Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016
The DILG Memorandum Circular No. 049-16 outlines the implementation guidelines for the Provision of Potable Water Supply under the Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program for the fiscal year 2016. This program aims to provide potable water to poor and waterless communities, promoting sustainable water supply and sanitation services through financial grants and capacity building for Local Government Units (LGUs). The memorandum details the processes for project proposal submission, eligibility assessments, fund management, and monitoring, ensuring compliance with national standards and policies. Additionally, it emphasizes collaboration between various government agencies and outlines penalties for non-compliance by implementing partners. The program is supported by a budget of Php 1.79 billion under the General Appropriations Act for the year.
Quick Answers
- What is Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016 about?
- The DILG Memorandum Circular No. 049-16 outlines the implementation guidelines for the Provision of Potable Water Supply under the Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program for the fiscal year 2016. This program aims to provide potable water to poor and waterless communities, promoting sustainable water supply and sanitation services through financial grants and capacity building for Local Government Units (LGUs). The memorandum details the processes for project proposal submission, eligibility assessments, fund management, and monitoring, ensuring compliance with national standards and policies. Additionally, it emphasizes collaboration between various government agencies and outlines penalties for non-compliance by implementing partners. The program is supported by a budget of Php 1.79 billion under the General Appropriations Act for the year.
- What type of law is DILG Memorandum Circular No. 049-16?
- Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016 (DILG Memorandum Circular No. 049-16) is a Philippine Other Rules and Procedures enacted by the Congress of the Philippines.
- When was Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016 enacted?
- Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016 (DILG Memorandum Circular No. 049-16) was enacted on Apr 6, 2016.
- What is the citation for Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016?
- Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016, DILG Memorandum Circular No. 049-16, Apr 6, 2016 (Philippines)
Law Information
- Reference Number
- DILG Memorandum Circular No. 049-16
- Date Enacted
- Category
- Other Rules and Procedures
- Subcategory
- Department of the Interior and Local Government
- Jurisdiction
- Philippines
- Enacting Body
- Congress of the Philippines
Full Law Text
April 6, 2016
DILG MEMORANDUM CIRCULAR NO. 049-16
GUIDELINES FOR THE IMPLEMENTATION OF THE PROVISION OF POTABLE WATER SUPPLY-SAGANA AT LIGTAS NA TUBIG SA LAHAT (SALINTUBIG) PROGRAM FOR FY 2016
1.0 Background
The Government is continuously implementing the Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program to pursue its commitment to provide water particularly for the poor and waterless communities.
The Program provides grant financing and capacity development to increase access to water and sanitation services and improve capacities of the Local Government Units (LGUs) and Water Service Providers (WSPs), in the planning, implementation and management of water supply facilities in a sustainable manner. Under the Program, Integrated Water, Sanitation and Hygiene are included in the capacity building programs for the day care centers and schools without access to potable water.
The Department of the Interior and Local Government (DILG) through the Office of Project Development Services (OPDS) in partnership with the DILG Regional Offices (ROs) and the target Provinces and Municipalities as implementing partners remains the lead agency for the FY 2016 SALINTUBIG Program.
2.0 Purpose
This Circular provides the policies, processes and responsibilities in the implementation of water supply subprojects which are funded under the Republic Act (RA) 10717 (GAA FY 2016) for the SALINTUBIG Program and shall cover the 446 subprojects in 86 Waterless Municipalities, 214 Waterless Barangays in 129 Municipalities, and 9 Resettlement Sites without access to potable water supply.
3.0 Legislative Compliance
The Program aims to contribute to the attainment of the goal of providing potable water to the entire country and the targets defined in the Philippine Development Plan 2011-2016, Millennium Development Goals (MDG), and the Philippine Water Supply Sector Roadmap and the Philippine Sustainable Sanitation Roadmap.
In December 2010, a Memorandum of Agreement (MOA) outlining joint responsibilities and accountabilities of partner agencies was executed by and between the Department of the Interior and Local Government (DILG), the Department of Health (DOH), and the National Anti-Poverty Commission (NAPC) to implement the administration's priority water and sanitation program for waterless municipalities, the Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program.
The National Government has appropriated in the DILG Budget the amount of Php1,793,150,000 under Republic Act (RA) 10717 (General Appropriations Act (GAA) FY 2016) for the Implementation of the Program.
4.0 Coverage
All concerned DILG Central Office/Regional/Provincial/City Directors, Cluster Heads and City/Municipal Local Government Operation Officers (C/MLGOOs); Provincial Governors, City/Municipal Mayors of concerned LGUs.
5.0 Definitions
For purposes of this Guidelines, the following terminologies shall be technically defined as follows:
a. DILG Fund — refers to National Government appropriation in the General Appropriation Act GY 2016 (RA 10717) under the DILG Budget for the Provision for Potable Water Supply (SALINTUBIG).
b. Georesistivity Study — a field survey that locates areas that have groundwater potential.
c. Implementing Partner — the LGU or any other entity who has the capability and who will be responsible in the preparation of Detailed Engineering Design (DED), procurement, implementation/supervision and evaluation of the subproject.
d. Local Government Units (LGUs) — as provided under the Local Government Code of 1991 or Republic Act No. 7160, assume the primary responsibility for the provision of basic services and facilities and the improvement of quality of life of their constituents.
e. Partner Agency — refers to other agencies such as DPWH, DSWD, Local Water Utilities Administration (LWUA), Water District (WD), Armed Forces of the Philippines — Engineering Brigade and State Universities contracted out by the Implementing Partner to implement the project.
f. Project Management Office (PMO) — refers to the Project Management Office (PMO) established in the DILG under the Office of Project Development Services (OPDS) which shall be responsible for the overall-project management of the SALINTUBIG Program.
g. Proponent LGU — the LGU who has the jurisdiction over the proposed subproject, including the operations and maintenance. The LGU could also be the Implementing Partner provided that the said LGU is eligible and capable to implement the subproject based on the criteria stipulated in Section 6.2.3 of this guidelines.
h. Provincial Technical Working Group (PTWG) — a team organized at the Provincial Level, chaired by the DILG Provincial Director (DILG-PD) with DILG City Director (DILG-CD), Cluster Heads or C/MLGOOs as members and technical staff from DILG-RO, to review/evaluate and approve/disapprove the subproject proposals (SPs) costing Php1Million and below. Representatives from the provincial government may be invited, preferably from the Provincial Engineering Office (PEO) and Provincial Planning and Development Office (PPDO).
i. Potability Test — the physical, chemical and bacteriological examinations of water from newly constructed systems or sources before and during construction and before they are operated and opened for public use.
j. Subprojects — are the eligible individual subprojects which shall be funded under the DILG Fund.
k. Variation Orders — a modification in the scope of works in a construction contract or supply in the form of addition, substitution, or omission from the original scope of works.
l. Waterless Municipalities — refer to communities where more than 50 percent of the population of poor households do not have access to "safe water" and with particularly high incidence of waterborne and sanitation-related diseases. CAIHTE
m. Water Source Validation — confirmation of viability of water source.
6.0 Policy Content and Guidelines
6.1 Fund Sources
6.1.1 DILG Fund
The National Government has appropriated the amount of Php1,512,730,000 in the DILG Budget under the Republic Act 10717 (GAA FY 2016) for the capital investment requirements for the implementation of water supply projects under the Program, herein referred to as DILG Fund.
6.1.2 LGU Counterpart
The Proponent LGU shall provide cash counterpart as reflected in the MOA as mentioned in Section 6.11.1.2.a.i which shall be deposited in the Implementing Partner's Trust Account used for the implementation of the subproject; while both the Proponent LGU and Implementing Partner shall provide in cash and/or in kind counterpart for the implementation of the project as defined in Section 6.11.1.2a.ii-v and Section 6.11.1.2b.
6.2 Eligibility and Capacity Assessment of Implementing Partners
6.2.1 As a general rule, the proponent LGU shall be the Implementing Partner unless it shall be found ineligible to implement the project as defined in the succeeding sections.
6.2.2 Proponent LGU/Implementing Partner shall be considered eligible to implement the subproject if it satisfies the following criteria:
6.2.2.1 Compliant with the Good Financial Housekeeping (GFH), a component of the Seal of Good Local Governance (SGLG) based on the latest available assessment.
6.2.2.2 Capacity to implement the subproject based on the following criteria to be determined by concerned DILG RO:
a. Technical capabilities to implement subprojects
b. Availability of qualified personnel who can manage the subproject
c. Availability of funds for the administrative costs
d. Previous experience in implementing similar subprojects
e. Capacity to implement subprojects through Competitive Bidding or by Administration
f. Capacity to monitor and evaluate subproject implementation
g. Absorptive capacity (capacity to implement additional projects, especially, if there are still on-going projects funded in previous years and/or funded by other agencies)
6.2.2.3 No unliquidated cash transfers six (6) months after the turnover to the Proponent LGU, if by contract and final inspection if by administration, of completed subproject/s from previous funded subprojects under the DILG Fund.
6.2.3 For Proponent LGUs that failed to comply with Section 6.2.2, concerned Provincial Government shall implement the subprojects, provided it has met the conditions mentioned in Section 6.2.2.
6.2.4 DILG Regional Offices (DILG-ROs) shall implement the subprojects where the Proponent LGU and the Provincial Government are ineligible to implement their subprojects or may opt to designate other Implementing Partner.
6.2.5 DILG-RO shall notify in writing (Eligibility Advice-See Annex A) the Proponent LGU whether it is eligible or not to implement the subproject immediately after assessment and the Implementing Partner if it is eligible to implement.
6.3 Subproject Preparation, Review and Approval Processes
6.3.1 Preparation and Submission of Subproject Proposals and Supporting Documents
6.3.1.1 The Proponent LGU shall submit to DILG Provincial Office (DILG-PO), within 45 calendar days upon receipt of the Eligibility Advice from the DILG-RO a Subproject Proposal (SP) a Simplified Feasibility Study (SFS) as shown in Annex B, with the following supporting documents:
a. Basic Supporting Documents:
i. Letter Request — a letter signed by the Local Chief Executive (LCE) submitting the required documents and requesting for the approval of the Simplified Feasibility Study (See Annex C for the format of Letter Request)
ii. Annual Budget or Annual Investment Plan (AIP) showing the budgeted amount for the required cash counterpart for the subproject/s (if any) of the Proponent LGU
iii. Subproject Implementation Schedule showing the activities and timelines for each activity from Detailed Engineering Design preparation up to subproject completion. (See Annex D)
iv. Certification from the Local Treasurer or Bank Certificate of their existing Trust Account for the implementation of the subprojects if the Proponent LGU is the Implementing Partner
(Note: Implementing Partner, which is not the Proponent LGU, shall be required to submit to DILG-RO the Certification from the Local Treasurer or Bank Certificate of the existing Trust Account before MOA Signing.)
b. Subproject Specific Documents:
• Geo-resistivity Study for new construction with underground water source to determine the availability and quantity of the water source.
• Certification from the Municipal Engineer that the source is adequate to serve the intended service area. The Proponent LGU may engage accredited technical service provider to conduct the source validation or they may seek technical assistance from DILG-RO.
• Copy of the receipt issued by the water testing center/laboratory accredited by DOH as proof of conduct water potability test.
6.3.1.2 The DILG-CD or C/MLGOO shall ensure the completeness of the documents before submission to the DILG-PO. In case there are lacking documents, the DILG-CD or C/MLGOO shall immediately notify the Proponent LGU. (See Annex E)
6.3.1.3 All the required documents mentioned in Section 6.3.1.1 shall be submitted to the DILG-PO. The DILG-PD shall:
a. For subproject costing Php1.00 Million and below, convene the Provincial Technical Working Group (PTWG) to review and approve the subproject proposals within fifteen (15) working days upon receipt of the proposals.
b. For subprojects costing above Php1.00 Million, endorse all the documents to the DILG-RO within two (2) working days after receipt. DETACa
6.3.1.4 In case the Proponent LGU fails to submit the required documents within the prescribed 45-day period, the DILG-PO shall advise, notify, and require the concerned Proponent LGU to explain the reason for their non-submission within ten (10) working days. If after validation and evaluation of their justification/explanation, the same is found to be unacceptable, or the Proponent LGU has no action within the ten-day period, the DILG-RO shall recommend to DILG-Central Office the transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
6.3.2 Review and Approval of Subprojects
6.3.2.1 For subprojects costing Php1.00 Million and below, the PTWG, as mentioned in Section 6.3.1.3.a shall review for approval/disapproval of the subproject proposals within fifteen (15) working days after receipt of the proposals. Within two (2) working days after approval, the DILG-PD shall endorse the approved subproject proposals to the DILG-RO. However, if the submitted subproject proposal is not acted upon by the PTWG within the prescribed 15-day period, the Project Development Management Unit (PDMU) shall take over the review and approval.
6.3.2.2 For subprojects costing above Php1.00 Million, the PDMU shall review the subproject proposals and recommend to the DILG-RD within fifteen (15) working days after receipt of the proposals. Within two (2) working days after receipt of the recommendation, the DILG-RD shall approve/disapprove subproject proposals.
6.3.2.3 If necessary, the PTWG or PDMU shall conduct site validation, including source validation for water subprojects, to verify the accuracy of the submitted documents and to further assess the feasibility of the subproject/s. The DILG-RO/PO may designate other accredited technical staff or agency to conduct site validation in behalf of DILG.
6.3.2.4 After assessment, the PTWG or PDMU shall notify the Proponent LGU to comply with the comments/recommendations. After receipt of the official notice, the Proponent LGU shall, within fifteen (15) working days submit the compliance to the comments/recommendations. Review and approval shall follow the same procedure stated in Section 6.3.2 of this guideline. In case the concerned LGU has not complied within the 15-day period, the DILG-RO/PTWG shall recommend to DILG Central Office the transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
6.3.2.5 If the PTWG/PDMU found the subproject is not feasible, DILG-RO/PO shall inform in writing the Proponent LGU of the findings. The Proponent LGU may replace the subproject, otherwise, the subproject will be cancelled and the DILG-RO/PO shall recommend to DILG-CO the transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects. Approval shall follow the same procedure mentioned above.
Annex F is the Checklist of Documentary Requirements for Subproject Review and Approval.
6.4 Signing of Memorandum of Agreement (MOA)
6.4.1 A Memorandum of Agreement (MOA) to be signed within five (5) working days after subproject approval by DILG-RD or upon receipt of the DILG-PD endorsement of approved subproject by PTWG shall be entered into:
a. By and between the DILG-RO and Proponent LGU as the Implementing Partner upon the submission of Sangguniang Bayan/Panlungsod (SB/SP) Resolution authorizing the LCE to enter into MOA with DILG. (See Annex G)
b. By and among the DILG-RO, Proponent LGU and Provincial Government or other Partner Agency as the Implementing Partner upon submission of the following requirement: (See Annex H)
1. For Proponent LGU, Sangguniang Bayan/Panlungsod (SB/SP) Resolution authorizing the LCE to enter into MOA with DILG.
2. For Provincial Government as Implementing Partner, Sangguniang Panlalawigan (SP) Resolution authorizing the LCE to enter into MOA with DILG and Proponent LGU. Furthermore, a Certification from the Local Treasurer or Bank Certificate of the existing Trust Account to be used in the implementation of the subproject.
3. For other Agency as Implementing Partner, Certification from the Agency Accountant or Bank Certificate of the existing Trust Account to be used in the implementation of the subproject.
6.4.2 The subproject cost to be reflected in the MOA shall be based on the amount determined after the review and approval of the subproject proposal and broken-down into DILG Fund and LGU Counterpart.
6.4.3 Immediately after the MOA signing, the DILG-RO shall obligate the whole amount of the DILG Fund stipulated in the MOA.
6.4.4 Copies of all perfected MOAs shall be submitted to both the Regional and Local Resident Auditors within five (5) working days from its execution in pursuant to COA Circular No. 2009-001, Section 3.1.1 dated 12 February 2009.
6.5 Issuance of Certificate of Availability of Funds (CAF)
6.5.1 Within three (3) working days after the MOA signing, the DILG-RO shall issue a Certificate of Availability of Funds (CAF) corresponding to the whole approved amount stipulated in the MOA to the Implementing Partner (See Annex I). Simultaneous with the issuance of CAF, DILG-RO shall also prepare, process and release the funds to the Implementing Partner in accordance to Section 6.11.2 (Mechanics for DILG Fund Releases).
Annex J is the Checklist of Documentary Requirements that will be used by PDMU on the request to Regional Budget Officer and/or Accountant in the issuance of CAF, obligation of funds and release of funds.
6.5.2 The CAF issued by the DILG-RO (equivalent to 100% of the allocation stipulated in the signed MOA) and the Annual Budget to cover the LGU Counterpart, if any, shall be the basis of the Implementing Partner to issue the CAF necessary to proceed with the procurement process provided that the Technical Design or DED has been approved by the DILG-RO.
6.6 Preparation and Submission of Technical Design/Detailed Engineering Design (TD/DED)
6.6.1 The Implementing Partner shall be responsible in the preparation and submission of the TD/DED. However, if the Implementing Partner is not the same as the Proponent LGU, the Implementing Partner shall closely coordinate with the Proponent LGU during the TD/DED preparation to ensure that the needs and welfare of the beneficiaries are considered.
6.6.2 In general, the preparation of TD/DED shall be financed from LGU counterpart fund. In order to facilitate the same, the Implementing Partner may opt to hire additional technical staff for the preparation of TD/DED to be obtained as part of their counterpart fund. Implementing Partner may use a portion of the DILG Fund but not to exceed 6% of the allocation stated in the signed MOA for the particular subproject in accordance to Section 6.11.2 (Mechanics for DILG Fund Releases).
