|
|
|
|
|
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
| Prepare Final PPMP within Budget Allocation | End User |
7
|
| as provided by the CFMS |
|
|
| Review and Process | CFMS |
1
|
| Review and Process | CPO |
14
|
| Approve | BAC Chairman |
2
|
| Issue Approved PPMP to End User | CPO |
2
|
|
––
|
||
| Total |
26
|
|
|
==
|
||
|
Annual Procurement Plan (APP)
|
|
|
|
|
|
|
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
|
|
||
| Consolidate Approved PPMP and prepare Final APP | CPO |
15
|
| Recommend Approval | BAC Chairman |
1
|
| Approve | USEC for Support |
|
| Services |
2
|
|
| Issue Approved APP to GPPB, CFMS and DBM-PS | CPO |
2
|
|
––
|
||
| Total |
20
|
|
|
==
|
||
| Updated Project Procurement Management Plan (U-PPMP) |
|
|
|
|
||
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
|
|
||
| Review and Process | CFMS |
1
|
| Review and Process | CPO |
14
|
| Approve | BAC Chairman |
2
|
| Issue Approved PPMP to End User | CPO |
2
|
|
––
|
||
| Total |
19
|
|
|
==
|
||
| Updated Annual Procurement Plan (U-APP) |
|
|
| Activity | Office |
Prescribed Time
|
|
(wd)
|
||
|
|
||
| Consolidate Approved PPMP and prepare Final APP | CPO |
15
|
| Recommend Approval | BAC Chairman |
1
|
| Approve | USEC for Support |
2
|
| Services |
|
|
| Issue Approved APP to GPPB, CFMS and DBM-PS | CPO |
2
|
|
––
|
||
| Total |
20
|
|
|
==
|
Purchase Request/Agency Purchase Request for Common Supplies and Equipment Available in PS-DBM
|
Activity
|
Office
|
Prescribed Time
|
||
|
|
|
(wd)
|
||
|
|
|
50T
|
3M
|
Above
|
|
|
|
|
|
3M
|
| Review PR and APR against approved APP, Sign PR and | CPO |
4
|
4
|
4
|
| APR CcHDaA |
|
|
|
|
| Recommend Approval/Approve PR | AMMS Director |
2
|
2
|
2
|
| Recommend Approval/Approve PR | ASEC for Support |
NA
|
3
|
2
|
| Services |
|
|
|
|
| Recommend Approval | USEC for Support |
NA
|
NA
|
2
|
| Services |
|
|
|
|
| Approve PR | Secretary |
NA
|
NA
|
3
|
| Prepare, Process and Sign ObR and Sign APR | CFMS |
4
|
4
|
4
|
| Approve APR | ASEC for Support |
3
|
3
|
3
|
| Services |
|
|
|
|
| Prepare and Sign DV | AMMS |
4
|
4
|
4
|
| Process and Sign DV, Issue Check | CFMS |
6
|
6
|
6
|
| Serve approved APR with Pre-Payment Check to PS-DBM | AMMS |
3
|
3
|
3
|
|
––
|
––
|
––
|
||
| Total |
26
|
29
|
33
|
|
|
==
|
==
|
==
|
Purchase Request (PR)/Purchase Order(PO) for Non-Common Goods Costing not more than P500T (Alternative Method) for Non-Exclusive Distributorship
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
|
(wd)
|
|
|
|
|
50T
|
500T
|
| Review PR against approved APP, Sign and Process | CPO |
4
|
4
|
| Recommend Approval/Approve PR | AMMS Director |
2
|
1
|
| Recommend Approval/Approve PR | ASEC for Support |
NA
|
3
|
| Services |
|
|
|
| Prepare ITB, Canvass and Sign ITB, Advertise, Prepare | CPO |
32
|
32
|
| Notice of Bid Opening, Open Bids, Deliberate, Prepare |
|
|
|
| and Sign Resolution of Award and Prepare PO |
|
|
|
| Review PO and Prepare and Sign ObR Letter Request | End User |
2
|
2
|
| Prepare and Sign ObR and CAF | CFMS |
4
|
4
|
| Approve PO | USEC for Support |
3
|
3
|
| Services |
|
|
|
| Prepare Notice of Award(NOA) | CPO |
3
|
3
|
| Sign NOA | ASEC for Support |
3
|
3
|
| Services |
|
|
|
| Serve NOA to Supplier | CPO |
3
|
3
|
|
––
|
––
|
||
| Total |
56
|
58
|
|
|
==
|
==
|
Purchase Request (PR)/Purchase Order(PO) for Non-Common Goods Costing not more than P500T (Alternative Method) for Exclusive Distributorship
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
|
(wd)
|
|
|
|
|
50T
|
500T |
| Review PR against approved APP, Sign and Process | CPO |
4
|
4
|
| Approve PR/Recommend Approval | AMMS Director |
2
|
1
|
| Approve PR | ASEC for Support |
NA
|
3
|
| Services |
|
|
|
| Prepare and Sign Resolution of Award and Prepare PO | CPO |
15
|
15
|
| Review PO and Prepare and Sign ObR Letter Request | End User |
2
|
2
|
| Prepare and Sign ObR and CAF | CFMS |
4
|
4
|
| Approve PO | USEC for Support |
3
|
3
|
| Services cdll |
|
|
|
| Prepare Notice of Award | CPO |
3
|
3
|
| Sign NOA | ASEC for Support |
3
|
3
|
| Services |
|
|
|
| Serve NOA to Supplier | CPO |
3
|
3
|
|
––
|
––
|
||
| Total |
39
|
41
|
|
|
==
|
==
|
Purchase Request (PR) for Goods through Public Bidding
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
|
(wd)
|
|
|
|
|
3M
|
Above
|
|
|
|
|
3M
|
| Review PR against approved APP, Sign and Process | CPO |
3
|
3
|
| Sign PR | AMMS Director |
2
|
2
|
| Approve PR/Recommend Approval | ASEC for Support |
3
|
1
|
| Services |
|
|
|
| Recommend Approval | USEC for Support |
NA
|
1
|
| Services |
|
|
|
| Approve PR | Secretary |
NA
|
3
|
| Prepare Bid Documents, Advertise, Prepare Notice of | CPO |
26
|
26
|
| Bid Opening, Deliberate, Prepare Resolution of Award, |
|
|
|
| Sign and Recommend Approval |
|
|
|
| Approve ROA/Recommend Approval | USEC for Support |
2
|
1
|
| Services |
|
|
|
| Approve ROA | Secretary |
NA
|
3
|
| Prepare Notice of Award (NOA) | CPO |
3
|
3
|