6.6.3 The Implementing Partner may prepare the DED through any of the following:
6.6.3.1 By Contract, through Competitive Bidding pursuant to RA 9184 (Government Procurement Reform Act) aDSIHc
6.6.3.2 Partnership agreement with any of the following:
a. Local Water Utilities Administration (LWUA)/Water District
b. Provincial Government
c. Armed Forces of the Philippines (AFP) Engineering Brigade
d. State Universities/Academes
e. National Agencies
6.6.3.3 By administration or in-house, provided that the Implementing Partner has the capacity to prepare DED
6.6.3.4 Upon the request of the Implementing Partner, the DILG-RO may directly engage the services of consultants or government agencies in the preparation of DED
6.6.3.5 The DILG-RO may also provide technical assistance if warranted.
6.6.4 Documentary Requirements
6.6.4.1 The following are the technical documents to be prepared and submitted by the Implementing Partner:
a. For Subprojects costing Php1.00 Million and below
The Implementing Partner shall prepare TD in lieu of the DED which may include but not limited to the following:
i. Program of Works (POW) signed by the Municipal Engineer and approved by the concerned LCE
ii. Technical Drawings
iii. Bill of Quantities including detailed computation (signed and sealed by the approving authorities)
b. For Subprojects costing above Php1.00 Million
The Implementing Partner shall prepare DED to include the following:
i. Program of Works (POW) signed by the Municipal Engineer and approved by the concerned LCE
ii. Detailed designs, plans and drawings (signed and sealed by the approving authorities)
iii. Detailed Design Report
• water demand projection
• hydraulic analysis taking into account the network diagram report and, if necessary, geo-resistivity report
iv. Bill of Quantities including detailed computation (signed and sealed by the approving authorities) in accordance with the approved National Standard
v. Any other supporting documents as may be required
c. The Implementing Partner shall submit the above mentioned documents in printed and electronic copies to DILG-RO through the DILG-PO.
d. The Implementing Partner shall submit the TD/DED mentioned above to DILG-RO through the DILG-PD or C/MLGOOs within 60 calendar days after the receipt of the first tranche. Non-compliance with the prescribed 60-day period, DILG-RO shall:
i. Advise, notify, and require the concerned Proponent LGU to explain the reason for their non-submission. If after validation and evaluation of their justification/explanation, the same is found to be unacceptable, the Implementing Partner has no action, the DILG-RO shall issue a Demand Letter, copy furnished the Local COA Auditor, requiring the Implementing Partner to return within fifteen (15) working days all the released amount to the DILG-RO; and
ii. Recommend to DILG Central Office the transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
6.6.4.2 In consideration of the time needed to secure the necessary permits, licenses, certificates, clearances, and other documentary requirements from other NGAs, received copies of applications for the said permits/clearances shall be submitted by the Proponent LGU within the prescribed 60-day period. Indicated below are the related requirements needed to be complied with:
a. Pursuant to RA 8371, for subproject areas with Indigenous People (IPs) that will be affected, a certification that the area affected does not overlap with any ancestral domain needs to be secured from the National Commission on Indigenous People (NCIP).
b. Application for the issuance of Water Permit from deputized agencies at National Water Resources Board (NWRB).
Note: Compliance in securing the above permits and licenses shall be the responsibility of the Proponent LGU.
6.6.5 The City Director or C/MLGOO shall ensure the completeness of the documents submitted as listed in Section 6.6.4 above, which shall be endorsed to the DILG-PO within two (2) working days upon receipt of the TD/DED (See Annex K and Annex L for the Documentary Checklist). The DILG-PD shall:
6.6.5.1 For subprojects costing Php1 Million and below, convene the Provincial Technical Working Group (PTWG) to review and approve the TD/DED within fifteen (15) working days upon receipt of the proposals.
6.6.5.2 For subprojects costing above Php1 Million, endorse all the documents to the DILG-RO within two (2) working days after receipt.
6.7 Approval of Technical Design/Detailed Engineering Design (DED)
6.7.1 For subprojects costing Php1 Million and below, the PTWG, shall review/evaluate and approve/disapprove TD within fifteen (15) working days after receipt of the proposals. Within two (2) working days after approval, the DILG-PD shall endorse the approved subproject proposals to the DILG-RO. However, if the submitted TD are not acted upon by the PTWG within the prescribed 15-day period, the PDMU shall take over the review and approval.
6.7.2 For subprojects costing above Php1 Million, the PDMU shall review the DED and recommend approval to DILG-RD within fifteen (15) working days after receipt of the DED. Within two (2) working days after receipt of the recommendation, the DILG-RD shall approve/disapprove the DED.
Annex M is the Documentary Checklist of TD/DED Approval.
6.7.3 TD/DED that did not pass the PTWG or DILG PDMU approval shall be returned to the Implementing Partner for revision complying with the comments/recommendations of the reviewing body.
6.7.4 After receipt of the official notice that the proposed subproject did not pass the review, the Implementing Partner shall, within seven (7) working days, submit the revised TD/DED. Review and approval shall follow the same procedure stated in Section 6.7.
6.7.5 In case the Implementing Partner has not complied within the seven (7)-day period, DILG-RO shall:
6.7.5.1 Advise, notify and require the concerned Implementing Partner to explain the reason for its non-submission. If after validation and evaluation, the reason is found unacceptable, or after due course, the Implementing Partner has no action, the DILG-RO shall issue a Demand Letter, with a copy furnished to Local COA Auditor, requiring the Implementing Partner to return within fifteen (15) working days, all the released amount to the DILG-Regional Office as the source agency; ETHIDa
6.7.5.2 Recommend to DILG Central Office the transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
6.7.6 The DILG-RO shall officially notify the Implementing Partner of the approval of the TD/DED and advise the Implementing Partner to proceed with the procurement process.
6.7.7 Within five (5) working days after the official notification of the Implementing Partner on the approval of the TD/DED, the DILG-RO shall submit the electronic copy of the approved documents mentioned in Section 6.6.4 to DILG Central Office (DILG-CO).
6.7.8 The Implementing Partner shall commence with the posting of Invitation to Bid (ITB) within five (5) working days upon receipt of the official communication on the approval of their TD/DED.
6.8 Mode of Implementation
6.8.1 In order to promote economy and efficiency in the procurement, the Implementing Partner shall adhere to the provisions of RA 9184 (Government Procurement Reform Act).
6.8.2 Subprojects to be implemented by Administration
6.8.2.1 Procurement of materials/goods shall strictly follow the RA 9184 and its Revised Implementing Rules and Regulations (RIRR).
6.8.3 Subprojects to be implemented by Contract
6.8.3.1 Implementing Partner shall strictly follow RA 9184 (Government Procurement Reform Act) and its RIRR on Competitive Bidding.
6.8.3.2 The Implementing Partner shall:
a. Start posting the advertisement of ITB within five (5) working days after the approval of the DED by the DILG-RO.
b. Submit to the DILG-RO, through the DILG-PD, a copy of the ITB as published on the newspaper and PhilGEPs within two (2) working days after publication and posting.
c. Complete the bidding process following the timeline stipulated in RA 9184 as summarized in Annex N.
6.8.3.3 The Implementing Partner shall invite the DILG-RD or the DILG-PD or their duly authorized representative to be present during the bid opening.
6.8.3.4 In the event of a failed bidding, the Implementing Partner shall immediately start the re-bidding process within five (5) calendar days after the Bids and Awards Committee (BAC) has issued a resolution declaring a failure of bidding in accordance with the timeline set-forth in RA 9184. Within the same period, the Implementing Partner shall submit to DILG-RO a revised Subproject Implementation Schedule indicating the revised target dates for the bidding.
6.8.3.5 In the event that the Implementing Partner will have to resort to negotiated procurement after two (2) failed biddings, the Implementing Partner shall commence the negotiation process within five (5) calendar days after the BAC has issued a resolution declaring a failure of bidding and complete the negotiation within fifteen (15) calendar days.
6.8.3.6 In case of failure in the two (2) biddings and the negotiated procurement, the Implementing Partner shall seek clearance from the DILG-RO to implement the subproject by Administration. In such case, the procurement of materials/goods shall adhere to RA 9184. Likewise, the Implementing Partner shall submit a revised POW that excludes Contractor's Profit, Taxes and Overhead Contingencies and Miscellaneous (OCM) expenses; with unit price derivations per item of work, for review, validation, and approval by the DILG-RO.
6.8.3.7 The bidding process is deemed completed upon the issuance of the Notice to Proceed (NTP) by the Implementing Partner.
6.8.4 Subprojects to be implemented by Contract for Design and Build Infrastructure Projects
6.8.4.1 The Implementing Partner may also implement the subproject by Contract for Design and Build Infrastructure Projects following the Guidelines for Procurement and Implementation of Contract for Design and Build Infrastructure Projects (see Annex G of RA 9184) subject to the review and approval of DED by the DILG-RO.
6.8.5 Subprojects to be implemented by Partner Agency (e.g., Local Water Utilities Administration (LWUA)/Water District, Provincial Government, Armed Forces of the Philippines (AFP) Engineering Brigade, State Universities, National Agencies)
6.8.5.1 The Implementing Partner shall enter into an agreement with a partner agency stipulating the roles and responsibility of both parties.
6.8.5.2 Procurement of materials/goods shall strictly follow the RA 9184 and its RIRR.
6.8.6 Per COA Circular No. 2009-001, Section 3.1.1 dated February 12, 2009, within five (5) working days from the execution of the contract, the Implementing Partner shall submit to the LGU Resident Auditor a copy of the said contract together with all the documents forming part, thereof, by reference or incorporation.
6.8.7 All procurement shall follow the approved implementation schedule as attached in the signed MOA.
6.9 Subproject Implementation
6.9.1 For Implementing Partners
6.9.1.1 The Implementing Partner shall designate a Project Engineer/Supervisor to supervise the construction/implementation on a day-to-day basis.
6.9.1.2 For subproject to be implemented by contract or in partnership with other agency, the Implementing Partner shall conduct a Pre-Construction Conference with the Contractor immediately after the acceptance of the NTP or prior to implementation to discuss the following:
a. Technical aspects of the Contract
b. Specific subproject timeline including the advice to Contactor to mobilize within seven (7) calendar days after the receipt of the NTP
c. Agree on the regular conduct of coordination meetings
d. The nature and thrust of the subproject in relation to SALINTUBIG to ensure that the Contractor or Partner Agency appreciates the Project
e. The participatory monitoring approach of SALINTUBIG
f. Compliance of the Contractor or Partner Agency to pertinent policies and guidelines
Annex O provides the complete agenda in the conduct of the Pre-Construction Conference.
6.9.1.3 Consistent with RA 6685 dated 12 December 1988, the Implementing Partner shall hire or ensure that the Contractor hires at least fifty percent (50%) of the unskilled and at least thirty percent (30%) of the skilled labor requirements from the available bona fide residents in the province, city, or municipality where the subproject is located. The Implementing Partner shall ensure that the following are strictly observed: (1) adoption of the standard labor salary rate, (2) adoption of the rotation process to accommodate as many community members in the labor force, (3) transparency in the criteria for selection, and (4) prioritization of those from the community with no current employment and are abled. cSEDTC
6.9.1.4 The Implementing Partner shall submit or cause the Contractor to submit a monthly report on the labor force employed within the subproject based on the format shown in Annex P as part of the Monthly Physical Accomplishment Report stipulated in Section 6.9.1.6 below.
6.9.1.5 The Implementing Partner shall observe/cause the Contractor or Partner Agency to observe the following:
i. Construction materials are available on site in accordance with the approved plans and specifications
ii. Project and/or Material Engineer is present on site
iii. Appropriate equipment are on site in accordance with the Equipment Schedule
iv. Actual implementation/construction is in accordance with the approved Plans and Technical Specifications
v. Quality control (QC) tests are conducted consistent with the frequency specified in the Technical Specifications for each item of work. The tests are conducted by accredited testing center/laboratory
vi. Waste disposal is done in accordance with prescribed standards
vii. Health and Safety standards set by DOLE are implemented
6.9.1.6 The Implementing Partner shall submit/require the Contractor or Partner Agency to submit a Monthly Physical Accomplishment Report within five (5) days after the end of each month using the report form shown in Annex Q — Statement of Work Accomplished (SWA). Copy of the report shall be submitted to the DILG-PD and PDMU within two (2) working days after the submission of the Contractor or Partner Agency.
6.9.1.7 In case there is noted/observed delay, the Implementing Partner shall:
a. If by administration, submit of a catch-up plan to complete the works within the approved implementation period
b. If by contract or in partnership with other agency, immediately issue a Warning Letter to the Contractor or Partner Agency and require the submission of a catch-up plan to complete the work within the approved contract period.
6.9.1.8 In case the delay is due to unforeseen events or work items known to the Implementing Partner, submit or immediately advise the Contractor or Partner Agency to submit a request within thirty (30) calendar days from the occurrence of such circumstances/events leading to the delay, for either suspension of works or extension of contract/implementation time.
For subproject implemented by contract, any Contractor's request submitted beyond the said period shall be denied. The Implementing Partner shall act on the Contractor's request within three (3) days upon receipt of the request.
6.9.1.9 In case there is a stoppage of work for unknown reasons or the Contractor has abandoned the subproject, the Implementing Partner shall immediately assess/evaluate the situation, determining the accomplished and remaining works, and shall officially notify the Contractor to explain the reason for abandonment and the consequence of its action. If warranted, Implementing Partner shall:
a. Forfeit the Performance Security Bond in favor of the Implementing Partner
b. File liquidated damages in accordance with RA 9184
c. Recommend to DILG blacklisting of the Contractor and
d. Recommend revocation of the Philippine Contractors' Accreditation Board (PCAB) License.
In such case, the Implementing Partner shall take over the work or immediately rebid the remaining works.
6.9.1.10 The Implementing Partner shall invite the presence of DILG-C/MLGOO and/or DILG-C/P/RD during major activities such as, but not limited to:
i. Well drilling
ii. Pumping test
iii. Pipe laying
iv. Leakage/hydro testing/commissioning
v. Water sampling for potability (before, during and after construction)
6.9.1.11 For subproject implemented by Contract or in partnership with other agency, the Implementing Partner shall:
a. Conduct inspection when the subproject reaches 95% physical accomplishment for punch listing. The Implementing Partner may invite the DILG-RO or DILG-PO to be present during inspection. Immediately after inspection, the Implementing Partner shall inform the Contractor or the Partner Agency to rectify the noted deficiencies, if any, and to complete the works within the remaining contract duration.
b. Within one (1) week upon receipt of the request for final inspection from the Contractor or Partner Agency, conduct final inspection and may invite the DILG-RO or DILG-PO to be present during inspection as technical adviser.
6.9.1.12 For subproject implemented by Administration, the Implementing Partner shall:
a. Request inspection from DILG-RO or DILG-PO when the subproject reaches 95% physical accomplishment for punch listing. Immediately after inspection, the Implementing Partner shall rectify the noted deficiencies, if any, and complete the works within the remaining implementation duration.
b. Conduct joint final inspection with DILG-RO/DILG-PO.
6.9.1.13 Within seven (7) working days upon receipt of Implementing Partner or of the Contractor's/Partner Agency's request for final Inspection of the subproject, the Implementing Partner shall also request for COA inspection.
6.9.1.14 The Implementing Partner shall officially turnover the completed subproject to the LGU who will operate and maintain the subproject.
6.9.1.15 The Implementing Partner shall prepare and submit to DILG-RO the Subproject Completion Report (SPCR) as Annex R, within six (6) months after completion, which should include the following documents/proof:
i. Certificate of acceptance of the project issued or signed by the recipient or beneficiaries
ii. Consolidated Liquidation Report showing all fund deposits and actual disbursements
iii. Others, as deemed necessary.
6.9.2 For DILG-ROs, Provincial/City Directors or MLGOOs
6.9.2.1 The DILG-RO, through the PDMU, shall take the lead in monitoring all aspects of subproject implementation.
6.9.2.2 During monitoring visits, the DILG-RO, through the PDMU, shall observe/check the following, among others:
a. Availability of construction materials on site in accordance with the approved plans and specifications
b. The presence of Materials Engineer on site
c. Availability of appropriate equipment on site in accordance with the Equipment Schedule
d. QC tests results conducted whether they are consistent with the frequency specified in the Technical Specifications, and whether the tests were conducted by accredited testing center/laboratory SDAaTC
e. Waste disposal is done in accordance with prescribed standards
f. Health and Safety standards set by DOLE are being implemented
g. Works are in accordance with the approved Plans and Specifications
The DILG-RO, through the PDMU, the DILG-C/PD and/or C/MLGOO, shall immediately advise the Implementing Partner for any noted deviations and advise the Implementing Partner to initiate corrective actions or to cause the Contractor/Partner Agency to initiate corrective actions.
6.9.2.3 The DILG-RO, through the PDMU, DILG-C/PD and/or C/MLGOO, shall validate reports submitted by the Implementing Partner of Implementing Partner's or the Contractor's/Partner Agency's compliance with the provisions of RA 6685 regarding the hiring of skilled and unskilled labor. If the Implementing Partner or Contractor/Partner Agency is not compliant with the said provisions, immediately advise the Implementing Partner to comply or cause the Contractor/Partner Agency to comply.
6.9.2.4 The DILG-RO, through the PDMU, shall evaluate all submitted reports by the Implementing Partners for the following cases:
a. Physical Works not in accordance with the Approved Plans and Specifications — The DILG-RO, through the PDMU, DILG-C/PD and/or C/MLGOO, shall advise the Implementing Partner to immediately implement corrective measures or issue notice to Contractor/Partner Agency to implement corrective measures on noted defects. Implementing Partner shall be advised to monitor Contractor's/Partner Agency's corrective actions.
b. Inconsistency between the reported and actual work accomplished, DILG-PD and/or PDMU shall advise the Implementing Partner to conduct a joint inspection within three (3) days to resolve inconsistences.
c. Any delay in subproject implementation. DILG-PD or PDMU shall advise the Implementing Partner to submit catch-up plan to complete the works within the approved implementation period, or issue Warning Letter to the Contractor/Partner Agency and require immediate submission of catch-up plan to complete the works within the approved contract period.
6.9.2.5 Poor quality of works — The PDMU shall check the results of QC tests conducted by the Implementing Partner or Contractor/Partner Agency, among others.
6.9.2.6 Annex S shows the list of minimum QC tests that should be conducted by the Implementing Partner of Contractor/Partner Agency per type of subproject. The DILG-ROs shall conduct separate QC tests, if necessary, to validate quality of the subproject.
6.9.2.7 In case there is a reported stoppage of work for unknown reasons or the Contractor has abandoned the subproject, the DILG-RO, through the PDMU, DILG-C/PD and/or C/MLGOO, shall advise the Implementing Partner to immediately assess/evaluate the situation and recommend appropriate action.
6.9.2.8 The DILG-RO, through the PDMU, DILG-C/PD and/or C/MLGOO shall closely monitor the subproject and advise the Implementing Partner to:
a. Before the subproject reaches 95%:
i. Join the inspection for Punch listing of the subproject implemented by Contract or in partnership with other agency.
ii. Organize and conduct inspection for subproject implemented by Administration.
b. Before the subproject reaches 100% physical accomplishment:
i. Join the final inspection for subproject implemented by Contract or in partnership with other agency.
ii. Organize and conduct final inspection for subproject implemented by Administration.
c. Advise Implementing Partner to request COA for final inspection.
6.9.3 All subprojects shall be completed within the approved contract duration. In case the Implementing Partner cannot comply with this provision, DILG-RO shall advice, notify and require the concerned Implementing Partner to explain the reason for its non-compliance. If after validation and evaluation, the reason is found unacceptable, or after due course, the Implementing Partner has no action, the DILG-RO shall recommend to DILG Central Office the transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
6.10 Adherence to National Government Standards and Policies
6.10.1 The Implementing Partner shall abide by the standards and policies set by the National Government, which are applicable to all phases of subproject preparation and implementation.
6.10.2 The DILG-RO shall ensure that these standards and policies are considered during appraisal and are being observed during actual implementation by the Implementing Partner.
6.10.3 Adherence of the Implementing Partner to existing national standards/guidelines, laws and policies, which include, but is not limited, to the following:
a. Buildings and other vertical structures per the CY2005 Revised Edition of the RIRR of the National Building Code (PD 1096), and Volume 1, 6th Edition of the National Structural Code of the Philippines published CY2010 by the Association of Structural Engineers of the Philippines
b. Vol. II, Standard Specifications for Public Works and Highways (2004 Edition)
c. "No-build" zone in accordance with FY2016 GAA
d. Philippine National Standard for Drinking Water pursuant to DO Administrative Order (AO) 2007-0012
e. Rainwater Collection Facilities pursuant to RA 6716
f. Code on Sanitation of the Philippines pursuant to Presidential Decree (PD) 856
g. Clean Water Act of 2014 pursuant to RA 9275
6.10.4 Infrastructure subprojects shall provide architectural and structural features, design, or facilities that will reasonably enhance mobility, safety, and welfare of persons with disability pursuant to Batas Pambansa (BP) 344 and RA 7277.
6.10.5 Infrastructure subprojects shall integrate energy-saving solutions in planning and implementation to mitigate the effect of climate change pursuant to RA 9729.
6.11 Fund Administration
In general, all prevailing COA rules and regulations shall be followed:
6.11.1 Fund Utilization
6.11.1.1 The DILG Fund shall:
a. Be used exclusively to finance for the following:
i. Construction/implementation of subprojects reflected in the signed MOA.
ii. Preparation of the DED, but it shall not be more than 6% of the subproject allocation based on the following conditions:
• If the Implementing Partner is not the Proponent LGU.
• If the Implementing Partner is the Proponent LGU, for construction of new subprojects costing above Php1 Million.
b. Not be used to finance administrative costs (e.g., office supplies, local travelling expenses, communication, honoraria, meetings and consultations, salaries, and any other related monitoring and construction supervision expenses) of Implementing Partner/Proponent LGU personnel overseeing and supervising the subproject implementation. Such expenses shall be borne by the Implementing Partner as LGU-counterpart fund.
Return any unexpended balances to the DILG-ROs of DILG Fund within six (6) months after subproject completion.
6.11.1.2 The Cash and/or in-kind counterpart of the Proponent LGU/Implementing Partner shall be used for the following:
a. Proponent LGU
i. The subproject cost in excess of the DILG Fund allocation (in cash) which shall be used exclusively for construction/implementation of the subproject and shall be deposited/transferred in the Implementing Partner's Trust Account used in the subproject implementation. acEHCD
ii. Preparatory activities (Feasibility Study/Subprojects Proposal preparation, survey/validation, social preparation activities, cost/fees for permits, tests, and etc.) including hiring of technical staff for the preparation of Feasibility Study.
iii. Conduct of Geo-resistivity for new construction of water supply facility with underground water source.
iv. Administrative cost for the implementation/supervision and evaluation of subproject including attendance to meetings and trainings (e.g., office supplies, local travelling expenses, communication, honoraria, meetings and consultations, salaries, and any other related construction supervision expenses).
v. Appropriate at least 1% of the subproject allocation for sanitation related activities such as behavioral change communication, barangay consultation on water, sanitation and hygiene and Community Led Total Sanitation (CLTS).
b. Implementing Partner
i. Preparation of TD/DED including hiring of technical staff in the preparation of TD/DED for subprojects not to be financed by the DILG Fund
ii. Construction Supervision including hiring of additional engineer
iii. Administrative cost for the implementation/supervision and evaluation of subproject including attendance to meetings and trainings (e.g., office supplies, local travelling expenses, communication, honoraria, meetings and consultations, salaries, and any other related construction supervision expenses)
6.11.2 Mechanics for SALINTUBIG-DILG Fund Management
6.11.2.1 DBM to DILG-RO
a. Based on the comprehensive release of the SALINTUBIG Funds by DBM to the DILG-ROs, the DILG-RO shall book up the SALINTUBIG-Funds in the regular account under Fund 101.
b. The DILG-RO shall immediately obligate the whole amount allotted for the subproject after MOA signing as stipulated in Section 6.4.3.
c. Based on the release of Notice of Cash Allocation (NCA) by DBM to DILG-RO, DILG-RO shall book up the Notice of Cash Allocation (NCA) as "Subsidy from National Government — 4-03-01-0101".
d. As a general rule, any unobligated allotment will automatically be reverted to the General Fund at the end of the appropriation validity period. In the case of FY2016 budget, the appropriation is valid until December 2017.
6.11.2.2 DILG-RO to CMs and Provinces as Implementing Partners
a. DILG shall issue CAF to the Implementing Partner equivalent to the DILG Fund allocation for the subproject as reflected in the MOA.
b. DILG shall transfer the DILG Fund to the Implementing Partner by issuing Authority to Debit Account (ADA) authorizing the government servicing bank to transfer fund to the Trust Account of the Implementing Partner. Thereafter, a Notice of Authority to Debit Account shall be issued to the Implementing Partner. However, the DILG-RO may opt to issue check in the name of the Implementing Partner instead of ADA. DILG-RO shall book up the cash transfer as "Due from LGUs — 1-03-030030". The DILG-RO concerned shall maintain a subsidiary ledger of the fund transfer pertaining to the subproject/s.
c. The Implementing Partner shall take up the transferred funds as "Due to NGAs". The Implementing Partner shall maintain a separate subsidiary ledger to facilitate tracking of fund receipt, utilization and liquidation.
d. Fund releases to Implementing Partner shall be made in the following tranches upon submission of required documents mentioned in Annex T.
• 100% of the Subproject Allocation shall be released upon MOA signing for subproject costing Php3 Million and below
• Two (2) tranches for subproject costing above Php3 Million as follows:
ü 1st Tranche — 80% of the Subproject Allocation upon MOA signing
ü 2nd Tranche — 20% of the Subproject Allocation or the approved Contract Cost less the first tranche, but not more than the remaining balance of the Subproject Allocation shall be released upon 20% liquidation of the 1st tranche and LGU cash counterpart fund (if any) mentioned in Section 6.11.1.2.a.i and 50% physical accomplishment
e. For subprojects that will be implemented by other agencies such as the AFP Engineering Brigade and other Implementing Partner, the concerned DILG-RO shall transfer the fund to these entities, based on the agreed and approved Implementation Schedule and signed MOA. These entities shall have a Trust Account (existing or new) for this purpose. The DILG-RD shall likewise enter into a MOA with these agencies.
f. Requests for the release of funds shall be submitted to the Concerned DILG-RO with the required supporting documents as mentioned in Annex T.
g. The DILG-RO shall review the submitted documents and conduct field inspection to validate the claimed physical accomplishment prior to the release of funds.
h. DILG-RO shall release the funds within seven (7) working days upon satisfactory compliance of the requirements in accordance to Section 6.11.2.2.f.
i. DILG-RDs are authorized to act on, sign and/or approve contracts, disbursement vouchers, checks, liquidation reports and all other related documents pertaining to the implementation of the DILG Projects with amounts equivalent to the approved subproject costs stipulated in the MOAs with the Implementing Partners, subject to the usual accounting and auditing rules and regulations.
j. The DILG-RO shall inform in writing the concerned Regional and Local Resident Auditors that the funds has been released to the Implementing Partner, immediately after the release of funds.
Note: The Proponent LGU shall deposit the Cash Counterpart Fund in the Implementing Partner's Trust Account before the issuance of the NTP and before the start of subproject implementation and the DILG Fund first tranche shall be 20% disbursed before the release of the last tranche.
6.11.3 Reporting and Liquidation
6.11.3.1 Liquidation of Fund Transfers
a. The Implementing Partner shall liquidate the funds by submitting to the DILG-RO, either in print or by way of electronic documents, the duly signed Report of Disbursement (ROD)/Liquidation (See Annex U).
b. The ROD submitted by the Implementing Partners shall be duly signed by the concerned Accountant and approved by the LCE/Head of Agency and duly received by the Local COA Auditor shall be taken up by the DILG-RO as liquidation subject to the post-audit of the Local COA Auditor. This shall also serve as the basis for the subsequent fund release to Implementing Partner.
c. The Implementing Partner shall submit to DILG-RO the Report of Disbursement (ROD)/Liquidation, if necessary, including copies of the supporting documents as evidence of the actual utilization of funds, within 10 days after the end of each month. SDHTEC
d. Within fifteen (15) calendar days after the end of each month, the DILG-RO shall submit to DILG Finance and Management Service (FMS) — Accounting Division, copy furnished OPDS, the Regional Consolidated Report on Fund Utilization and Liquidation. (See Annex V)
e. The DILG-RO or any authorized representative may conduct spot checks of the fund utilization, proper recording of book of accounts, and overall financial management of the Implementing Partner.
f. All fund transfers shall be liquidated within six (6) months after the completion of each subproject. Unexpended balance shall be returned to DILG-RO within the prescribed six-month period. The Implementing Partner shall submit to the DILG-RO the Consolidated Report showing all fund receipts and actual disbursements based on the monthly submitted ROD as mentioned in Section 6.11.3.1.b.
g. In case of non-submission, DILG-RO shall notify in writing the Implementing Partners on the need to submit the required liquidation reports.
6.11.3.2 Liquidation of Regional Operational Fund
Every 10th day after the end of each month, the DILG-RO shall submit to DILG Finance and Management Service (FMS) — Accounting Division, copy furnish OPDS, the ROD on the utilization of the sub-allotment for operational expenses. The subsequent sub-allotment shall only be released upon submission of the liquidation report showing that at least 50% of the released amount have been disbursed.
6.11.4 Illustrative Accounting Code of Entries for the DILG Fund Transfer
6.11.4.1 Annex W is the matrix/table of illustrative accounting entries for Regional Office and LGUs in their respective books of accounts, showing entries from the issuance of Notice of Cash Allocation (NCA) to the transfer of assets by DILG-RO to LGUs.
6.12 Implementation Arrangement
6.12.1 Project Management Office (PMO)
Project Management Office (PMO) lodged in the DILG Central Office under the Office of Project Development Services (OPDS) which shall be responsible for the overall-project management, in close coordination with other line agencies involved in the implementation of the SALINTUBIG Projects. Specifically, the PMO shall be responsible for the following:
6.12.1.1 Formulation/Updating of Operational Guidelines and Strategies for effective implementation.
6.12.1.2 Over-all physical and financial planning.
6.12.1.3 Over-all fund management.
6.12.1.4 Development monitoring and evaluation systems.
6.12.1.5 Development and maintenance of databases for the DILG Fund Projects.
6.12.1.6 Preparation and submission of consolidated weekly, monthly, quarterly, annual and other regular reports to the DILG Management and other partner agencies either in print or by electronic copy.
6.12.1.7 Provision of advisory and technical assistance to DILG Field Offices and Implementing Partners in the development, implementation, operation, and management of big ticket and critical subprojects.
6.12.1.8 Conduct risk assessment to determine critical subprojects.
6.12.1.9 Close monitoring of big ticket and critical subprojects.
6.12.1.10 Development and implementation of the following capacity development programs for the Implementing Partners, WATSAN Councils/Teams, Water Service Providers, and including day care centers and schools without access to potable water:
1) Pre-implementation Phase
i. Program Orientation and Feasibility Study (FS) Preparation
ii. Water Supply and Sanitation Sector Plan (MW4SP) Preparation
iii. Detailed Engineering Design (DED) Preparation and Procurement
2) Implementation Phase
iv. Construction Supervision and Fund Management
v. Human Rights-Based Local WATSAN Governance (HRBLWG) and Strategic Communication
vi. Community Organizing and Skills Enhancement Using Rights-Based Approach
3) Sustainability Phase
vii. Operations and Maintenance (O&M)
• LGU-Managed Water Supply Project
• BWASA-Managed Water Supply Project
viii. Ring-fencing and Business Planning for LGU-managed Water Supply Project
ix. Performance Benchmarking
x. Water Safety Plan (WSP) Preparation
6.12.1.11 Conduct of regular consultations/dialogues with DILG-ROs and LGUs
6.12.2 DILG Regional Offices (DILG-RO)
The DILG Regional Offices (DILG-RO) shall take the lead and be responsible for the efficient and effective implementation of the DILG Fund Project at the local level, and shall take appropriate measures to ensure that the DILG Funds transferred to Implementing Partners are used for the intended purpose.
6.12.2.1 The DILG Regional Director (DILG-RD) shall:
a. Organize PTWGs in all participating provinces to review and approve proposals and Technical Designs for subprojects amounting to Php1 Million and below
b. On behalf of the DILG, enter into a MOA with the Implementing Partners for the implementation and release of funds for the subprojects
c. Enter into a Partnership Agreement with service providers for the DED preparation
d. Approve/disapprove subproject proposals and DED for subprojects above Php1 Million
e. Sign and/or approve contracts, disbursement vouchers, checks, liquidation reports and other documents related to subproject implementation
6.12.2.2 The DILG Regional Offices (DILG-RO), thru the Project Development and Management Units (PDMUs), shall take the lead and be responsible for the efficient and effective implementation of the DILG Fund Project at the local level. The PDMUs shall be responsible for the following:
a. Conduct regional fund management, which includes among others, review of documents submitted by the Proponent LGU/Implementing Partners prior to release of funds, and verifying satisfactory compliance of requirements;
b. Conduct regional physical and financial planning;
c. Review, assess, and validate the proposed subprojects;
d. Conduct eligibility assessment of Proponent LGUs;
e. Review, evaluate, and recommend approval of subproject proposals and DED;
f. Implement subprojects, as necessary;
g. Provide advisory and technical assistance to DILG Provincial/Municipal Offices and Implementing Partners, in the development, implementation, operation and management of subprojects;
h. Ensure the compliance to requirements of Proponent LGUs/Implementing Partners;
i. Assist in the conduct of capacity development assistance to Implementing Partners;
j. Provide support to the Provincial and Municipal Offices in the monitoring and evaluation for subprojects costing Php1 Million and below;
k. Prepare and submit timely Physical and Financial Accomplishments of all SALINTUBIG subprojects to DILG Central Office thru FMS and OPDS; AScHCD
l. Prepare regular alert status reports that will provide the management advance information on what is happening on the ground that will guide in addressing possible bottleneck;
m. Conduct regular consultations/dialogues with LGUs and other stakeholders;
n. Recommend cancellation of non-moving subprojects and transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects; and
o. Conduct separate QC tests, as necessary.
6.12.3 DILG Provincial/City/Municipal Offices
The DILG-C/PD and C/MLGOOs shall assist the DILG-RO in overseeing the implementation of the DILG Fund Project at the local level. The DILG-C/PD or his/her duly designated representative shall act as the Person in the Province/City. The C/MLGOOs shall serve as the SALINTUBIG-Focal Person in the municipality. The DILG-PD shall be responsible for the following:
6.12.3.1 Convene the PTWG for the review and approval of the submitted subproject proposals.
6.12.3.2 Assist in the conduct of the capacity development activities at the provincial/city/municipal level.
6.12.3.3 Brief the Proponent LGUs and Implementing Partners of the DILG Fund Project Guidelines and Timelines.
6.12.3.4 Monitor and provide timely reports/feedback to the DILG-RO on the progress of activities in all phases of subproject implementation to include but not limited to the following:
a. Status of the preparation of subproject proposals, DED/Technical Design and other supporting documents
b. Progress of the preparation of Bidding Documents
c. Issuance of the SB Resolution authorizing the Mayor to sign the MOA
d. Status of Procurement
e. Status of Subproject Implementation
6.12.3.5 Review the completeness of the relevant documents submitted by the Implementing Partners.
6.12.3.6 Facilitate the finalization of documents required in MOA signing.
6.12.3.7 Provide feedback whether Implementing Partner has issued CAF to BAC as a requirement to commence with the procurement process.