| Sign NOA | USEC for Support |
2
|
1
|
| Services |
|
|
|
| Sign NOA | Secretary |
NA
|
1
|
| Serve NOA to Supplier and Furnish End User a copy | CPO |
1
|
1
|
| Prepare Contract and Prepare and Sign ObR Letter | End User |
7
|
7
|
| Request EaCSHI |
|
|
|
| Prepare and Sign ObR and CAF | CFMS |
4
|
4
|
| Approve Contract/Recommend Approval | USEC for Support |
1
|
1
|
| Services |
|
|
|
| Approve Contract | Secretary |
NA
|
1
|
| Prepare and process Notice to Proceed (NTP) | End User |
1
|
1
|
| Sign NTP | ASEC for Support |
3
|
1
|
| Services |
|
|
|
| Sign NTP | USEC for Support |
NA
|
2
|
| Services |
|
|
|
| Issue Contract and NTP | End User |
2
|
2
|
|
––
|
––
|
||
| Total |
60
|
65
|
|
|
==
|
==
|
Disbursement Voucher (DV) for Procurement of Non-Common Goods
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
| Receive Delivery Receipt (DR)/Invoice, Prepare Request | AMMS |
4
|
| for Inspection, Inspect, Prepare and Sign Inspection and |
|
|
| Acceptance Report (IAR) |
|
|
| Inspect and Sign IAR | CFMS |
2
|
| Prepare Requisition Issuance Slip (RIS) and Issue Goods | AMMS |
3
|
| to End User |
|
|
| Accept Goods, Sign RIS and Submit Waste Material (If |
|
|
| Applicable) | End User |
3
|
| Prepare and Sign DV | AMMS |
4
|
| Process, Sign DV and Issue Check to Supplier | CFMS |
8
|
|
––
|
||
| Total |
24
|
|
|
==
|
Disbursement Voucher (DV) for Reimbursement (Office Supplies & Equipment)
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
| Conduct inspection, Prepare and sign IAR | AMMS |
2
|
| Conduct inspection and sign IAR | CFMS |
2
|
| Prepare DV and attach supporting documents | End User |
2
|
| Process and Sign DV | CFMS |
6
|
| Approve DV | End User Director |
2
|
| Prepare and issue Check | CFMS |
2
|
|
––
|
||
| Total |
16
|
|
|
==
|
Disbursement Voucher (DV) for Reimbursement (Service Vehicle Parts)
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
| Conduct inspection and Prepare and sign IAR | BOE |
2
|
| Prepare DV and attach supporting documents | End User |
2
|
| Process and Sign DV | CFMS |
6
|
| Approve DV | End User Director |
2
|
| Prepare and issue Check | CFMS |
2
|
|
––
|
||
| Total |
14
|
|
|
==
|
Payment of Essential Services
|
Activity
|
Office
|
Prescribed Time
|
|
|
|
(wd)
|
|
|
|
|
| Prepare, process and sign Request of ObR, DV and Graph | AMMS (for |
4
|
| Water and |
|
|
| Electricity) |
|
|
| MIS (for |
|
|
| Telephone |
|
|
| trunk line, |
|
|
| Internet and |
|
|
| Leased Lines) |
|
|
| Head of |
|
|
| Offices |
|
|
| (NDD/IDD) |
|
|
| Prepare, Process and Sign ObR and DV | CFMS |
5
|
| Approve DV | AMMS (for |
2
|
| Water and |
|
|
| Electricity) |
|
|
| MIS (for |
|
|
| Telephone |
|
|
| trunk line, |
|
|
| Internet and |
|
|
| Leased Lines) |
|
|
| Head of |
|
|
| Offices |
|
|
| (NDD/IDD) |
|
|
| Prepare and issue Check | CFMS |
2
|
|
––
|
||
| Total |
13
|
|
|
==
|
ANNEX B
DoTS IMPLEMENTING GUIDELINESImplementing/Processing Offices
| Project Procurement Management Plan (PPMP) | ||
|
Doer
|
Activity
|
|
| CFMS | 1. | Send approved budget allocation (e-copy) to the DoTS |
| Center. | ||
| DoTS Center | 2. | Create PPMP transaction in DoTS for all End Users |
| (Heads of Offices). | ||
| 3. | Forward approved budget allocation to all End Users | |
| (Heads of Offices). | ||
| 4. | Print DoTS Header and forward it to all End Users. | |
| End User | 5. | Prepare Final PPMP within Budget Allocation as |
| provided by the CFMS. | ||
| 6. | Process and Sign PPMP. | |
| 7. | Forward PPMP to CFMS. | |
| CFMS | 8. | Evaluate PPMP and sign. |
| 9. | Forward PPMP to CPO. | |
| CPO | 10. | Process, Record and Sign PPMP. |
| 11. | Submit the PPMP to the BAC Chairman. | |
| BAC Chairman | 12. | Approve PPMP. |
| 13. | Forward the document to the CPO. | |
| CPO | 14. | Forward approved PPMP to End User. |
| End User | 15. | Close the transaction in the DoTS. |
| Annual Procurement Plan (APP) | ||
|
Doer
|
Activity
|
|
| DoTS Center | 1. | Verify completeness of Approved PPMP. |
| 2. | Create APP transaction in DoTS. | |
| 3. | Print DoTS Header and submit to the CPO. | |
| CPO | 4. | Consolidate approved PPMP and Prepare Final APP in |
| accordance with the approved budget allocation. | ||
| 5. | Attach DoTS Header, process and Sign APP. | |
| 6. | Submit the APP to the BAC Chairman. | |
| BAC Chairman | 7. | Initial and forward the APP to the Office of the |
| Undersecretary for Support Services. | ||
| Undersecretary for | 8. | Review and approve APP. |
| Support Services | ||
| 9. | Forward the document to the CPO. | |
| CPO | 10. | Issue Approved APP to GPPB, CFMS and DBM-PS. |
| DoTS Center | 11. | Close the transaction in the DoTS. |
| Updated Project Procurement Management Plan (U-PPMP) | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare U-PPMP within Budget Allocation as provided |
| by the CFMS and submit to the DoTS Center. | ||
| DoTS Center | 2. | Check completeness of SDs. |
| 3. | Register U-PPMP into DoTS. | |
| 4. | Print and attach DoTS Header. | |
| 5. | Forward U-PPMP to CFMS. | |
| CFMS | 6. | Evaluate U-PPMP and sign. |
| 7. | Forward U-PPMP to CPO. | |
| CPO | 8. | Process, Record and Sign U-PPMP. |
| 9. | Submit U-PPMP to the BAC Chairman. | |
| BAC Chairman | 10. | Approve U-PPMP. |
| 11. | Forward the document to the CPO. | |
| CPO | 12. | Furnish End User with approved. |
| DoTS Center | 13. | Close the transaction in the DoTS. |
| Updated Annual Procurement Plan (U-APP) | ||
|
Doer
|
Activity
|
|
| DoTS Center | 1. | At the third week of March, June, September and |
| December, verify completeness of Approved U-PPMP. | ||
| 2. | Create U-APP transaction in DoTS. | |
| 3. | Print DoTS Header and submit to the CPO. | |
| CPO | 4. | Consolidate approved U-PPMP if any and Prepare Final |
| U-APP in accordance with the approved budget | ||
| allocation. | ||
| 5. | Attach DoTS Header, Process and Sign U-APP. | |
| 6. | Submit the U-APP to the BAC Chairman. | |
| BAC Chairman | 7. | Initial and forward the U-APP to the Office of the |
| Undersecretary for Support Services. | ||
| Undersecretary for | 8. | Review and approve U-APP. |
| Support Services | ||
| 9. | Forward the document to the CPO. | |
| CPO | 10. | Issue Approved U-APP to GPPB, CFMS and DBM-PS. |
| DoTS Center | 11. | Close the transaction in the DoTS. |
| Purchase Request (PR)/Agency Purchase Request (APR) for Common Supplies and Equipment Available in PS-DBM | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare PR, ObR Letter Request, APR and Supporting |
| Documents (SDs) and submit to the DoTS Center. | ||
| DoTS Center | 2. | Check completeness of SDs. |
| 3. | Register PR into DoTS. | |
| 4. | Print DoTS Header and attach to the PR. | |
| 5. | Forward the documents to the CPO. | |
| CPO | 6. | Review PR and APR against approved APP. |
| 7. | Sign PR and APR. | |
| 8. | Forward the documents to the office of the AMMS | |
| Director. | ||
| AMMS Director | 9. | Approve PR amounting up to P50T. |
| 10. | For PR above P50T up to P3M and APR, Initial and | |
| forward the documents to the Office of the Assistant | ||
| Secretary for Support Services. | ||
| Assistant Secretary for | 11. | Approve PR amounting to 3M. |
| Support Services | ||
| 12. | For PR above P3M and APR, Initial and forward the | |
| documents to the Office of the Undersecretary for | ||
| Support Services. | ||
| Undersecretary for | 13. | For PR above P3M, Initial and forward the documents to |
| Support Services | the Office of the Secretary for Approval. | |
| Secretary | 14. | For PR above P3M, Approve and forward the documents |
| to the CFMS. | ||
| CFMS | 15. | Prepare, Process and Sign ObR. |
| 16. | Sign APR. | |
| 17. | Forward the documents to the Office of the Assistant | |
| Secretary for Support Services. | ||
| Assistant Secretary for | 18. | Approve APR. |
| Support Services | ||
| 19. | Return the documents to the AMMS (SPMD). | |
| AMMS | 20. | Prepare and sign DV. |
| 21. | Forward the documents to the CFMS. | |
| CFMS | 22. | Process and sign DV, issue check remit to LBP. |
| 23. | Forward the documents to the AMMS (SPMD). | |
| AMMS | 24. | Close transaction in the DoTS. |
| Purchase Request (PR)/Purchase Order (PO) for Non-Common Goods Costing not more than P500T (Alternative Method) for Non-Exclusive Distributorship | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare PR and Supporting Documents (SDs) and submit |
| to the DoTS Center. | ||
| DoTS Center | 2. | Check completeness of SDs. |
| 3. | Register PR into DoTS. | |
| 4. | Print DoTS Header and attach to the PR. | |
| 5. | Forward the documents to the CPO. | |
| CPO | 6. | Review PR against the approved APP. |
| 7. | Sign PR. | |
| 8. | Forward the documents to the office of the AMMS | |
| Director. | ||
| AMMS Director | 9. | Approve PR amounting up to P50T. |
| 10. | For PR above P50T up to P500T, Initial and forward the | |
| documents to the Office of the Assistant Secretary for | ||
| Support Services. | ||
| Assistant Secretary for | 11. | Approve PR. |
| Support Services | ||
| 12. | Return approved PR and SDs to the CPO. | |
| CPO | 13. | Prepare Invitation to Bid (ITB). |
| 14. | Canvass. | |
| 15. | Sign/Initial ITB. | |
| 16. | Advertise. | |
| 17. | Prepare Notice of Bid Opening. | |
| 18. | Open bids and deliberate. | |
| 19. | If Bidding failed twice, go to Step 39. | |
| 20. | If Bid is Greater than ABC, go to Step 39. | |
| 21. | Prepare and sign Resolution of Award (ROA). | |
| 22. | Prepare PO. | |
| 23. | Forward the documents to the End User. | |
| End User | 24. | Review and process PO. |
| 25. | Prepare and sign ObR Letter Request. | |
| 26. | Forward PO and ObR Letter Request to the CFMS. | |
| CFMS | 27. | Prepare and Sign ObR and CAF. |
| 28. | Forward the documents to the Office of the | |
| Undersecretary for Support Services. | ||
| Undersecretary for | 29. | Approve PO. |
| Support Services | ||