6.12.3.8 Monitor and provide advice during the bidding process.
6.12.3.9 Attend during the Bid Opening, if necessary.
6.12.3.10 Ensure timely submission of accomplishment reports (including pictures) and upon subproject completion, attest to the existence of the subproject.
6.12.3.11 Ensure that Implementing Partner install and regularly update the Subproject Community Billboard in compliance with the COA issuance No. 2013-004 dated January 30, 2013 and other relevant guidelines.
6.12.3.12 Participate in the conduct of punch listing and final inspection and submit report to DILG-RO within two (2) days after inspection.
6.12.3.13 Ensure that the DILG Funds are utilized for the intended purpose.
6.12.3.14 Assist in the conduct of spot checking on the book of accounts and ledgers of the Implementing Partners.
6.12.4 The Provincial Technical Working Group (PTWG)
The Provincial Technical Working Group (PTWG) shall be chaired by the DILG-PD with City Director, Cluster Heads or C/MLGOOs as members. Representatives from the Provincial Government, preferably from the Provincial Engineering Office (PEO) and Provincial Planning and Development Office (PPDO), are to assist in the review of subproject proposals. The PTWG shall:
6.12.4.1 Review, evaluate, and approve/disapprove subproject proposals and technical documents costing Php1 Million and below.
6.12.4.2 Conduct site visits and field validation to further assess the feasibility of the proposed subproject.
6.12.4.3 Prepare consolidated evaluation report for submission to the DILG-RD.
6.12.4.4 Recommend cancellation of non-moving subprojects and blacklisting of non-performing Proponent LGUs/Implementing Partner to DILG-RD.
6.12.5 Proponent LGU/Implementing Partner
Assessment of the eligibility of the Proponent LGU as the Implementing Partner shall be in accordance with Section 6.2 of this Guideline and shall be further validated during Subproject Review Process. The Implementing Partner may be the Provincial Government or the City/Municipal Government or any other entity that may be designated by the DILG-RD.
6.12.5.1 The Proponent LGU shall:
a. Prepare subproject proposal/s
b. Provide counterpart funds, as necessary
c. Adhere to existing national standards/guidelines, laws and policies stipulated in Section 6.10, among others
d. If not the Implementing Partner, enter into a MOA with DILG and Implementing Partner
e. If not the Implementing Partner, jointly monitor the implementation of subproject with the Implementing Partner
f. Commit to provide annual operations and maintenance funds through an SB Resolution
g. Identify appropriate institution to manage, operate and maintain the subproject
6.12.5.2 The Implementing Partner shall:
a. Enter into a MOA/Tripartite MOA, whichever is applicable, with the DILG and/or Proponent LGU for the implementation of subproject
b. Maintain a Trust Account for the transfer of funds
c. Designate a focal person/appropriate focal unit/department in the organization which will manage and coordinate the implementation of subproject/s, including financial transactions
d. Designate a full time Project Engineer/Supervisor to oversee the physical implementation of the subprojects to ensure that it is in accordance with the plans and specifications
e. Adhere to existing national standards/guidelines, laws and policies stipulated in Section 6.10, among others
f. Adhere to the provisions of RA 9184 and its RIRR
g. Ensure that subproject is implemented in accordance with the approved schedule, within the approved budget and in accordance with acceptable standards
h. Submit monthly financial and physical accomplishment reports DILG-RO
i. Submit a timely report of all DILG Fund Project that it has implemented, either in print or by electronic copy to DILG-RO
j. Liquidation of the DILG Fund on time
k. Return to DILG-RO any of the unexpended balance of the DILG Fund.
6.13 Monitoring and Evaluation
6.13.1 Progress Monitoring
6.13.1.1 DILG-PMO
a. Conduct SALINTUBIG Project risk assessment and site visits for big ticket and critical subprojects and spot checks in all phases of subproject implementation, whenever necessary. AcICHD
b. Shall submit a consolidated quarterly monitoring report to DBM thru the DILG-Planning Service and FMS.
c. Conduct Quarterly SALINTUBIG Project Implementation Reviews.
6.13.1.2 DILG Field Offices
DILG-ROs shall take the lead in the progress monitoring of all SALINTUBIG subprojects funded by DILG.
a. Progress monitoring shall be conducted by the DILG Regional/Provincial/City/Municipal Offices and shall cover, but not limited to the following:
i. physical status and accomplishment;
ii. financial status to include utilization/disbursement rates;
iii. problems encountered and recommended solutions; and
iv. risk analysis.
b. Monitoring and reporting of progress of subproject implementation will be done weekly, monthly and quarterly using Monitoring and Evaluation (M&E) forms prescribed by DILG PMO
c. Regularly update the Programs/Projects Monitoring System (PPMS) — http://ppms.dilg.gov.ph/projectsmapv3/mapprojectv3.php
6.13.1.3 Alert Mechanisms shall be established to ensure timely resolution of issues that may arise before, during and after subproject implementation.
6.13.2 Transparency and Accountability Mechanisms
The following Transparency and Accountability Mechanisms shall be operationalized in the implementation of subprojects:
6.13.2.1 Implementing Partner shall install subproject billboards on the subproject sites to provide information including the period of implementation, fund allocation and status of fund utilization consistent with COA Circular No. 2013-004, dated 30 January 2013 — Information and Publicity on Programs/Projects/Activities of Government Agencies on subproject reporting and monitoring.
6.13.2.2 Implementing Partners shall post in their respective websites, within thirty (30) calendars days from entering into Contract with the winning contractor/bidder, the following information per subproject:
a. Subproject title and detailed description, which shall include the nature and location;
b. The detailed estimates in arriving at the Approved Budget for the Contract; and
c. The winning contractor and the detailed estimates of the bid awarded.
6.13.2.3 Implementing Partner shall also post in their respective websites within thirty (30) calendars days from the issuance of subproject completion the following:
a. Detailed actual cost of the subproject; and
b. Variation orders, if any.
6.13.2.4 DILG-PMO and DILG-ROs shall post the subproject implementation status on their respective websites. Full disclosure of subproject information and status of implementation is encouraged through tri-media.
6.13.3 Project Evaluation
Data on specific social and economic indicators shall be regularly collected in SALINTUBIG project sites to aid in outcome evaluation. A separate guideline will be issued for the detailed SALINTUBIG Project evaluation system/procedure.
6.13.4 Information Dissemination and Institutional Learning
The PMO and DILG-ROs shall establish processes and mechanisms for the regular sharing of findings from monitoring and evaluation initiatives. This will include sharing of information on challenges encountered, good practices and lessons learned from program implementation. These are envisioned to be fed into planning and programming to facilitate institutional learning.
6.14 Penalties and Sanctions
The DILG Regional Director is authorized to:
6.14.1 Terminate/cancel the implementation of the subproject in the following instances:
6.14.1.1 Implementing Partner's/Implementing LGU's non-compliance to subproject processes, standards and requirements;
6.14.1.2 Corruption and fraudulent practices;
6.14.1.3 When situations/circumstances would make it improbable for the subproject to continue to be carried out; and
6.14.1.4 Upon request of the Implementing Partner.
In case the subproject is partially or fully cancelled due to the fault of the Implementing Partner, the Implementing Partner shall be obliged to return the spent amount and unexpended balance of the released portion of the funds or the pertinent portion related to the cancelled component of the subproject, whichever applies without prejudice to Section 6.14.3 hereof.
6.14.2 Suspend/withhold the release of the final tranche if any of the following occurs:
6.14.2.1 The DILG, during the conduct of review and monitoring activities determines that: (i) the procurement of any contract is inconsistent with RA 9184 provisions; and/or (ii) Implementing Partner is performing unsatisfactorily in the implementation and execution of the subproject or in the event that substantial slippage in implementation is incurred;
6.14.2.2 Extraordinary conditions such as force majeure, fortuitous events and the like which shall make it necessary to suspend the implementation of the subproject.
Implementing Partner will be given a period of one (1) month to resolve the issue, improve performance, or remedy the situation. However, termination will be resorted to only, if Implementing Partner, having been duly notified, does not make any effort to institute measures that will address issues at hand.
6.14.3 File the appropriate civil, criminal and/or administrative case against the concerned local public official/s for acts or omissions in relation to the performance of their duties under this Memorandum Circular.
7.0 References
• RA 9184
• RA 10717 (GAA FY2016)
• RA 6685 dated 12 December 1988
• COA Circular
• Buildings and other vertical structures per the CY2005 Revised Edition of the RIRR of the National Building Code (PD 1096), and Volume 1, 6th Edition of the National Structural Code of the Philippines published CY2010 by the Association of Structural Engineers of the Philippines
• Vol. II, Standard Specifications for Public Works and Highways (2004 Edition)
• Tourism facilities per Department of Tourism (DOT) guidelines
• "No-build" zone in accordance with FY2015 GAA
• Philippine National Standard for Drinking Water pursuant to Department of Health (DOH) Administrative Order (AO) 2007-0012
• Rainwater Collection Facilities pursuant to RA 6716
• Code on Sanitation of the Philippines pursuant to Presidential Decree (PD) 856
• Clean Water Act of 2014 pursuant to RA 9275
8.0 Annexes
Annex A — Pro-forma Eligibility Advice
Annex B — Simplified Feasibility Study (SFS) Format
Annex C — Pro-Forma Letter Request
Annex D — Pro-Forma Subproject Implementation Schedule
Annex E — Checklist for Documentary Requirements for Submission of SFS
Annex F — Checklist for Documentary Requirements for DILG-RO Review/Approval
Annex G — Pro-Forma Memorandum of Agreement (MOA) between DILG and LGU
Annex H — Tripartite Memorandum of Agreement (MOA)
Annex I — Pro-forma Certificate of Availability of Funds (CAF)
Annex J — Checklist for Documentary Requirements for Release of CAF and Fund TAIaHE
Annex K — Checklist for Documentary Requirements for Submission of Technical Specification/Design
Annex L — Checklist for Documentary Requirements for Submission of DED
Annex M — Checklist for Documentary Requirements for DED Approval
Annex N — Procurement Timelines
Annex O — Preconstruction Conference Agenda
Annex P — Labor Force Report
Annex Q — Statement of Work Accomplished
Annex R — Pro-forma Subproject Completion Report (SPCR)
Annex S — Minimum Requirements for Quality Control Tests
Annex T — Summary of Documentary Requirements
Annex U — Pro-forma Report of Disbursement/Liquidation (ROD)
Annex V — Pro-forma Consolidated Report of Disbursement (CROD)
Annex W — Illustrative Accounting Code of Entries for Fund Transfer
9.0 Inquiries/Appeals and Escalation
The Water Supply and Sanitation-Project Monitoring Office (WSS-PMO) of the Offices of Project Development Services (OPDS) is responsible for drafting/formulating/issuing the policy. Inquiries or complaints concerning this document should be directed/addressed to OPDS through the WSS-PMO on any of the following: Tel. No. (02)-928-5854, email address at [email protected] com or mailing address at DILG-NAPOLCOM Center, EDSA corner Quezon Avenue, West Triangle, Quezon City for appropriate action.
10.0 Effectivity
This policy shall take effect immediately.
(SGD.) MEL SENEN S. SARMIENTOSecretary
APPENDIX 1
Acronyms and Abbreviations
| AFP | Armed Forces of the Philippines |
| AIP | Annual Investment Plan |
| AO | Administrative Order |
| BAC | Bids and Awards Committee |
| BP | Batas Pambansa |
| BTr | Bureau of Treasury |
| CAF | Certificate of Availability of Funds |
| CLTS | Community Led Total Sanitation |
| COA | Commission on Audit |
| CSO | Civil Society Organization |
| DBM | Department of Budget and Management |
| DED | Detailed Engineering Design |
| DILG | Department of the Interior and Local Government |
| DILG-PD | Department of the Interior and Local Government Provincial Director |
| DILG-PO | Department of the Interior and Local Government Provincial Office |
| DILG-RD | Department of the Interior and Local Government Regional Director |
| DILG-RO | Department of the Interior and Local Government Regional Office |
| DOH | Department of Health |
| DOLE | Department of Labor and Employment |
| DOT | Department of Tourism |
| ECC | Environmental Compliance Certificate |
| EO | Executive Order |
| FMS | Finance and Management Service |
| FY | Fiscal Year |
| GAA | General Appropriations Act |
| GFH | Good Financial Housekeeping |
| IP | Indigenous People |
| IRR | Implementing Rules and Regulations |
| ITB | Invitation to Bid |
| LCE | Local Chief Executive |
| LGUs | Local Government Units |
| LWUA | Local Water Utilities Administration |
| M&E | Monitoring and Evaluation |
| MC | Memorandum Circular |
| MGB | Mines and Geoscience Bureau |
| MLGOOs | Municipal Local Government Operation Officers |
| MOA | Memorandum of Agreement |
| NAPC | National Anti-Poverty Commission |
| NCA | Notice of Cash Allocation |
| NCIP | National Commission on Indigenous People |
| NG | National Government |
| NGAs | National Government Agencies |
| NGO | Non-government organization |
| NTP | Notice to Proceed |
| NWRB | National Water Resources Board |
| OCM | Overhead Contingencies and Miscellaneous |
| OPDS | Office of Project Development Services |
| P/CD | Provincial or City Directors |
| PCAB | Philippine Contractors' Accreditation Board |
| PCCP | Portland Cement Concrete Pavement |
| PD | Presidential Decree |
| PDMU | Project Development Management Unit |
| PEO | Provincial Engineering Office |
| PFP | Program Financial Plan |
| PMO | Project Management Office |
| POs | People's Organization |
| POW | Program of Works |
| PPDO | Provincial Planning and Development Office |
| PTWG | Provincial Technical Working Group |
| QC | Quality Control |
| RA | Republic Act |
| ROD | Report of Disbursement |
| SB | Sangguniang Bayan |
| SFS | Simplified Feasibility Study |
| SGLG | Seal of Good Local Governance |
| SP | Subproject Proposal |
| SPCR | Subproject Completion Report |
| SWA | Statement of Work Accomplished |
ANNEX A
Pro-Forma Eligibility Advice
Republic of the PhilippinesDepartment of the Interior and Local GovernmentRegional Office (____)
DATE
NAME OF LOCAL CHIEF EXECUTIVE
Dear Mayor :
This is to inform you that your Municipality/Province has been found (eligible/ineligible) to implement your project under the Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program FY 2016.
Upon receipt of this letter, you are expected to take the necessary actions/steps stipulated in the Guidelines following this advice. cDHAES
Sincerely,
SIGNATORY
ANNEX B
Simplified Feasibility Study for WS
Simplified Feasibility Study Format
I. Description
A. Project Title
Indicate Project Title
(For infrastructure projects, specify if the project is New Construction, Rehabilitation or Upgrading of an existing facility.)
B. Project Location
Provide data on the location of the project including Congressional District of the City/Municipality (CM).
C. Brief Summary of the Project
• Indicate the development concerns that the project wishes to address and cite existing indicators to describe the development situation.
• Elaborate on the potential impact of the project on the locality and/or community.
• Enumerate indicators that will demonstrate the current conditions being addressed.
• Discuss if the project is complementary to other projects (i.e., CCT, PAMANA and Focus LGUs).
D. Project Goals and Objectives
Describe project goals (what you hope to achieve) and objectives (in measurable terms). State how the specific program/project/activity contributes to the improvement of the target beneficiaries.
E. Total Project Cost
Indicate the Total Project Cost in Pesos and the percentage of contribution/counterpart of the proponent (if any):
|
Line
|
City/Municipality
|
Other Partners
|
Nat'l. Gov't.
|
Total
|
|
Items
|
Counterpart
|
Support
|
Subsidy
|
|
|
|
|
|
|
|
|
___________
|
_______________
|
______________
|
_______________
|
___________
|
|
___________
|
_______________
|
______________
|
_______________
|
___________
|
|
___________
|
_______________
|
______________
|
_______________
|
___________
|
|
Total
|
_______________
|
______________
|
_______________
|
___________
|
|
% share
|
_______________
|
______________
|
_______________
|
___________
|
F. Target Beneficiaries
Identify the direct and indirect beneficiaries of the project, and the potential project benefits that might accrue to them.
G. Project Partners
• Describe other partners in the project, CSO participation, their roles and commitments, if any.
• Describe other sources of funding for the project including other support received relevant to this proposal.
H. Technical Evaluation (for Infra Projects)
Site Analysis
Describe the physical and spatial location of the proposed project, including:
— Topography
— Hydrology
— Soil Investigation
— Proximity to Utilities
— Vulnerability to Natural Hazards
— Land Use/Zoning Plans
Notes: (to take into account DRRM)
— The proposed site should not be susceptible to excessive surface run-off or flooding except for small water impounding projects and inland fishery projects
— The proposed site should not be located on or near the slopes that is prone to landslide and erosion
— The proposed site should not be located near an active fault line
— The proposed site will not disturb historical and monumental markers
— For road projects, describe if it is linked with an existing national road
— For new water supply projects, describe its distance from the potential source
II. Project Components and Implementation Schedule
• Identify and describe the major components and activities to be carried out in the implementation of the project. The plan should be presented by task with the responsible parties which shall carry out the tasks.