| 30. | Return documents to the CPO | |
| CPO | 31. | Prepare and Sign Notice of Award (NOA). |
| 32. | Forward the documents to the Office of the Assistant | |
| Secretary for Support Services. | ||
| Assistant Secretary for | 33. | Sign NOA. |
| Support Services | ||
| 34. | Return documents to the CPO. | |
| CPO | 35. | Serve NOA. |
| 36. | Close the transaction in the DoTS upon completion of | |
| the process. | ||
| Purchase Request (PR)/Purchase Order (PO) for Non-Common Goods Costing not more than P500T (Alternative Method) for Exclusive Distributorship | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare PR and Supporting Documents (SDs) and submit |
| to the DoTS Center. | ||
| DoTS Center | 2. | Check completeness of SDs. |
| 3. | Register PR into DoTS. | |
| 4. | Print DoTS Header and attach to the PR. | |
| 5. | Forward the documents to the CPO. | |
| CPO | 6. | Review PR against the approved APP. |
| 7. | Sign PR. | |
| 8. | Forward the documents to the office of the AMMS | |
| Director. | ||
| AMMS Director | 9. | Approve PR amounting up to P50T. |
| 10. | For PR above P50T up to P500T, Initial and forward the | |
| documents to the Office of the Assistant Secretary for | ||
| Support Services. | ||
| Assistant Secretary for | 11. | Approve PR. |
| Support Services | ||
| 12. | Forward the documents to the CPO. | |
| CPO | 13. | Prepare and sign Resolution of Award (ROA). |
| 14. | Prepare PO. | |
| 15. | Forward the PO to the End User. | |
| End User | 16. | Review and process PO. |
| 17. | Prepare and sign ObR Letter Request. | |
| 18. | Forward PO and ObR Letter Request to the CFMS. | |
| CFMS | 19. | Prepare and Sign ObR and CAF. |
| 20. | Forward the documents to the Office of the | |
| Undersecretary for Support Services. | ||
| Undersecretary for | 21. | Approve PO. |
| Support Services | ||
| 22. | Return documents to the CPO. | |
| CPO | 23. | Prepare and Sign Notice of Award (NOA). |
| 24. | Forward the documents to the Office of the Assistant | |
| Secretary for Support Services. | ||
| Assistant Secretary for | 25. | Sign NOA. |
| Support Services | ||
| 26. | Return documents to the CPO. | |
| CPO | 27. | Serve NOA to Supplier. |
| 28. | Close the transaction in the DoTS upon completion of | |
| the process. | ||
| Purchase Request (PR) for Goods through Public Bidding | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare PR and Supporting Documents (SDs) and submit |
| to the DoTS Center. | ||
| DoTS Center | 2. | Check completeness of SDs. |
| 3. | Register PR into DoTS. | |
| 4. | Print DoTS Header and attach to the PR. | |
| 5. | Forward the documents to the CPO. | |
| CPO | 6. | Review PR against approved APP. |
| 7. | Sign PR. | |
| 8. | Forward the documents to the office of the AMMS | |
| Director. | ||
| AMMS Director | 9. | Sign/Initial PR. |
| 10. | Forward PR up to P3M and SDs to the Office of the | |
| Assistant Secretary for Support Services. | ||
| Assistant Secretary for | 11. | Approve PR. |
| Support Services | ||
| 12. | For PR above P3M, initial and forward SDs to the office | |
| of the Undersecretary for Support Services. | ||
| Undersecretary for | 13. | Approve PR. |
| Support Services | ||
| 14. | Forward PR and SDs to the Office of the Secretary. | |
| Secretary | 15. | Approve PR. |
| 16. | Forward approved PR and SDs to the CPO. | |
| CPO | 17. | Prepare Bid Documents. |
| 18. | Conduct Pre-Procurement Conference (optional for | |
| goods costing P2M and below). | ||
| 19. | Advertise Invitation to Apply and Eligibility to Bid | |
| (ITAEB). | ||
| 20. | Issue Bid Documents. | |
| 21. | Prepare Notice for Pre-Bid Conference (optional for | |
| goods costing below P1M). | ||
| 22. | Conduct Pre-Bid Conference (P1M and above). | |
| 23. | Open bids and determine Lowest Complying Bidder | |
| (LCB). | ||
| 24. | Endorse eligibility requirement, technical and financial | |
| proposal and abstract to bids to End User. | ||
| 25. | Deliberate. | |
| 26. | Prepare and sign Resolution of Award (ROA). | |
| 27. | For approved PR up to P3M, forward ROA to the Office | |
| of the Undersecretary for Support Services. | ||
| Undersecretary for | 28. | Approve ROA. |
| Support Services | ||
| 29. | For approved PR above P3M, initial and forward ROA | |
| to the Office of the Secretary. | ||
| Secretary | 30. | Approve ROA. |
| 31. | Forward approved ROA to CPO. | |
| CPO | 32. | Prepare and Sign Notice of Award (NOA). |
| 33. | For NOA up to P3M, forward NOA to the Office of the | |
| Undersecretary for Support Services. | ||
| Undersecretary for | 34. | Approve NOA. |
| Support Services | ||
| 35. | For NOA above P3M, initial and forward NOA to the | |
| Office of the Secretary. | ||
| Secretary | 36. | Approve NOA. |
| 37. | Forward approved NOA to CPO. | |
| CPO | 38. | Serve NOA to Supplier. |
| 39. | Furnish End User a copy of NOA. | |
| End User | 40. | Prepare and process Contract. |
| 41. | Prepare and sign ObR Letter Request. | |
| 42. | Forward the Contract, ObR Letter Request and SDs to | |
| the CFMS. | ||
| CFMS | 43. | Process and sign ObR and CAF. |
| 44. | For Contract up to P3M, forward Contract and SDs to | |
| the Office of the Undersecretary for Support Services. | ||
| Undersecretary for | 45. | Approve Contract. |
| Support Services | ||
| 46. | For Contract above P3M, initial and forward Contract | |
| and SDs to the Office of the Secretary. | ||
| Secretary | 47. | Approve Contract. |
| 48. | Return approved Contract and SDs to End User. | |
| End User | 49. | Prepare and process and sign Notice to Proceed (NTP). |
| 50. | For NTP up to P3M, initial and forward NTP and SDs to | |
| the Office of the Assistant Secretary for Support | ||
| Services. | ||
| Assistant Secretary for | 51. | Approve NTP. |
| Support Services | ||
| 52. | For NTP above P3M, initial and forward NTP and SDs | |
| to the Office of the Undersecretary for Support Services. | ||
| Undersecretary for | 53. | Approve NTP. |
| Support Services | ||
| 54. | Forward NTP to End User. | |
| End User | 55. | Issue Contract and NTP to Supplier. |
| 56. | Close the transaction in the DoTS. | |
| Disbursement Voucher (DV) for Procurement of Non-Common Goods | ||
|
Doer
|
Activity
|
|
| Supplier | 1. | Submit Delivery Receipt (DR)/Invoice to the DoTS |
| Center. | ||
| DoTS Center | 2. | Register DV into DoTS. |
| 3. | Print DoTS Header and attach to the Delivery Receipt | |
| (DR)/Invoice. | ||
| 4. | Forward the DR/Invoice to the AMMS (SPMD). | |
| AMMS | 5. | Receive DR/Invoice, prepare Request for Inspection. |
| 6. | Conduct inspection and Prepare and sign Inspection and | |
| Acceptance Report (IAR). | ||
| 7. | Forward the IAR to the CFMS (ASMCD). | |
| CFMS | 8. | Conduct inspection and sign IAR. |
| 9. | Return IAR to the AMMS (SPMD). | |
| AMMS | 10. | Prepare Requisition Issuance Slip (RIS). |
| 11. | Issue Goods and forward RIS to the End User. | |
| End User | 12. | Accept Goods. |
| 13. | Sign RIS. | |
| 14. | Return RIS and Submit Waste Material Report (if | |
| applicable) to the AMMS (SPMD). | ||
| AMMS | 15. | Prepare and sign DV. |
| 16. | Forward DV to the CFMS. | |
| CFMS | 17. | Process, sign DV and issue Check to Supplier. |
| 18. | Close the transaction in the DoTS. | |
| Disbursement Voucher (DV) for Reimbursement (Office Supplies and Equipment) | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare and submit request for Inspection report signed |
| by End User and Delivery Receipt (DR)/Invoice to the | ||
| DoTS Center. | ||
| DoTS Center | 2. | Register DV into DoTS. |
| 3. | Print DoTS Header and attach to the End User request | |
| for inspection report and Delivery Receipt (DR)/Invoice. | ||
| 4. | Forward the request for Inspection report and Delivery | |
| Receipt (DR)/Invoice to the AMMS (SPMD). | ||
| AMMS | 5. | Conduct inspection and Prepare and sign Inspection and |
| Acceptance Report (IAR). | ||
| 6. | Forward the IAR to the CFMS (ASMCD). | |
| CFMS | 7. | Conduct inspection and sign IAR. |
| 8. | Return IAR to AMMS (SPMD). | |
| 9. | Issue Post Inspection and Acceptance Report and History | |
| of Repair to the End User. | ||
| End User | 10. | Prepare DV and attach SDs. |
| 11. | Forward document/s including of at least three (3) | |
| canvass from reputable suppliers (for items amounting | ||
| more than P1,000 per invoice) to the AMMS (SPMD). | ||
| CFMS | 12. | Process and Sign DV. |
| 13. | Forward DV to the office of the office of the AMMS | |
| Director. | ||
| End User Director | 14. | Approve DV. |
| 15. | Forward approved DV to CFMS. | |
| CFMS | 16. | Prepare and issue Check to End User. |
| 17. | Close the transaction in the DoTS. | |
| Disbursement Voucher (DV) for Reimbursement (Service Vehicle Parts) | ||
|
Doer
|
Activity
|
|
| End User | 1. | Prepare and submit request for Inspection report signed |
| by End User and supporting documents (SDs) to the | ||
| DoTS Center. | ||
| DoTS Center | 2. | Check completeness of Supporting Documents (SDs) |
| and attachments. | ||
| 3. | Register DV into DoTS. | |
| 4. | Print DoTS Header and attach to the End User request | |
| for inspection report. | ||
| 5. | Forward the document to the BOE (CESPD). | |
| BOE | 6. | Conduct inspection. |
| 7. | Prepare and sign Post Repair Inspection Report. | |
| 8. | Issue Post Inspection and Acceptance Report and History | |
| of Repair to the End User. | ||
| End User | 9. | Prepare DV and attach supporting documents. |
| 10. | Forward document/s including of at least three (3) | |
| canvass from reputable suppliers (for items amounting | ||
| more than P1,000 per invoice) to the CPO | ||
| CFMS | 11. | Process and Sign DV. |
| 12. | Forward DV to the office of the AMMS Director. | |
| End User Director | 13. | Approve DV. |
| 14. | Forward approved DV to CFMS. | |
| CFMS | 15. | Prepare and issue Check to End User. |
| 16. | Close the transaction in the DoTS. | |