• Include a time table of activities showing when each task will be completed. This should be presented in a table format and cover all months or quarters of the project implementation.
III. Work and Financial Plan
Include detailed financial schedules of the proposed project.
IV. Project Management
Name the key officers and personnel that will be directly accountable for the project. Describe the on and post-project management scheme, internal monitoring and evaluation procedures.
V. Project Sustainability
• Demonstrate how the benefits/returns of the project can be greater than the costs.
• Describe how the project will be sustained after the assistance in terms of policy, user's fees and charges and related ordinances; office/unit responsible for the operation and maintenance.
Prepared by:
Signature above Printed Name
Endorsed by:
Signature above Printed Name
ANNEX B-1
Simplified Feasibility Study for WS
Simplified Feasibility Study Format
ANNEX C
Pro-Forma Letter Request
Republic of the Philippines
Office of the City/Municipal Mayor
____________
(NAME OF REGIONAL DIRECTOR)
THRU: Name of Provincial DirectorProvincial Director
Dear Sir/Ma'am,
In line with our Local Poverty Reduction Action Plan (LPRAP), may we respectfully request your office for the approval of (_______________________) (PROJECT NAME) with a project cost of (____________________________) (amount in words) (_____________________) (amount in numbers) to be funded under the Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program. ASEcHI
Enclosed herewith is the following list of supporting documents as requirement:
1. Simplified Feasibility Study (SFS)
2. Certification from the Treasurer if they have existing Trust Account or Bank Certificate for new Trust Account
3. Subproject Implementation Schedule
4. Annual Investment Plan/Annual Budget Plan
5. Geo-resistivity Study for new construction with underground water source to determine the availability and quantity of the water source
6. Certification from Municipal Engineer that the source is adequate to serve the intended service area. The Proponent LGU may engage accredited technical service provider to conduct the source validation
7. Copy of the receipt issued by the water testing center/laboratory accredited by DOH as proof of conduct water potability test.
Should you need further clarification, you may contact (________________________) (NAME OF CONTACT PERSON) at telephone number XXX-XXX-XX-XX.
Anticipating for your positive response.
Sincerely,
(NAME OF LCE)
ANNEX D
Subproject Implementation Schedule
SALINTUBIG Program — DILG Fund__________________________________
Subproject Implementation Schedule
| Project Title: ______________________ | ||||
|
|
|
|
Timelines
|
|
|
Sn
|
Activity
|
Duration
|
Start
|
Finish
|
| 1 | DED PREPARATION |
___________
|
___________
|
___________
|
| 1.01 | Preparation of DED |
___________
|
___________
|
___________
|
| 1.02 | Submission to DILG |
___________
|
___________
|
___________
|
| 2 | SUBPROJECT REVIEW/ |
|
|
|
| APPROVAL |
___________
|
___________
|
___________
|
|
| 2.01 | Endorsement to PTWG/PDMU |
___________
|
___________
|
___________
|
| 2.02 | Review by PTWG/PDMU |
___________
|
___________
|
___________
|
| 2.03 | Approval by DILG Provincial/ |
|
|
|
| Regional Director |
___________
|
___________
|
___________
|
|
| 2.04 | Confirmation letter to LGU on the |
|
|
|
| Approval of the DED |
___________
|
___________
|
___________
|
|
| 3 | PROCUREMENT PROCESS |
___________
|
___________
|
___________
|
| 3.01 | Bid Preparation |
___________
|
___________
|
___________
|
| 3.02 | Pre-Procurement Conference |
___________
|
___________
|
___________
|
| 3.03 | Ad/Posting ITB |
___________
|
___________
|
___________
|
| 3.04 | Pre-bid Conference |
___________
|
___________
|
___________
|
| 3.05 | Submission and Receipts of Bids |
___________
|
___________
|
___________
|
| 3.06 | Opening of Bids |
___________
|
___________
|
___________
|
| 3.07 | Bid Evaluation |
___________
|
___________
|
___________
|
| 3.08 | Post Qualification |
___________
|
___________
|
___________
|
| 3.09 | Issuance at BAC Resolution w/BER |
___________
|
___________
|
___________
|
| 3.1 | Issuance of Notice of Award |
___________
|
___________
|
___________
|
| 3.11 | Contract Signing |
___________
|
___________
|
___________
|
| 3.12 | Issuance of Notice to Proceed |
___________
|
___________
|
___________
|
| 4 | CONSTRUCTION/ |
|
|
|
| IMPLEMENTATION |
|
|
|
|
| (Indicative Duration based on POW) |
___________
|
___________
|
___________
|
|
| 4.01 | Mobilization |
___________
|
___________
|
___________
|
| 4.02 | Implementation |
___________
|
___________
|
___________
|
| 4.03 | Punch Listing |
___________
|
___________
|
___________
|
| 4.04 | Acceptance |
___________
|
___________
|
___________
|
| Prepared by: | Approved by: | |||
|
______________________________
|
________________________
|
|||
|
Provincial/City/Municipal Engineer
|
Governor/Mayor
|
|||
| Concurred by: | ||||
|
________________________
|
||||
|
DILG Provincial Director
|
ANNEX E
Checklist for Documentary Requirements for Submission of SFS
Republic of the PhilippinesDepartment of the Interior and Local GovernmentProvincial Office of ________, Region _____
List of Documentary Requirements for Submission of
NAME OF LGU: ______________________________
PROVINCE: ______________________________
SUB-PROJECT TITLE: ______________________________
DILG FUND SUBSIDY: ______________________________
|
Item
|
|
|
|
|
|
No.
|
Documents
|
Present
|
Absent
|
Remarks
|
| Basic Requirements | ||||
| 1 | Official Letter submitting the required | |||
| documents signed by the LCE | __________ | __________ | ______________ | |
| 2 | Simplified Feasibility Study (SFS) for | |||
| water supply or Project Brief/Profile | ||||
| for evacuation center | __________ | __________ | ______________ | |
| 3 | Certification from the Treasurer if they | |||
| have existing Trust Account or Bank | ||||
| Certificate for new Trust Account, | ||||
| specifying the Bank Name and Branch | ||||
| and Account Name and Number | __________ | __________ | ______________ | |
| 4 | Subproject Implementation Schedule | |||
| showing the duration, target start and | ||||
| finish of each milestone from DED | ||||
| preparation up to subproject completion | __________ | __________ | ______________ | |
| 5 | Annual Investment Plan/Annual Budget | |||
| Plan if the total subproject cost is more | ||||
| than the DILG Allocation | __________ | __________ | ______________ | |
| 6 | Geo-resistivity Study for new | |||
| construction with underground water | ||||
| source to determine the availability and | ||||
| quantity of the water source | __________ | __________ | ______________ | |
| 7 | Certification from Municipal Engineer | |||
| that the source is adequate to serve the | ||||
| intended service area. The Proponent | ||||
| LGU may engage accredited technical | ||||
| service provider to conduct the source | ||||
| validation | __________ | __________ | ______________ | |
| 8 | Copy of the receipt issued by the water | |||
| testing center/laboratory accredited by | ||||
| DOH as proof of conduct of water | ||||
| potability test | __________ | __________ | ______________ | |
| Check for Completeness by: | Noted by: | |||
|
___________________________
|
________________________
|
|||
|
MLGOO
|
DILG Provincial Director
|
ANNEX F
Checklist of Documentary Requirements for MOA Signing
Republic of the PhilippinesDepartment of the Interior and Local GovernmentRegional Office (___)
List of Documentary Requirements for MOA SigningSALINTUBIG PROGRAM 2016
NAME OF LGU: ______________________________
PROVINCE: ______________________________
SUB-PROJECT: ______________________________
DILG FUND SUBSIDY: ______________________________
|
Item
|
|
|
|
|
|
No.
|
Documents
|
Present
|
Absent
|
Remarks
|
| Basic Requirements | ||||
| 1 | Official Letter submitting the required | |||
| documents signed by the LCE |
__________
|
__________
|
______________
|
|
| 2 | Simplified Feasibility Study (SFS) for |
|
|
|
| water supply or Project Brief/Profile |
|
|
|
|
| for evacuation center |
__________
|
__________
|
______________
|
|
| 3 | Certification from the Treasurer if they |
|
|
|
| have existing Trust Account or Bank |
|
|
|
|
| Certificate for new Trust Account, |
|
|
|
|
| specifying the Bank Name and Branch |
|
|
|
|
| and Account Name and Number |
__________
|
__________
|
______________
|
|
| 4 | Subproject Implementation Schedule |
|
|
|
| showing the duration, target start and |
|
|
|
|
| finish of each milestone from DED |
|
|
|
|
| preparation up to subproject completion |
__________
|
__________
|
______________
|
|
| 5 | Annual Investment Plan/Annual Budget |
|
|
|
| Plan if the total subproject cost is more |
|
|
|
|
| than the DILG Allocation |
__________
|
__________
|
______________
|
|
| 6 | Geo-resistivity Study for new |
|
|
|
| construction with underground water |
|
|
|
|
| source to determine the availability and |
|
|
|
|
| quantity of the water source |
__________
|
__________
|
______________
|
|
| 7 | Certification from Municipal Engineer |
|
|
|
| that the source is adequate to serve the |
|
|
|
|
| intended service area. The Proponent |
|
|
|
|
| LGU may engage accredited technical |
|
|
|
|
| service provider to conduct the source |
|
|
|
|
| validation |
__________
|
__________
|
______________
|
|
| 8 | Copy of the receipt issued by the water |
|
|
|
| testing center/laboratory accredited by |
|
|
|
|
| DOH as proof of conduct of water |
|
|
|
|
| potability test |
__________
|
__________
|
______________
|
|
| Additional Requirement for MOA Signing |
|
|
|
|
| 1 | Sangguniang Panlalawigan/Bayan |
|
|
|
| (SP/SB) Resolution authorizing the LCE |
|
|
|
|
| to enter into MOA with DILG |
__________
|
__________
|
______________
|
|
| 2 | Recommendation report on the |
|
|
|
| subproject from reviewing body |
|
|
|
|
| indicating whether the subproject is |
|
|
|
|
| approved or disapproved |
__________
|
__________
|
______________
|
|
| 3 | Memorandum of Agreement (MOA) |
|
|
|
| already signed by the LCE and for RD's |
|
|
|
|
| signature |
__________
|
__________
|
______________
|
|
| Check and Reviewed by: | Approved by: | |||
|
___________________________
|
__________________________________
|
|||
|
PTWG/PDMU Head
|
Provincial Director/Regional Director
|
ANNEX G
SALINTUBIG MOA between LGU and DILG
Memorandum of Agreement (MOA)For the Implementation of the Provision for Potable Water
KNOWN ALL MEN BY THESE PRESENTS:
This Agreement made and executed into this ___ day of _____ 201__ by and between:
The DEPARTMENT OF THE INTERIOR AND LOCAL GOVERNMENT, a national government agency represented herein by its Regional Director, ___________________________, Region ___________ with office address at __________________________________, hereinafter referred to as the "DILG".
-and-
The City/Municipality of ___________________ a local government unit (LGU) in the ______________ Region, duly established under the laws of the Republic of the Philippines, with address at __________________________________ herein represented by its Governor/City Mayor/Municipal Mayor Hon. _______________________________, hereinafter referred to as the "Implementing Partner".
WITNESSETH
WHEREAS, The Government continuous to implement Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program to pursue its commitment to provide water particularly for the poor and waterless communities;
WHEREAS, The Program aims to contribute to the attainment of the goal of providing potable water to the entire country and the targets defined in the Philippine Development Plan 2011-2016, Millennium Development Goals (MDG), and the Philippine Water Supply Sector Roadmap and the Philippine Sustainable Sanitation Roadmap;
WHEREAS, the DILG is the lead executing agency responsible for the provision of grant financing and capacity development to increase access to water and sanitation services and improve capacities of the Local Government Units (LGUs) and Water Service Providers (WSPs) in the planning, implementation and management of water supply facilities in a sustainable manner;
WHEREAS, provision for potable water supply are allocated in the FY 2016 budget of the DILG under Republic Act 10717 (FY 2016 General Appropriations Act);
WHEREAS, the City/Municipality of _________________ has been identified by Program as one of the priority areas and had complied with all the requirements;
WHEREAS, the City/Municipality has proposed the subproject in Article 1 Section 1.1 of this Agreement;
NOW, THEREFORE, for and in consideration of the foregoing premises, the parties to this Agreement do hereby agree on the following terms and conditions:
ARTICLE I
Scope
Section 1.1. This Memorandum of Agreement (MOA) covers the implementation of the following 201__ SALINTUBIG Subproject/s in the Municipality of ________, Province of ______________ in accordance with DILG Memorandum No. ___ 201___ — Guidelines for the Implementation Provision for Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG), herein referred to as the "SALINTUBIG Guidelines", which forms an integral part of this Agreement.
|
|
Sub-
|
|
|
|
Allocation
|
|
|
Subprojects
|
Proj.
|
Target
|
HH
|
DILG
|
LGU
|
Total
|
|
Title
|
ID No.
|
Barangay/s
|
Served
|
Allocation
|
Counterpart
|
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
|
Total
|
|
|
_________
|
_________
|
_________
|
Section 1.2. The DILG shall make available to the Implementing Partner chargeable against the FY 201__ General Appropriation Act to finance the subproject/s stipulated in Section 1.1 above, not to exceed the aggregate amount of ___________________________________________, (amount in words) _________________ (Php) subject to the terms and conditions of this Agreement.
Section 1.3. The funds shall be released after signing of this Memorandum of Agreement (MOA) in accordance with the provision in the SALINTUBIGGuidelines. The Implementing Partner shall submit to DILG within sixty (60) days after the release of fund, the Technical Specifications or Detailed Engineering Design (DED), whichever is applicable, and other required documents stipulated in SALINTUBIGGuidelines. The DILG shall review and approve/disapprove the submitted documents within fifteen (15) days provided that the documents are complete and compliant with the requirements stated in SALINTUBIGGuidelines. The Implementing Partner can only utilize the funds after the DILG approval of the Technical Design or DED, whichever is applicable, and other supporting documents.
Section 1.4. In case the Implementing Partner fails to submit the required documents within the prescribed period, the DILG-RO shall advise and notify the concerned LGU and require them to explain the reason for its non-submission. If after validation and evaluation, the reason is found not acceptable or after due course the LGU has no action, the DILG Regional Office shall issue a Demand Letter, copy furnish Local COA Auditor, requiring the Implementing Partner to return all the released amount to the DILG Region Office as the source agency. In such a case, the project shall be deemed cancelled.
Section 1.5. Implementing Partner shall also be required to comply with the timelines stipulated in Annex A (Implementation Schedule) of this MOA. Failure to comply with the agreed period, the DILG shall have the option to terminate the project as stipulated in Article III of this MOA. The DILG has also the option to transfer of the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
Section 1.6. In case the subproject/s cost is/are more than the allocation as stipulated in Section 1.1, the Implementing Partner shall provide cash counterpart equivalent to the excess in subproject allocation.
Section 1.7. The Implementing Partner shall also provide counterpart fund to cover administrative costs (e.g., office supplies, local travelling expenses, communication, honoraria, meetings and consultations, salaries, and any other related monitoring and construction supervision expenses) of Implementing Partner personnel overseeing and monitoring the subproject. ITAaHc
ARTICLE II
Other Covenants
Section 2.1. The Implementing Partner shall take out and maintain with responsible insurers such insurances, against such risk and in such amounts as shall be consistent with appropriate government and/or business practices to cover:
a. Hazards incidental to acquisition, transportation and delivery of goods financed out of the Fund to the place of installation.
b. Risk of fire, flood and other damages to the facilities constructed in whole or part out of the Fund.
Section 2.2. Upon the issuance of Certificate of Acceptance the Implementing Partner shall:
a. Take out and maintain with responsible insurers such insurances, against such risk and in such amounts as shall be consistent with appropriate government and/or business practices to cover risk of fire, flood and other damages to the facilities constructed in whole or part out of the Fund.
b. Operate and maintain, or cause to be operated and maintained property, the facility provided under the Project and shall include in their annual appropriation funds for the maintenance and operation of the completed facility.
Section 2.3. Any notice or request or permission to be given or made in this Agreement shall be in writing and shall be deemed to have been duly given or made when it is delivered in the case of DILG to ________________________________ (office address) and in the case of the Implementing Partner to ____________________________, (office address) or such other addresses which the parties hereto may specify in writing.
a. Any action required or permitted to be taken, and any documents required or permitted to be executed under this Agreement on behalf of DILG may be taken or executed by the DILG Regional Director of Region _____ or his/her authorized representative.
b. Any action required or permitted to be taken, and any documents required or permitted to be executed under this Agreement on behalf of Implementing Partner may be taken or executed by the Provincial Governor/City Mayor/Municipal Mayor or such persons as he/she shall designate in writing.
Section 2.4. In no case shall the fund transferred be utilized for the payment of additional compensation to employees in the form of allowances, incentive pay, bonuses, honorarium, or other forms of additional compensation, except as may be authorized by law or existing regulations, nor shall it be used to create new positions, to augment salaries of regular personnel.
Section 2.5. By mutual consent, this Agreement or any part thereof may be changed, modified, revised and amended or supplemented for the purpose of effective implementation and management of the Subproject/s. All other parties concerned shall be notified/informed of such changes, revisions and amendments.
Section 2.6. All disputes or controversies between the parties arising out or in connection with this Agreement, which is not settled, between the parties shall be elevated initially to the DILG-Central Office.