| Payment of Essential Services | ||
|
Doer
|
Activity
|
|
| Service Provider | 1. | Submit Bill to the DoTS Center. |
| DoTS Center | 2. | Register the Bill into DoTS. |
| 3. | Print and attach the DoTS Header. | |
| 4. | Submit the Bill to the AMMS for processing. | |
| AMMS | For Water and Electricity | |
| 5. | Prepare, process and sign Request of ObR, DV and | |
| Graph. | ||
| 6. | Process bills. | |
| 7. | Forward the documents to the CFMS. | |
| MIS | For Telephone Trunk Line, Internet and Leased Lines | |
| 5. | Prepare, process and sign Request of ObR, and DV. | |
| 6. | Process bills. | |
| 7. | Forward the documents to the CFMS. | |
| Head of Offices | For Long Distance Calls | |
| 5. | Prepare, process and sign Request of ObR, and DV. | |
| 6. | Process bills. | |
| 7. | Forward the documents to the CFMS. | |
| CFMS | 8. | Prepare process and Sign ObR. |
| 9. | Process and Sign DV. | |
| 10. | Forward DV, ObR and other documents to the office of | |
| the AMMS Director. | ||
| AMMS/MIS/Head of | 11. | Approve DV. |
| Offices | ||
| 12. | Forward approved DV to CFMS. | |
| CFMS | 13. | Prepare and issue Check to the Billing Company. |
| 14. | Close the transaction in the DoTS. |
ANNEX C-1
CHECKLIST OF SUPPORTING DOCUMENTS AND ATTACHMENTS FOR DoTS
| Purchase Request (PR) | |||
| I. | New Procurement | ||
| A. | Goods and Services | ||
| [ ] | 1. | Approved Annual Procurement Plan (APP) — copy of specific pages where | |
| items are listed/indicated | |||
| [ ] | 2. | Project Procurement Management Plan (PPMP) | |
| [ ] | 3. | Budget Earmarking fund allocation (Capital Outlay) from Budget Division | |
| (above 110T) | |||
| [ ] | 4. | Authority from DBM/OP (above 10T per single equipment) | |
| B. | Additional Requirements for the following . . . | ||
| a. | Concurrence of the Lending Institution on the Rankings | ||
| [ ] | 1. | MIS Evaluation Certification/approved specification | |
| b. | Aircon | ||
| [ ] | 1. | Installation Layout with specific measurement | |
| c. | Other Equipment (for Exclusive Distributor) | ||
| [ ] | 1. | Original Price Quotation | |
| [ ] | 2. | Clear copy of Certificate of Sole/Exclusive Distributorship duly | |
| authenticated by the Philippine Consulate from country origin | |||
| II. | Repair and Maintenance | ||
| A. | Land, Aircraft and Water Equipment/Service Vehicle, Building and Other Equipment | ||
| [ ] | 1. | Approved Annual Procurement Plan (APP) — copy of specific pages where | |
| items are listed/indicated | |||
| [ ] | 2. | Project Procurement Management Plan (PPMP) | |
| [ ] | 3. | Budget Earmarking fund allocation from Budget Division (above 100T) | |
| [ ] | 4. | Certified True Copy of Acknowledgement Receipt of Equipment (ARE) | |
| B. | Additional Requirements for the following . . . | ||
| a. | Land, Aircraft and Water Equipment/Service Vehicle | ||
| [ ] | 1. | Original Copy of Job Order (BOE) | |
| [ ] | 2. | Original or Certified True Copy of History of Repair (BOE) | |
| [ ] | 3. | Certified True Copy of Vehicle Registration | |
| [ ] | 4. | Original Copy of Certification that the Vehicle is included in the | |
| Department Inventory of Vehicle (BOE) | |||
| b. | ICT Equipment | ||
| [ ] | 1. | IT HelpDesk Certification/Evaluation Report | |
| [ ] | 2. | Pre-Inspection Report (SPMD) | |
| c. | Aircon | ||
| [ ] | 1. | Spot Inspection Report by Facilities and Maintenance Division (FMD) | |
| [ ] | 2. | Pre-Inspection Report (SPMD) | |
| d. | Building | ||
| [ ] | 1. | Program of Work and Detailed estimates by FMD | |
| e. | Other Equipment | ||
| [ ] | 1. | Pre-Inspection Report (SPMD) | |
| I hereby certify that the above | |||
| supporting documents are complete | |||
| Print Name: ____________________ | |||
| Designation: ____________________ | |||
| Date: __________________________ |
Disbursement Voucher (DV) for Reimbursement
| I. | Office Supplies, Spare Parts for Motor Vehicle and Other Equipment and Materials for Repair and Maintenance of Building | |
| [ ] | 1. | Disbursement Voucher (DV) |
| [ ] | 2. | Obligation Request (ObR) |
| [ ] | 3. | Inspection and Acceptance Report (IAR) |
| [ ] | 4. | Official Receipt/Sales Invoice |
| [ ] | 5. | Purchase Request (If applicable) |
| [ ] | 6. | Approved Annual Procurement Plan (APP) (If applicable) |
| [ ] | 7. | Project Procurement Management Plan (PPMP) (If applicable) |
| [ ] | 8. | Quotation from at least 3 suppliers (per Invoice Receipt Costing above 1K) |
| [ ] | 9. | Certificate of Emergency Purchase |
| II. | Additional Requirements on Spare Parts for Motor Vehicle and other Equipment | |
| [ ] | 1. | Approved Job Order/Post Inspection Report |
| [ ] | 2. | Approved Waste Material Report |
| [ ] | 3. | History of Repair |
| [ ] | 4. | Certified True Copy of Acknowledgement Receipt of Equipment (ARE) |
| [ ] | 5. | Certified True Copy of current LTO Registration |
| [ ] | 6. | Certification that the vehicle is included in the Department Inventory of |
| Vehicle | ||
| III. | Additional Requirements for the following . . . | |
| A. | ICT Equipment | |
| [ ] | 1. | MIS Spot Report |
| [ ] | 2. | SPMD-AMMS Pre-Inspection Report |
| [ ] | 3. | ARE |
| B. | Aircon | |
| [ ] | 1. | FMD-AMMS Spot Report |
| [ ] | 2. | SPMD-AMMS Pre-Inspection Report |
| [ ] | 3. | ARE |
| C. | Other Equipment | |
| [ ] | 1. | SPMD-AMMS Pre-Inspection Report |
| [ ] | 2. | ARE |
| D. | Fuel and Petroleum Products | |
| [ ] | 1. | Driver's Trip Tickets duly accomplished and approved |
| [ ] | 2. | Certification of no fuel withdrawal (BOE) |
| I hereby certify that the above | ||
| supporting documents are complete | ||
| Print Name: ____________________ | ||
| Designation: ____________________ | ||
| Date: __________________________ |
Disbursement Voucher (DV) for Regular Procurement
| I. | Office Supplies, Spare Parts for Motor Vehicle and Other Equipment and Materials for Repair and Maintenance of Building | |
| [ ] | 1. | Disbursement Voucher (DV) |
| [ ] | 2. | Obligation Request (ObR) |
| [ ] | 3. | Inspection and Acceptance Report (IAR) |
| [ ] | 4. | Official Receipt/Sales Invoice |
| [ ] | 5. | Purchase Request/APR |
| [ ] | 6. | Approved Annual Procurement Plan (APP) |
| [ ] | 7. | Project Procurement Management Plan (PPMP) |
| [ ] | 8. | Purchase Order |
| [ ] | 9. | Notice of Award |
| [ ] | 10. | Bid Documents (Quotation, Abstract of Bids and Resolution of Award) |
| [ ] | 11. | Certified True Copy of Submission of Purchase/Work Order to COA- |
| Resident Auditor | ||
| [ ] | 12. | Advertisement (Newspaper and/or Website) * |
| [ ] | 13. | Stock Position Sheet, for single item costing P1000 and above |
| [ ] | 14. | Performance Bond |
| [ ] | 15. | Test Results, for items that are subject to Test |
| II. | Additional Requirements on Spare Parts for Motor Vehicle and other Equipment | |
| [ ] | 1. | Approved Job Order (JO) |
| [ ] | 2. | Approved Waste Material Report (WMR) |
| [ ] | 3. | History of Repair |
| [ ] | 4. | Certified True Copy of Acknowledgement Receipt of Equipment (ARE) |
| [ ] | 5. | Certified True Copy of current LTO Registration |
| [ ] | 6. | Certification that the vehicle is included in the Department Inventory of |
| Vehicle | ||
| III. | Additional Requirements for the following . . . | |
| A. | ICT Equipment | |
| [ ] | 1. | MIS Spot Report |
| [ ] | 2. | SPMD-AMMS Pre-Inspection Report |
| [ ] | 3. | ARE |
| B. | Aircon | |
| [ ] | 1. | FMD-AMMS Spot Report |
| [ ] | 2. | SPMD-AMMS Pre-Inspection Report |
| [ ] | 3. | ARE |
| C. | Other Equipment | |
| [ ] | 1. | SPMD-AMMS Pre-Inspection Report |
| [ ] | 2. | ARE |
| I hereby certify that the above | ||
| supporting documents are complete | ||
| Print Name: ____________________ | ||
| Designation: ____________________ | ||
| Date: __________________________ |
Payments of Essential Services
| I. | Bills | |
| [ ] | 1. | Maynilad Bill |
| [ ] | 2. | Meralco Bill |
| [ ] | 3. | ETPI Bill (Trunk Line) |
| [ ] | 4. | Innove Bill (Internet) |
| [ ] | 5. | ePLDT Bill (Leased Lines) |
| I hereby certify that the above | ||
| supporting documents are complete | ||
| Print Name: ____________________ | ||
| Designation: ____________________ | ||
| Date: __________________________ |
ANNEX D
January 19, 2004
MEMORANDUM
| TO ALL | : | Undersecretaries |
| Assistant Secretaries | ||
| Regional Directors/Asst. Regional Directors | ||
| Bureau Directors/Asst. Bureau Directors | ||
| Project Directors/Asst. Project Directors | ||
| Project Managers/Asst. Project Managers | ||
| District Engineers/Asst. District Engineers | ||
| Division/Section Chiefs | ||
| Others Concerned | ||
| This Department | ||
| SUBJECT | : | Additional Guidelines on the Imposition of Administrative Sanctions on Erring DPWH Officials and Employees Involved in Project Implementation and Processing of Project Documents |
In addition to the administrative offenses with corresponding penalties which are already defined under existing laws and civil service rules and regulations and in order to have consistent guidelines for the imposition of administrative sanctions against erring DPWH officials and employees involved in project implementation and processing of project documents pending the issuance of a Department Order covering sanctions on irresponsible actuations in all phases of the project cycle, from planning to implementation, these guidelines are hereby prescribed. TaCDAH
The guidelines shall cover all DPWH officials and employees involved in project implementation regardless of employment status, whether or not they hold permanent, temporary, contractual, casual in hold-over or officer-in-charge capacity.
1.0 Quality Control
1.1 For Project Engineers, Project Inspectors and Materials Engineers
The sanctions shall be consistent with the guidelines prescribed in the memorandum of then Secretary Gregorio R. Vigilar dated 29 January 1999 (Annex A).