ARTICLE III
Termination or Suspension
Section 3.1. The DILG reserves the right to:
a. Terminate/Cancel the implementation of the subprojects in following instances:
• Implementing Partner non-compliance to prescribed processes, standards, requirements and timelines stipulated in Annex A
• Occurrence of fraudulent practices
• Occurrence of force majeure where it becomes improbable for the projects to continue to be carried out
In such case that the subproject/s are partially or fully cancelled due to the fault of the Implementing Partner, the Implementing Partner shall be obliged to return the spent amount and the unexpended balance of the released portion of the funds of the pertinent portions related to the cancelled component.
b. Suspend/Withhold the release of the final tranche in the following instances:
• Implementing Partner is performing unsatisfactorily in the implementation and execution of the project or in the event that substantial slippage in implementation is incurred.
• Extraordinary conditions such as force majeure, fortuitous events and the like which shall make it necessary to suspend the implementation of the project.
c. File the appropriate civil, criminal and/or administrative case against the concerned local public official/s for acts or omissions in relation to the performance of their duties under this Memorandum Circular.
Section 3.2. Implementing Partner will be given one month to resolve the issue, improve performance or remedy the situation. However, termination will be resorted to only, if Implementing Partner, having been duly notified, do not make any effort to institute measure that will address issues at hand.
ARTICLE IV
Anti-Graft and Corruption Practices Act
Section 4.1. Neither of the parties to this Agreement shall unduly benefit from each other nor gain anything which is disadvantageous to the Government, and in violation of Republic Act No. 3019, as amended, otherwise known as the Anti-graft and Corrupt Practices Act.
ARTICLE V
Effectivity of the Agreement
Section 5.1. This Agreement shall take effect immediately upon approval and signing by the contracting parties and shall remain in force and effect until the completion of the subproject/s and the requirements stipulated under this MOA and the accompanying SALINTUBIGGuidelines, unless sooner terminated.
IN WITNESS WHEREOF, the Parties hereto, acting through their representatives thereto authorized, have caused this Agreement to be signed in their respective names in ___________, Philippines on _____ day of ______________ 201____.
|
PROVINCE/CITY/MUNICIPALITY of
|
DEPARTMENT OF THE INTERIOR
|
|
______________________________
|
AND LOCAL GOVERNMENT
|
|
(LGU Name)
|
|
|
______________________________
|
______________________________
|
|
Governor/Mayor
|
DILG Regional Director
|
WITNESSES
|
______________________________
|
______________________________
|
|
______________________________
|
______________________________
|
Acknowledgment
Republic of the Philippines)
BEFORE ME, a Notary Public for and in ______________________________, this ________ day of ___________________ 201____, personally appeared the following:
Name Gov't. issued ID No./Date and Place Issued
1. (Governor/Mayor) _____________________________________
2. (Regional Director) _____________________________________
both known to me to be the same persons who executed the foregoing instruments and acknowledged to me that the same is their own free and voluntary act of deed.
This instrument refers to a Memorandum of Agreement consisting of ______ () pages including this page where the acknowledgement is duly written, has been signed by the parties and their instrumental witnesses on each and every page thereof.
WITNESS MY HAND AND NOTARIAL SEAL.
Doc. No. ______________;
SALINTUBIG MOA — Subproject Implementation Schedule
SALINTUBIG ProgramName of Implementing Partner
Subproject Implementation Schedule
| Project Title: ______________________ | ||||
|
|
|
|
Timelines
|
|
|
Sn
|
Activity
|
Duration
|
Start
|
Finish
|
| 1 | DED PREPARATION |
___________
|
___________
|
___________
|
| 1.01 | Preparation DED |
___________
|
___________
|
___________
|
| 1.02 | Submission to DILG |
___________
|
___________
|
___________
|
| 2 | SUBPROJECT REVIEW/ |
|
|
|
| APPROVAL |
___________
|
___________
|
___________
|
|
| 2.01 | Endorsement to PTWG/PDMU |
___________
|
___________
|
___________
|
| 2.02 | Review by PTWG/PDMU |
___________
|
___________
|
___________
|
| 2.03 | Approval by DILG Provincial/ |
|
|
|
| Regional Director |
___________
|
___________
|
___________
|
|
| 2.04 | Confirmation letter to LGU on the |
|
|
|
| Approval of the DED |
___________
|
___________
|
___________
|
|
| 3 | PROCUREMENT PROCESS |
___________
|
___________
|
___________
|
| 3.01 | Bid Preparation |
___________
|
___________
|
___________
|
| 3.02 | Pre-Procurement Conference |
___________
|
___________
|
___________
|
| 3.03 | Ad/Posting ITB |
___________
|
___________
|
___________
|
| 3.04 | Pre-bid Conference |
___________
|
___________
|
___________
|
| 3.05 | Submission and Receipts of Bids |
___________
|
___________
|
___________
|
| 3.06 | Opening of Bids |
___________
|
___________
|
___________
|
| 3.07 | Bid Evaluation |
___________
|
___________
|
___________
|
| 3.08 | Post Qualification |
___________
|
___________
|
___________
|
| 3.09 | Issuance at BAC Resolution w/BER |
___________
|
___________
|
___________
|
| 3.1 | Issuance of Notice of Award |
___________
|
___________
|
___________
|
| 3.11 | Contract Signing |
___________
|
___________
|
___________
|
| 3.12 | Issuance of Notice to Proceed |
___________
|
___________
|
___________
|
| 4 | CONSTRUCTION/ |
|
|
|
| IMPLEMENTATION |
|
|
|
|
| (Subject for change with the actual |
|
|
|
|
| contract agreement with the winning |
|
|
|
|
| bidder) |
___________
|
___________
|
___________
|
|
| 4.01 | Mobilization |
___________
|
___________
|
___________
|
| 4.02 | Implementation |
___________
|
___________
|
___________
|
| 4.03 | Punch Listing |
___________
|
___________
|
___________
|
| 4.04 | Acceptance |
___________
|
___________
|
___________
|
| Prepared by: |
Approved by:
|
|||
|
______________________________
|
________________________
|
|||
|
Provincial/City/Municipal Engineer
|
Governor/Mayor
|
|||
| Concurred by: | ||||
|
________________________
|
||||
|
DILG Provincial Director
|
ANNEX H
SALINTUBIG MOA (Tripartite)
Memorandum of Agreement (MOA)
KNOWN ALL MEN BY THESE PRESENTS:
This Agreement made and executed into this ___ day of ____ 201__ by and between:
The DEPARTMENT OF THE INTERIOR AND LOCAL GOVERNMENT, a national government agency (NGA) represented herein by its Regional Director, _____________________________, Region _____ with office address at _____________________________, hereinafter referred to as the "DILG".
The _______________________ of ___________________ a local government unit (LGU)/NGA in the _____________________ Region, duly established under the laws of the Republic of the Philippines, with address at __________________________________________________________________________________________________________________________ herein represented by its ________________________________________, Hon. ____________________________________, hereinafter referred to as the "Implementing Partner". CHTAIc
-and-
The City/Municipality of ___________________ a local government unit (LGU) in the ________________ Region, duly established under the laws of the Republic of the Philippines, with address at ____________________________________________________________________________________ herein represented by its City Mayor/Municipal Mayor, Hon. _________________________________, hereinafter referred to as the "Proponent LGU".
WITNESSETH
WHEREAS, The Government continuous to implement Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program to pursue its commitment to provide water particularly for the poor and waterless communities;
WHEREAS, The Program aims to contribute to the attainment of the goal of providing potable water to the entire country and the targets defined in the Philippine Development Plan 2011-2016, Millennium Development Goals (MDG), and the Philippine Water Supply Sector Roadmap and the Philippine Sustainable Sanitation Roadmap;
WHEREAS, the DILG is the lead executing agency responsible for the provision of grant financing and capacity development to increase access to water and sanitation services and improve capacities of the Local Government Units (LGUs) and Water Service Providers (WSPs) in the planning, implementation and management of water supply facilities in a sustainable manner;
WHEREAS, provision for potable water supply are allocated in the FY 2016 budget of the DILG under Republic Act 10717 (FY 2016 General Appropriations Act);
WHEREAS, the City/Municipality of _________________ has been identified by Program as one of the priority areas and had complied with all the requirements;
WHEREAS, the City/Municipality has proposed the subproject in Article 4 Section 1.1of this Agreement;
NOW, THEREFORE, for and in consideration of the foregoing premises, the parties to this Agreement do hereby agree on the following terms and conditions:
ARTICLE I
Scope
Section 1.1. This Memorandum of Agreement (MOA) covers the implementation of the following 201___ SALINTUBIG Subproject/s in the Municipality of _______, Province of ____________ in accordance with DILG Memorandum No. ____ 201___ — Guidelines for the Implementation Provision for Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program herein referred to as the "SALINTUBIG Guidelines", which forms an integral part of this Agreement.
|
|
Sub-
|
|
|
|
Allocation
|
|
|
Subprojects
|
Proj.
|
Target
|
HH
|
DILG
|
LGU
|
Total
|
|
Title
|
ID No.
|
Barangay/s
|
Served
|
Allocation
|
Counterpart
|
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
_____________
|
________
|
__________
|
_________
|
_________
|
_________
|
_________
|
|
|
|
Total
|
|
_________
|
_________
|
_________
|
Section 1.2. The DILG shall make available to the Implementing Partner chargeable against the FY 201___ General Appropriation Act to finance the subproject/s stipulated in Section 1.1 above, not to exceed the aggregate amount of ______________________________________________, (amount in words), _________________________________ (Php) subject to the terms and conditions of this Agreement.
Section 1.3. The funds shall be released after signing of this Memorandum of Agreement (MOA) in accordance with the provision in the SALINTUBIG Guidelines. The Implementing Partner shall submit to DILG within sixty (60) days after the release of fund, the Technical Specifications or Detailed Engineering Design (DED), whichever is applicable, and other required documents stipulated in the SALINTUBIG Guidelines. The DILG shall review and approve/disapprove the submitted documents within fifteen (15) days provided that the documents are complete and compliant with the requirements stated in SALINTUBIG Guidelines. The Implementing Partner can only utilize the funds after the DILG approval of the Technical Design or DED, whichever is applicable, and other supporting documents.
Section 1.4. In case the Implementing Partner fails to submit the required documents within the prescribed period, the DILG-RO shall advise and notify the concerned LGU and require them to explain the reason for its non-submission. If after validation and evaluation, the reason is found not acceptable or after due course the LGU has no action, the DILG Regional Office shall issue a Demand Letter requiring the Implementing Partner to return all the released amount to the DILG Regional Office as the source agency. In such a case, the project shall be deemed cancelled.
Section 1.5. Implementing Partner shall also be required to comply with the timelines stipulated in Annex A (Implementation Schedule) of this MOA. Failure to comply with the agreed period, the DILG shall have the option to terminate the project as stipulated in Article III of this MOA. The DILG has also the option to transfer the LGU Budget Allocation to other eligible LGU within the Region in need of water supply and with good record in implementing subprojects.
Section 1.6. In case the subproject/s cost is/are more than the allocation as stipulated in Section 1.1, the Proponent LGU shall provide cash counterpart equivalent to the excess in subproject/s allocation and shall transfer the said amount to the Implementing Partner.
Section 1.7. The Proponent LGU shall also provide counterpart in cash or in kind to finance the preparatory activities and monitoring in the implementation of the subproject/s.
ARTICLE II
Other Covenants
Section 2.1. The Proponent LGU shall take out and maintain with responsible insurers such insurances, against such risk and in such amounts as shall be consistent with appropriate government and/or business practices to cover:
a. Hazards incidental to acquisition, transportation and delivery of goods financed out of the Fund to the place of installation.
b. Risk of fire, flood and other damages to the facilities constructed in whole or part out of the Fund.
Section 2.2. Upon the issuance of Certificate of Acceptance the Proponent LGU shall:
a. Take out and maintain with responsible insurers such insurances, against such risk and in such amounts as shall be consistent with appropriate government and/or business practices to cover risk of fire, flood and other damages to the facilities constructed in whole or part out of the Fund.
b. Operate and maintain, or cause to be operated and maintained properly, the facility provided under the Project and shall include in their annual appropriation funds for the maintenance and operation of the completed facility.
Section 2.3. Any notice or request or permission to be given or made in this Agreement shall be in writing and shall be deemed to have been duly given or made when it is delivered in the case of DILG to _______________________________, (office address) in the case of the Implementing Partner to _______________________________________ (office address) and in the case of the Proponent LGU to ___________________________ (office address) or such other addresses which the parties hereto may specify in writing.
a. Any action required or permitted to be taken, and any documents required or permitted to be executed under this Agreement on behalf of DILG may be taken or executed by the DILG Regional Director of Region ___ or his/her authorized representative.
b. Any action required or permitted to be taken, and any documents required or permitted to be executed under this Agreement on behalf of Implementing Partner may be taken or executed by the ____________________________ or such persons as he/she shall designate in writing.
c. Any action required or permitted to be taken, and any documents required or permitted to be executed under this Agreement on behalf of Proponent LGU may be taken or executed by the City Mayor/Municipal Mayor or such persons as he/she shall designate in writing.
Section 2.4. In no case shall the fund transferred be utilized for the payment of additional compensation to employees in the form of allowances, incentive pay, bonuses, honorarium, or other forms of additional compensation, except as may be authorized by law or existing regulations, nor shall it be used to create new positions, to augment salaries of regular personnel.
Section 2.5. By mutual consent, this Agreement or any part thereof may be changed, modified, revised and amended or supplemented for the purpose of effective implementation and management of the Subproject/s. All other parties concerned shall be notified/informed of such changes, revisions and amendments.
Section 2.6. All disputes or controversies between the parties arising out or in connection with this Agreement, which is not settled, between the parties shall be elevated initially to DILG-Central Office.
ARTICLE III
Termination or Suspension
Section 3.1. The DILG reserves the right to:
a. Terminate/Cancel the implementation of the subprojects in following instances:
• Implementing Partner non-compliance to prescribed processes, standards, requirements and timelines stipulated in Annex A
• Occurrence of fraudulent practices
• Occurrence of force majeure where it becomes improbable for the projects to continue to be carried out
In such case that the subproject/s are partially or fully cancelled due to the fault of the Implementing Partner, the Implementing Partner shall be obliged to return the spent amount and the unexpended balance of the released portion of the funds of the pertinent portions related to the cancelled component.
b. Suspend/Withhold the release of the final tranche in the following instances:
• Implementing Partner is performing unsatisfactorily in the implementation and execution of the project or in the event that substantial slippage in implementation is incurred.
• Extraordinary conditions such as force majeure, fortuitous events and the like which shall make it necessary to suspend the implementation of the project. EATCcI
c. File the appropriate civil, criminal and/or administrative case against the concerned local public official/s for acts or omissions in relation to the performance of their duties under this Memorandum Circular.
Section 3.2. Implementing Partner will be given one month to resolve the issue, improve performance or remedy the situation. However, termination will be resorted to only, if Implementing Partner, having been duly notified, do not make any effort to institute measure that will address issues at hand.
ARTICLE IV
Anti-Graft and Corruption Practices Act
Section 4.1. Neither of the parties to this Agreement shall unduly benefit from each other nor gain anything which is disadvantageous to the Government, and in violation of Republic Act No. 3019, as amended, otherwise known as the Anti-graft and Corrupt Practices Act.
ARTICLE V
Effectivity of the Agreement
Section 5.1. This Agreement shall take effect immediately upon approval and signing by the contracting parties and shall remain in force and effect until the completion of the subproject/s and the requirements stipulated under this MOA and the accompanying Guidelines in the Management of the SALINTUBIG Fund, unless sooner terminated.
IN WITNESS WHEREOF, the Parties hereto, acting through their representatives thereto authorized, have caused this Agreement to be signed in their respective names in _________, Philippines on ____ day of ___________ 201___.
|
PROVINCE of __________________
|
CITY/MUNICIPALITY of (LGU Name)
|
|
_______________________________
|
______________________________
|
|
Governor
|
Mayor
|
DEPARTMENT OF THE INTERIOR
___________________________
WITNESSES
|
_______________________________
|
_______________________________
|
|
_______________________________
|
_______________________________
|
Acknowledgment
Republic of the Philippines)
BEFORE ME, a Notary Public for and in __________________________, this ____day of _________________ 201___, personally appeared the following:
|
Name
|
Gov't. Issued ID No./Date and Place Issued
|
|
|
1
|
(Mayor) |
_____________________________________
|
|
2
|
(Governor) |
_____________________________________
|
|
3
|
(Regional Director) |
_____________________________________
|
known to me to be the same persons who executed the foregoing instruments and acknowledged to me that the same is their own free and voluntary act of deed.
This instrument refers to a Memorandum of Agreement consisting of _______ (____) pages including this page where the acknowledgement is duly written, has been signed by the parties and their instrumental witnesses on each and every page thereof.
WITNESS MY HAND AND NOTARIAL SEAL.