1.2 For Regional Directors, Asst. Regional Directors for Operations, Project Directors, Asst. Project Directors, Project Managers, Asst. Project Managers, District Engineers, Asst. District Engineers and Chiefs of Construction Divisions/Sections of Field Offices. ATaDHC
The sanctions shall be based on the quarterly ratings of quality control performance in project implementation pursuant to Memorandum dated 7 April 1989 as amended by Department Order No. 137, series of 1991. Department Order No. 9, series of 2004, further amends Department Order No. 137 shifting the quality control rating to quarterly.
The following sanctions shall be imposed on the above officials when their implementing office is rated "Unsatisfactory".
a. An Unsatisfactory rating for a quarter — Reprimand.
b. Unsatisfactory rating for two (2) consecutive quarters — Suspension for three (3) months. AaSTIH
The sanction shall be imposed on the Regional Director, Asst. Regional Director for Construction Operations and the Chief of the Construction Division if the implementing office is a Regional Office.
The sanction shall be imposed on the Project Director and Asst. Project Director, or Project Manager and Asst. Project Manager as the case may be, if the implementing office is a Project Management Office.
The sanction shall be imposed on the District Engineer, Asst. District Engineer and the Chief of the Construction Section if the implementing office is a District Office.
Unlike the sanctions for Project Engineers, Project Inspectors and Materials Engineers, the sanctions on the DPWH officials shall not be cumulative. If a reprimand was given on any given quarter and no sanction was given on the succeeding quarter, the sanction for the subsequent quarter will not be suspension but will still be a reprimand. IcTEaC
2.0 Physical Accomplishment
2.1 For Project Engineers and Project Inspectors
A sanction shall be imposed if in any given reporting period:
a) he fails to initiate calibrated actions (in accordance with D.O. 102, series of 1988) on a project/s under his supervision with a negative slippage, and
b) he gets ten (10) points or greater based on the values shown in Table 1.
Table 1
|
Slippage
|
|
Points
|
|
|
|
1 Project
|
2 Projects
|
3 Projects
|
| 5%-10% |
-
|
5
|
10
|
| 11%-15% |
5
|
10
|
15
|
| > 15% |
10
|
15
|
20
|
The calibrated sanction shall be as follows:
1st Offense — Reprimand SAHIDc
2nd Offense — Suspension for six (6) months
3rd Offense — Suspension for one (1) year
2.2 For Heads/Deputies of Implementing Office
A sanction shall be imposed on the Regional Directors, Asst. Regional Directors for Construction Operations, Project Directors, Asst. Project Directors, Project Managers, Asst. Project Managers, District Engineers and Chiefs of Construction Divisions/Sections of Field Offices, if in any given reporting period: cADaIH
a) he fails to institute calibrated actions (in accordance with D.O. 102, series of 1988) on a project/s with negative slippage under his supervision; and
b) he gets ten (10) points or greater based on the values shown in Table 1.
1st Offense — Reprimand
2nd Offense — Suspension for three (3) months cHDaEI
3rd Offense — Suspension for six (6) months
3.0 Maintenance
The sanctions shall be consistent with the guidelines prescribed in Department Order No. 31, series of 2000 (Annex B).
4.0 Documents Processing
The documents referred to in this section are those included in the Documents Tracking System (DoTS) as listed in D.O. No. 273, series of 2003. The sanctions are based on the failure to use the DoTS and/or failure to process documents within the prescribed period. EDcICT
4.1 Non Usage of the DoTS
4.1.1 The calibrated sanction for designated DoTS officers are as follows:
1st Offense — Reprimand
2nd Offense — Suspension for one (1) month
3rd Offense — Suspension for six (6) months AIaSTE
4th Offense — Suspension for one (1) year
4.1.2 The calibrated sanction for heads and deputies of the processing offices are as follows:
1st Offense — Warning
2nd Offense — Reprimand cDECIA
4.2 Processing Exceeded Prescribed Time
The calibrated sanction for failure to process documents within the prescribed time are shown in Table 2.
Table 2
|
|
Offense
|
|
|
|
|
|
|
(Frequency)
|
|
|
|
|
|
|
|
1st Offense
|
2nd Offense
|
3rd Offense
|
4th Offense
|
|
Official
|
|
(3 times)
|
(5 times)
|
(7 times)
|
(More than
|
|
|
|
|
|
|
7 times)
|
| Action Officers | Reprimand | Suspension | Suspension | - | |
| for 6 mos. | for 1 year | ||||
| Division Chiefs/ | Warning | Reprimand | Suspension | Suspension | |
| Section Chiefs/ | for 6 mos. | for 1 year | |||
| Chiefs of Staff | |||||
| Heads of Office | Warning | Reprimand | Suspension | Suspension | |
| (DE/RD/BD/SD/PD) | for 3 mos. | for 6 mos. | |||
| and their Assistants | |||||
| and Action Officers | |||||
| of Asec/Usec/Sec) |
In case a DPWH official or employee was sanctioned simultaneously for quality control, physical accomplishment, maintenance or processing of documents, the heavier penalty shall be imposed. TEacSA
All officials and employees will be required to explain in writing for any violation committed prior to the imposition of sanction, if their explanations are not acceptable.
For your guidance and compliance.
(SGD.) FLORANTE SORIQUEZActing Secretary
Cite This Law
Implementation of the Document Tracking System (DoTS) for the Procurement of Goods, DPWH Department Order No. 008-12, Feb 21, 2012 (Philippines)
Implementation of the Document Tracking System (DoTS) for the Procurement of Goods, DPWH Department Order No. 008-12 (Phil. 2012)
Browse More Other Rules and Procedures
Explore other laws in the Other Rules and Procedures category.
View All Other Rules and ProceduresNeed Help Understanding This Law?
Ask our AI assistant to explain provisions, implications, or related laws.
Ask AI About This Law