Doc. No. ______________;
SALINTUBIG MOA (Tripartite) — Subproject Implementation Schedule
SALINTUBIG ProgramName of Implementing Partner
Subproject Implementation Schedule
| Project Title: ______________________ | ||||
|
|
Timelines
|
|
||
|
Sn
|
Activity
|
Duration
|
Start
|
Finish
|
|
1
|
DED PREPARATION |
___________
|
___________
|
___________
|
|
1.01
|
Preparation DED |
___________
|
___________
|
___________
|
|
1.02
|
Submission to DILG |
___________
|
___________
|
___________
|
|
2
|
SUBPROJECT REVIEW/ |
|
|
|
|
|
APPROVAL |
___________
|
___________
|
___________
|
|
2.01
|
Endorsement to PTWG/PDMU |
___________
|
___________
|
___________
|
|
2.02
|
Review by PTWG/PDMU |
___________
|
___________
|
___________
|
|
2.03
|
Approval by DILG Provincial/ |
|
|
|
|
|
Regional Director |
___________
|
___________
|
___________
|
|
2.04
|
Confirmation letter to LGU on the |
|
|
|
|
|
Approval of the DED |
___________
|
___________
|
___________
|
|
3
|
PROCUREMENT PROCESS |
___________
|
___________
|
___________
|
|
3.01
|
Bid Preparation |
___________
|
___________
|
___________
|
|
3.02
|
Pre-Procurement Conference |
___________
|
___________
|
___________
|
|
3.03
|
Ad/Posting ITB |
___________
|
___________
|
___________
|
|
3.04
|
Pre-bid Conference |
___________
|
___________
|
___________
|
|
3.05
|
Submission and Receipts of Bids |
___________
|
___________
|
___________
|
|
3.06
|
Opening of Bids |
___________
|
___________
|
___________
|
|
3.07
|
Bid Evaluation |
___________
|
___________
|
___________
|
|
3.08
|
Post Qualification |
___________
|
___________
|
___________
|
|
3.09
|
Issuance at BAC Resolution w/BER |
___________
|
___________
|
___________
|
|
3.1
|
Issuance of Notice of Award |
___________
|
___________
|
___________
|
|
3.11
|
Contract Signing |
___________
|
___________
|
___________
|
|
3.12
|
Issuance of Notice to Proceed |
___________
|
___________
|
___________
|
|
4
|
CONSTRUCTION/ |
|
|
|
|
|
IMPLEMENTATION |
___________
|
___________
|
___________
|
|
4.01
|
Mobilization |
___________
|
___________
|
___________
|
|
4.02
|
Implementation |
___________
|
___________
|
___________
|
|
4.03
|
Punch Listing |
___________
|
___________
|
___________
|
|
4.04
|
Acceptance |
___________
|
___________
|
___________
|
| Prepared by: | Approved by: | |||
|
______________________________
|
________________________
|
|||
|
Provincial/City/Municipal Engineer
|
Governor/Mayor
|
|||
| Concurred by: | ||||
|
________________________
|
||||
|
DILG Provincial Director
|
ANNEX I
CAF Format
CAF No. _______
Certification of Availability of Funds (CAF)
Pursuant to the provisions of RA ____ (FY 201___ General Appropriations Act), the amount of ____________________________________________________ (amount in words of the total Regional Allocation) (Php_____________________________ amount in figures) has been allocated to DILG Region ___ for the implementation of ________________________________ (name of Program/Project) and booked-up by this Office under Fund 101.
This Office hereby certifies that a portion of the said appropriations is available for the Province/City/Municipality of ______________________ (name of LGU) amounting to ___________________________________________________________ (amount in words based on the signed MOA) (Php_______________________ amount in figures) and shall be charged against the abovementioned appropriations to finance the following ___________________ Fund Sub-projects:
|
Project Title
|
Amount
|
|
| 1. | __________________________________ |
_________________
|
| 2 | __________________________________ |
_________________
|
| 3 | __________________________________ |
_________________
|
| TOTAL |
_________________
|
The corresponding cash shall be released in accordance with the signed Memorandum of Agreement (MOA) between the DILG Region and the Province/City/Municipality of ______________________ (name of LGU) signed on _____________________ 201__ and the Guidelines for the Implementation of SALINTUBIG Program No. ___ Series 201___). Tentative cash releases shall be as follows:
|
Project Title
|
First Tranche (80%)
|
Second Tranche (20%)
|
|||
|
|
Amount
|
Date
|
Amount
|
Date
|
|
| 1. | ________________ | ___________ | __________ | __________ | _________ |
| 2 | ________________ | ___________ | __________ | __________ | _________ |
| 3 | ________________ | ___________ | __________ | __________ | _________ |
| TOTAL | ___________ | __________ | |||
| Certified correct by: | Approved by: | ||||
|
______________________________
|
__________________________
|
||||
|
DILG Regional Accountant
|
DILG Regional Director
|
ANNEX J
Checklist of Documentary Requirements for 1st tranche release and CAF
Republic of the PhilippinesDepartment of the Interior and Local GovernmentRegional Office (___)
List of Documentary Requirements SALINTUBIG PROGRAM 2016
NAME OF LGU: ______________________________
PROVINCE: ______________________________
SUB-PROJECT: ______________________________
DILG FUND SUBSIDY: ______________________________
|
Item
|
|
|
|
|
|
No.
|
Documents
|
Present
|
Absent
|
Remarks
|
| Basic Requirements | ||||
| 1 | Official Letter submitting the required | |||
| documents signed by the LCE |
__________
|
__________
|
______________
|
|
| 2 | Simplified Feasibility Study (SFS) for |
|
|
|
| water supply or Project Brief/Profile |
|
|
|
|
| for evacuation center |
__________
|
__________
|
______________
|
|
| 3 | Certification from the Treasurer if they |
|
|
|
| have existing Trust Account or Bank |
|
|
|
|
| Certificate for new Trust Account, |
|
|
|
|
| specifying the Bank Name and Branch |
|
|
|
|
| and Account Name and Number |
__________
|
__________
|
______________
|
|
| 4 | Subproject Implementation Schedule |
|
|
|
| showing the duration, target start and |
|
|
|
|
| finish of each milestone from DED |
|
|
|
|
| preparation up to subproject completion |
__________
|
__________
|
______________
|
|
| 5 | Annual Investment Plan/Annual Budget |
|
|
|
| Plan if the total subproject cost is more |
|
|
|
|
| than the DILG Allocation |
__________
|
__________
|
______________
|
|
| 6 | Geo-resistivity Study for new |
|
|
|
| construction with underground water |
|
|
|
|
| source to determine the availability and |
|
|
|
|
| quantity of the water source |
__________
|
__________
|
______________
|
|
| 7 | Certification from Municipal Engineer |
|
|
|
| that the source is adequate to serve the |
|
|
|
|
| intended service area. The Proponent |
|
|
|
|
| LGU may engage accredited technical |
|
|
|
|
| service provider to conduct the source |
|
|
|
|
| validation |
__________
|
__________
|
______________
|
|
| 8 | Copy of the receipt issued by the water |
|
|
|
| testing center/laboratory accredited by |
|
|
|
|
| DOH as proof of conduct of water |
|
|
|
|
| potability test |
__________
|
__________
|
______________
|
|
| Additional Requirement for Obligation/Release of CAF and 1st Tranche |
|
|
||
| 1 | Sangguniang Panlalawigan/Bayan |
|
|
|
| (SP/SB) Resolution authorizing the LCE |
|
|
|
|
| to enter into MOA with DILG |
__________
|
__________
|
______________
|
|
| 2 | Recommendation report on the |
|
|
|
| subproject from reviewing body |
|
|
|
|
| indicating whether the subproject is |
|
|
|
|
| approved or disapproved |
__________
|
__________
|
______________
|
|
| 3 | Perfected Memorandum of Agreement |
|
|
|
| (MOA) already signed by the LCE and |
|
|
|
|
| RD |
__________
|
__________
|
______________
|
|
| Check and Reviewed by: | Approved by: | |||
|
___________________________
|
________________________________
|
|||
|
PTWG/PDMU Head
|
Provincial Director/Regional Director
|
ANNEX K
Documentary Requirements for Technical Specification
Republic of the PhilippinesDepartment of the Interior and Local GovernmentRegional Office (___)
List of Documentary RequirementsSALINTUBIG PROGRAM 2016
NAME OF LGU: ______________________________
PROVINCE: ______________________________
SUB-PROJECT: ______________________________
DILG FUND SUBSIDY: ______________________________
|
Item
|
|
|
|
|
|
No.
|
Documents
|
Present
|
Absent
|
Remarks
|
| Technical Specification | ||||
| 1 | Official Letter submitting the required | |||
| documents signed by the LCE | __________ | __________ | ______________ | |
| 2 | Program of Works (POW) signed | |||
| by the Municipal Engineer and | ||||
| approved by the concerned LCE | __________ | __________ | ______________ | |
| 3 | Technical Drawings signed by the | |||
| approving authorities | __________ | __________ | ______________ | |
| 4 | Bill of Quantities including detailed | |||
| computation (signed and sealed by | ||||
| the approving authorities) | __________ | __________ | ______________ | |
| Necessary Permits, Licenses Certificates and/or Clearances | ||||
| 1 | Application for the issuance of | |||
| Water Permit from deputized | ||||
| agencies of National Water | ||||
| Resources Board (NWRB) | __________ | __________ | ______________ | |
| Check for Completeness by: | Noted by: | |||
|
___________________________
|
________________________________
|
|||
|
C/MLGOO
|
Provincial Director
|
ANNEX L
Documentary Requirements for DED
Republic of the PhilippinesDepartment of the Interior and Local GovernmentRegional Office (___)
List of Documentary RequirementsSALINTUBIG PROGRAM 2016
NAME OF LGU: ______________________________
PROVINCE: ______________________________
SUB-PROJECT: ______________________________
DILG FUND SUBSIDY: ______________________________
|
Item
|
|
|
|
|
|
|
No.
|
Documents
|
Present
|
Absent
|
Remarks
|
|
| Technical Specification | |||||
| 1 | Official Letter submitting the required | ||||
| documents signed by the LCE | __________ | __________ | ______________ | ||
| 2 | Program of Works (POW) signed | ||||
| by the Municipal Engine er and | |||||
| approved by the concerned LCE | __________ | __________ | ______________ | ||
| 3 | Detailed Engineering Designs | ||||
| (DED), plans and drawings (signed | |||||
| and sealed by the approving authorities) | __________ | __________ | ______________ | ||
| 4 | Bill of Quantities including detailed | ||||
| computation (signed and sealed by | |||||
| the approving authorities) | __________ | __________ | ______________ | ||
| 5 | Detailed Design Report for Water | ||||
| Supply | |||||
| • | water demand projection | ||||
| • | hydraulic analysis taking into | ||||
| account the network diagram | |||||
| report and, if necessary | |||||
| geo-resistivity report | __________ | __________ | ______________ | ||
| 6 | Any other supporting documents as | ||||
| may be required | __________ | __________ | ______________ | ||
| Necessary Permits, Licenses, Certificates and/or Clearances | |||||
| 1 | Application for the issuance of | ||||
| Water Permits from deputized | |||||
| agencies of National Water | |||||
| Resources Board (NWRB) | __________ | __________ | ______________ | ||
| Check for Completeness by: | Noted by: | ||||
| ___________________________ | ________________________________ | ||||
| C/MLGOO | Provincial Director |
ANNEX M
Documentary Requirements for DED Approval
Republic of the PhilippinesDepartment of the Interior and Local GovernmentRegional Office (___)
List of Documentary RequirementsSALINTUBIG PROGRAM 2016
NAME OF LGU: ______________________________
PROVINCE: ______________________________
SUB-PROJECT: ______________________________
DILG FUND SUBSIDY: ______________________________
|
Item
|
|
|
|
|
|
|
No.
|
Documents
|
Present
|
Absent
|
Remarks
|
|
| Technical Specification | |||||
| 1 | Official Letter submitting the required | ||||
| documents signed by the LCE | __________ | __________ | ______________ | ||
| 2 | Reviewed Program of Works (POW) | ||||
| signed by the Municipal Engineer | |||||
| and approved by the concerned LCE | __________ | __________ | ______________ | ||
| 3 | Reviewed Detailed Engineering Designs | ||||
| (DED), plans and drawings signed | |||||
| and sealed by the approving authorities | |||||
| or Technical Drawings signed by the | |||||
| approving authorities | __________ | __________ | ______________ | ||
| 4 | Reviewed Bill of Quantities including | ||||
| detailed computation (signed and sealed | |||||
| by the approving authorities) | __________ | __________ | ______________ | ||
| 5 | Reviewed Detailed Design Report for | ||||
| Water Supply | |||||
| • | water demand projection | ||||
| • | hydraulic analysis taking into | ||||
| account the network diagram | |||||
| report and, if necessary, | |||||
| geo-resistivity report | __________ | __________ | ______________ | ||
| 6 | Any other supporting documents as | ||||
| may be required | __________ | __________ | ______________ | ||
| Necessary Permits, Licenses, Certificates and/or Clearances | |||||
| 1 | Application for the issuance of | ||||
| Water Permits from deputized | |||||
| agencies of National Water | |||||
| Resources Board (NWRB) | __________ | __________ | ______________ | ||
| Reviewed by: | Approved by: | ||||
|
___________________________
|
________________________________
|
||||
|
Reviewing Engineer
|
PTWG Head/PDMU Head
|
Noted by:
___________________________
ANNEX N
Procurement Timelines
|
Activities
|
|
Particulars
|
|
| 1. | Advertisement and Posting in | • | Advertisement and Posting in |
| PhilGEPS | PhilGEPS should start simultaneously | ||
| on the same day. | |||
| • | For Infrastructure project above 5M | ||
| and Goods above 2M, advertised is | |||
| done at least once in one (1) | |||
| newspaper of general nationwide | |||
| circulation which has been regularly | |||
| published for at least (2) two years | |||
| before the date of issue of the | |||
| Advertisement. | |||
| • | For infrastructure projects below 5M | ||
| and Goods below 2M, advertisement | |||
| in a newspaper is not mandatory. | |||
| • | Posting in of invitation to Bid in | ||
| PhilGEPS and Conspicuous places | |||
| must be done continuously for (7) | |||
| calendar days. | |||
| 2 | Issuance of Bidding Documents | • | Issuance of Bidding Documents must |
| start from 1st day of Advertisement | |||
| and Posting until the date set for the | |||
| submission and receipt of Bids. | |||
| 3 | Pre Bid Conference | • | Must be conducted at least (12) |
| calendar days before Bid Opening. | |||
| • | Must be conducted at least one (1) for | ||
| contracts with an ABC of 1M and | |||
| above. | |||
| • | For contracts with an ABC of 1M | ||
| below, pre-bid conference may be | |||
| conducted at the discretion of the | |||
| BAC. | |||
| 4 | Supplemental/Bid Bulletin | • | Issuance should at least be seven (7) |
| calendar days before Bid Opening. | |||
| 5 | Submission and Receipt of Bids | • | For Goods, deadline of submission of |
| Bids must be set within (45) calendar | |||
| days from the last day of Posting. | |||
| • | For Infrastructure Projects, deadline of | ||
| submission of Bids must be set within | |||
| fifty (50) calendar days for projects | |||
| 50M and below and sixty-five (65) | |||
| calendar days for projects above 50 M. | |||
| • | Please take note that deadline of | ||
| submission of Bids may be earlier than | |||
| (45) and (65) calendar days. | |||
| 6 | Bid Evaluation | • | Bid Evaluation should be completed |
| within seven (7) calendar days for | |||
| Goods and Infrastructure above 50 M, | |||
| five (5) calendar days for | |||
| Infrastructure 50 M and below. | |||
| • | Bid Evaluation may be completed | ||
| earlier than five (5) and seven (7) | |||
| calendar days, respectively. | |||
| 7 | Post Qualification | • | Post qualification process shall be |
| completed in not more than seven (7) | |||
| calendar days from determination of | |||
| the Lowest Calculated Bid (LCB). | |||
| • | In exceptional cases post qualification | ||
| period may be extended by the Head | |||
| of Procuring Entity (HOPE), but in no | |||
| case shall the aggregate period exceed | |||
| thirty (30) calendar days. | |||
| 8. | Approval of resolution/issuance of | • | Should be done within seven (7) |
| Notice of Award | calendar days for Goods and | ||
| Infrastructure above 50 M, four (4) | |||
| calendar days for infrastructure 50 M | |||
| and below. | |||
| • | The BAC shall post within three (3) | ||
| calendar days from its issuance, the | |||
| NOA in the PhilGEPS, its website and | |||
| conspicuous places. | |||
| 9. | Contract preparation and signing | • | Should be done within ten (10) |
| calendar days from receipt of NOA, | |||
| including the posting of the required | |||
| Performance Security. | |||
| 10 | Approval of Contract by higher | • | Should be done within fifteen (15) |
| authority | calendar days for Goods and | ||
| Infrastructure above 50 M, five (5) | |||
| calendar days for Infrastructure 50 M | |||
| and below. | |||
| • | If no action on the contracts is taken | ||
| by the HOPE or the approving | |||
| authority within the periods specified, | |||
| the contract concerned shall be deemed | |||
| approved. | |||
| 11. | Issuance of Notice to Proceed | • | Should be done within three (3) |
| calendar days for Goods and | |||
| Infrastructure above 50 M, two (2) | |||
| calendar days for Infrastructure 50 M | |||
| and below. | |||
| • | Contract effectivity date shall not be | ||
| later than seven (7) calendar days from | |||
| its issuance. |
ANNEX O
Pre-construction Conference Agenda
Suggested Pre-Construction Conference Agenda
1. Project Matters
1.1 General Contract Data
• Name and No. of Contract
• Name of Contract
• Contract Price Award Date
• Contract Duration
1.2 Scope of Works DHITCc
1.3 Delegation of duties and Responsibilities and Command Structure
1.4 Documents required from contractor
• Performance Bond
• Insurance
• Construction Program
• Form of Agreement
1.5 Drawings of Project Sign Board Possession of Site
1.6 Measurement and Payment
• Measurement Method
• Frequency of Payment
• Contingencies and Dayworks
1.7 Verification of RROW acquisition/LAPP has been completed and that the Contractor has permission to move to the site
1.8 Review and agree the activities, flow-chart, forms and schedules of subproject monitoring and reporting
1.9 Arrange and agree with Contractor's Program of Works
1.10 Obtain from Contractor the List of Sub-contractors for approval by the Implementing Partner
1.11 Request Contractor's Organizational Chart and CVs of personnel for comparison with those included in the bid
1.12. Request Contractor's equipment and manpower utilization schedule for approval of the Implementing Partner
1.13 Possible meeting with public utility authorities to coordinate and resolve possible work conflicts
1.14 Any other business
• Traffic control
• Safety
• Resources Proposed
• Subcontractors
• Environmental Control Project Vehicle add Field Office
• Construction Camp Location
2. Site Matters
2.1 Checks Contractor's shop drawing for signboard to ensure conformity with the Technical Specification, Contract Drawing or as directed by the Project Engineer
2.2 Check's Contractor's mobilization of plant, equipment and personnel is in accordance with those details included in the Bidding documents, and all equipment is in good working condition and calibrated, if necessary
2.3 Arrange with Contractor the operation for verification of quantities
2.4 Arrange with Contractor the procedure for measurement and valuation including printing any necessary forms
2.5 Check the Contractor's identification and quality of material sources
2.6 Identify with Contractor possible areas for disposal of water materials
2.7 Checks Contractor's proposal for safety
2.8 Checks Contractor's proposal to ensure protection of environment
2.9 Verify with Contractor the provision and calibration of laboratory equipment and that the said equipment is sufficient to meet the Minimum Test Requirement of DPWH Standards Specifications and Schedule of Minimum Test Requirements
2.10 Request Contractor to submit Job Mix Formula proposal for Concrete Works
2.11 Organize with Contractor the work-request system plus monitoring, testing and reporting procedures
3. Site Records
3.1 Supervision Reporting and Documentation
• Correspondence to/from Resident Engineer
• Correspondence to/from Contractor
• Correspondence with Other Implementing Partners
• Site Instruction
• Program of works
• Work Request form
• S-Curve reflecting the target and actual accomplishment
• Daily accomplishment
• Monthly Progress Report
• Minutes of Meetings
• Site Supervision Staff Attendance Record
• Monthly Labor Force Employment Report
• Memorandum Orders
• Daily Weather Records
• Progress Photographs
• Labor Issues
• Vehicle and Equipment
• Expenses
3.2 Quality Control Testing
• Quality Control Program
• Concrete Design Mix-Trial Mix and Test Results
• Materials Report in support of Contractors claim
• Weekly Quality Control Assurance
• Status of Tests
• Summary of Labor Tests
• Schedule of Tests
• Routine Testing (Quality test of aggregates and other materials)
3.3 Quantity Measurements
• Approved AS-staked Plan
• AS-staked quality computations
• Variation Orders
• Measurement and Quantities-Daily/weekly Record signed by Resident Engineer and Contractor
• Approved As-built Plan
• As-built Quantity Computations
ANNEX P
Labour Force Employment Report
Republic of the Philippines
Labor Force Employment Report
ANNEX Q
Statement of Work Accomplished (SWA)
ANNEX R
Pro-forma Subproject Completion Report (SPR)
Subproject Completion Report (SPCR)
| Minimum Data that can be seen | ||||||
| 1 | Background of the Project | • | Brief description of the project. | |||
| 1.1. | Background | • | How the project materialized. | |||
| 1.2. | Project Formulation Process | • | How the LGU became the beneficiary of the | |||
| Program. | ||||||
| 2 | Project Design | |||||
| 2.1. | Basic Information of the Project | |||||
| 2.1.1. | Project Proponent(s); | |||||
| 2.1.2. | Project Title; | |||||
| 2.1.3. | Project Description; | |||||
| 2.1.4. | Project Location; | • | Proponents (number of HH and Population | |||
| to be served) | ||||||
| 2.1.5. | Project Duration: | • | Title of the project with exact location. | |||
| 2.1.5.1. | Target Start Date; | • | Description of the project such as laying of | |||
| 100 lm distribution pipeline, etc. | ||||||
| 2.1.5.2. | Actual Start Date; | • | The target and actual start and completion of | |||
| the project. | ||||||
| 2.1.5.3. | Target Completion Date; | |||||
| 2.1.5.4. | Actual Completion Date; | |||||
| 2.1.6. | Project Beneficiaries: | |||||
| 2.1.6.1. | Number of Households; | |||||
| 2.1.6.2. | Number of Population; | |||||
| 2.1.7. | Date of MOA Signed: | |||||
| 3 | Activities/Scope of Work(s) of the Project; | • | Scope or work stated in the approved POW | |||
| such as construction of 10 cu.m reservoir, | ||||||
| excavation and other major and minor | ||||||
| activities. | ||||||
| 4 | Fund Management | |||||
| 4.1. | Fund Allocation; | |||||
| 4.2. | LGU Counterpart: | • | Total allocation from the DILG, counterpart | |||
| from LGU (cash on in-kind) | ||||||
| 4.2.1. | Cash; | |||||
| 4.2.2. | In-kind; | |||||
| 4.3. | Total Project Cost; | |||||
| 5 | Fund Utilization: | |||||
| 5.1. | Release of First Tranche: | |||||
| 5.1.1. | Amount; | |||||
| 5.1.2. | Released Date; | |||||
| 5.1.3. | Check No.; | • | Process flow of transfer of fund to LGU with | |||
| amount, date of released and check | ||||||
| number. | ||||||
| 5.2. | Release of Second Tranche: | |||||
| 5.2.1. | Amount; | |||||
| 5.2.2. | Released Date; | |||||
| 5.2.3 | Check No.: | |||||
| 6 | Project Accomplishment; | • | Actual number of HH served, actual scope of | |||
| work delivered. | ||||||
| • | Changes in the project in terms of technical | |||||
| concern. | ||||||
| 7 | Type of Management of the Completed Water Supply Facility | • | Responsible for the operation and | |||
| (LGU-managed, BWASA, Cooperative, Water District, and | management of the completed water supply | |||||
| other Private Water Service Provider) | facility and provision of safe, affordable, | |||||
| continuous and quality drinking water to all | ||||||
| households in the community | ||||||
| 8 | Problem(s) Encountered; | • | Weather conditions, securing of Deed of | |||
| Donations, accident in the project. | ||||||
| 9 | Insights/Recommendations; | • | Any recommendations that will be helpful for | |||
| example use this materials instead of the | ||||||
| other one. | ||||||
| 10 | Annexes: | |||||
| 9.1. n | Photo/Video Documentation; | • | Project documentation, minutes of meeting, | |||
| variation order and other documents that will | ||||||
| support the project. | ||||||
| 9.2. | Minute(s) of Meeting; | |||||
| 9.3. | Other documents that may help/support the project | |||||
| Prepared by: | ||||||
|
___________________________
|
||||||
|
Municipal Engineer
|
||||||
|
Certified Correct:
|
||||||
|
__________________________
|
||||||
|
Municipal Mayor
|
ANNEX S
Minimum Quality Requirements
Minimum Requirements Quality Control Test
SCHEDULE OF MINIMUM TEST REQUIREMENT GOVERNING ITEMS OF WORK OF DPWH STANDARD SPECIFICATIONS FOR HIGHWAYS, BRIDGES AND AIRPORT, 1988 (VOLUME II)
PART C
Earthwork
Item 100-Clearing and Grubbing —
Tests: None
Item 101-Removal of Structures and Obstruction —
Tests: None
Item 102-Excavation —
Tests: Same as for items 103, 104 and 105, whichever is applicable.
Item 103-Structure Excavation
If excavated materials are wasted, the volume involved shall be reported, so that quality control requirements may be adjusted accordingly. Submit Project Engineer Certificate of Waste.
If excavated materials are incorporated into the work:
Tests: For every 1500m3 or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (LL, PL, P.I.)
For every 150mm layer in uncompacted depth
1-D, Field Density Test
Item 104-Embankment
Tests: For every 1500m3 or fraction thereof
1-G, Grading Test
1-P, Plasticity Test (LL, PL, P.I.)
1-C, Laboratory Compaction Test
For each 500m2 of each layer of compacted fill or fraction thereof at least one group of three (3) in-situ density tests. The layers shall be placed not exceeding 200mm in loose measurement or based on the result of compaction trials.
Item 105-Sub-grade Preparation
Same as for item 104
Item 106-Compaction Equipment and Density Control Strips
Tests: Same as for items 104, 105, 200, 201, 202, 203, 204, 205, 206 and 300
Item 107-Overhaul
Tests: None
PART D
Sub-Base and Base Course
Item 200-Aggregate Sub-base Course
Tests: For every 300m3 or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (LL, PL, P.I.)
For every 1500m3 or fraction thereof:
1-Q, Quality Test (Grading, Plasticity & Abrasion)
1-C, Lab. Compaction Test
For every 2500m3 or fraction thereof:
1-CBR, California Bearing Ratio
For every layer of 150mm of compacted depth/based on the results of Compaction trials. At least one group of three (3) in-situ density tests for each 500m2 or fraction thereof.
Item 201-Aggregate Base Course
Tests: For every 300m3 or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (LL, PL, P.I.)
For every 1500m3 OR fraction thereof:
1-Q Quality Test (Grading, Plasticity & Abrasion)
1-C Lab. Compaction Test
For every 2500m3 or fraction thereof:
1-CBR, California Bearing Ratio Test
For every layer of 150mm of compacted depth/based on the results of compaction trials at least one group of three (3) in-situ density tests for each 500m3 or fraction thereof.
Item 202-Crushed Aggregate Base Course
Tests: Same as for Item 201
For every 1500m3 or fraction thereof:
1-F, Fractured Face
Item 203-Lime Stabilized Road Mix Base Course
Amount of Lime to be added: 3 to 12 mass percent of dry soil aggregate
Tests:
A. Soil Aggregate
For every 300m3 or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (LL, PL, P.I.)
For every 1500m3 or fraction thereof:
1-Q, Quality Test (Grading, Plasticity & Abrasion)
B. Mix
For every 300m3 or fraction thereof:
1-C, Laboratory Compaction Test
1-UC, Unconfined Compression Test
1-CBR, California Bearing Ratio Test
C. Compacted Base Course
For every 150mm compacted depth:
1-D, Field Density Test for every 150m or fraction thereof
1-T, thickness Determination for every 150m or fraction thereof
D. Hydrated Lime
For every 100t or fraction thereof:
1-Q, Quality Test
Item 204-Portland Cement Stabilized Road Mix Base Course
Amount of Cement to be added: 6 to 10 mass percent of dry soil aggregate
Tests:
A. Soil Aggregate — Same as for Item 203
B. Cement
1-Q, Quality Test for every 2,000 bags or fraction thereof
C. Water
1-Q, Quality Test/Project Engineer's Certificate
D. Mix
For every 300m3 or fraction thereof:
1-C, Laboratory Compaction Test
1-UC, Unconfined Compression Test
1-UCBR, California Bearing Ratio Test
E. Compacted Base Course
For every layer at 150mm compacted depth
1-D, Field Density Test for every 150m or fraction thereof
1-T, Thickness determination for every 150m or fraction thereof
Item 205-Asphalt Stabilized Road Mix Base Course
Amount of Asphalt to be added: 4 to 7 mass of dry soil aggregate
Tests:
A. Soil Aggregate — same as for Item 203
B. Emulsified Asphalt:
1-Q, Quality Test for every 40t or 200 drums or fraction thereof
C. Mix — same as for Item 203
D. Compacted Base Course — same as for Item 203
Item 206-Portland Cement Treated Plant Mix Base Course
Amount of cement to be added: 6 to 10 mass % of dry soil aggregate
A. Soil Aggregate
Test: Same as for Item 203
B. Portland Cement
Tests: For every 2,000 bags or fraction thereof:
1-Q, Quality Test
C. Water
Tests: 1-Q, Quality Test/Project Engineer's Certificate
D. Mix
Tests: Same as for Item 2004
E. Compacted Base Course
Tests: For every layer of 150mm compacted depth
1-D, Field Density Test for every 150m or fraction thereof
1-T, Thickness determination for every 150m or fraction thereof
Item 207-Aggregate Stockpile
Tests: Same as the specified Item No. of the Specifications.
PART E
Surface Course
Item 300-Aggregate Surface Course
Tests: For every 300m3 or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (LL PL, P.I.)
For every 1,500m3 or fraction thereof:
1-C, Compaction Test
1-Q, Quality Test (Grading, Plasticity and Abrasion)
For every layer of 150mm of compacted depth/based on the results of compaction trials:
At least one (1) group of three in-situ density tests for each 500m2 or fraction thereof.
For Crushed Gravel of Crushed Stone, 1,500m3 or fraction thereof:
1-F, Fractured Face
Item 301-Bituminous Prime Coat
Quantity: 1 TO 2 L/m2
Tests: 1-Q, Quality Test for every 40t or 200 drums
Item 302-Bituminous Tack Coat
Quantity: 0.2 to 0.7 L/m2
Tests: 1-Q, Quality Test for every 40t or 200 drums.
Item 303-Bituminous Seal Coat
A. Bituminous Materials
Quantity: 0.2 to 1.5 L/m2
Tests: 1-Q, Quality Test for every 40t or 200 drums
B. Cover Aggregates
Quality: From 5 to 14 Kg/m2
Tests: From every 75 m3/200 kg or fraction thereof:
1-G, Grading Test
Item 304-Bituminous Surface Treatment (Double or Single Treatment)
A. Aggregates
Quantity: Using Cut-Back Asphalt or Asphalt Cement — 13.6 Kg/m2 for Single Treatment 38.0 Kg/m2 for Double Treatment 27.2 kg/m2-1st course 10.68 kg/m2-2nd course
Using Emulsified Asphalt — 13.6 kg/m2 for Single Treatment 19.04 kg/m2 for Double Treatment 13.6 kg/m2-1st course 5.44 kg/m2-2nd course
Tests: For every 75 m3/200 kg. or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (PL, LL, PI)
For every 1500 m3 or fraction thereof:
1-Q, Quality Test for: (Grading, Plasticity, Abrasion, Stripping and Bulk Specific Gravity)
1-F, Fractured Face.
B. Bituminous Materials
Quantity: Using Cut-Back Asphalt or Asphalt Cement — 1.36 L/m2 for Single Treatment 2.94 L/m2 for Double Treatment 1.36 L/m2-1st Course 1.58 L/m2-2nd Course
Quantity: Using Emulsified Asphalt — 1.58 L/m2 for Single Treatment 2.04 L/m2 for Double treatment None-1st Course 2.04-2nd Course
Test: Same as for ITEM 301
Item 305-Bituminous Penetration Macadam Pavement
A. Aggregates
Quantity: Using Asphalt Cement or Rapid Curing Course (Crushed) — 90 kg/m2 Key (Crushed) (13 & 11) — 24 kg/m2 Cover (Crushed or Screened) — 8 kg/m2
Quantity: Using Emulsified Asphalt Course (Crushed) — 90 kg/m2 Choker (Crushed) — 10 kg/m2 Key (Crushed) (10 & 8) — 18 kg/m2 Cover (Crushed or Screened) — 8 kg/m2
Tests: Same as for ITEM 304
B. Bituminous Materials
Quantity: Asphalt Cement/Rapid Curing: 7.2 L/m2 Quantity: Emulsified Asphalt: 11.0 L/m2
Tests: Same as for ITEM 301
Item 306-Bituminous Road Mix Surface Course
A. Aggregates
Tests: Same as for Item 304
B. Bituminous Materials
Quantity: Using Cut-Back Asphalt — 4.5 to 7.0 mass % of total dry aggregates
Quantity: Using Emulsified Asphalt — 6.0 to 10.0 mass % of total dry aggregate
Tests: Same as for Item 301
C. Mix
Tests: For every 75 Cu.M./130t of fraction thereof:
1-G, Grading Test
1-Ext., Extraction
1-Sty., Stability
1-C, Laboratory Compaction
D. Hydrated Lime
For every 100 t for fraction thereof:
Tests: 1-Q, Quality Test
E. Compaction Pavement
For each full day's operation:
Tests: D & T (Density and Thickness Tests) — at Least one (1) but not more than three (3) samples shall be taken.
Item 307-Bituminous Plant-Mix Surface Course — General
A. Aggregates
Tests:
For every 75 Cu.M/200 t or fraction thereof:
1-G & P, Grading and Plasticity Tests
For every 1,500 Cu.M./4000 t or fraction thereof:
1-Q, Quality Test for: (Grading, Plasticity, Abrasion, Stripping and Bulk Specific Gravity)
1-F, Fractured Face
B. Bituminous Materials
Quantity: 5.0 to 8.0 mass % of total dry aggregates
Tests: 1-Q, Quality Test for each 40 t or traction thereof.
C. Mix
Tests: For every 75 m3/130 t or fraction thereof:
1-G, Grading Test
1-Ext., Extraction
1-Sty., Stability
1-C, Laboratory Compaction
D. Hydrated Lime
Tests: For every 100 t or fraction thereof:
1-Q, Quality Test
E. Mineral Filler
Tests: For every 75 m3 or fraction thereof:
1-G & P, Grading and Plasticity Tests (LL, PL, PI)
F. Compacted Pavement
Tests: For each full day's operation:
D & T (Density and Thickness Tests) — at least one (1) but not more than three (3) samples shall be taken.
Item 308-Bituminous Plant — Mix Surface Course, Cold-Laid
A. Aggregates
Tests: Same as for Item 307
B. Bituminous Materials
Quantity: Using Cut-Back Asphalt — 4.5 to 7.0 mass percent of total dry aggregate.
Quantity: Using Emulsified Asphalt — 6.0 to 10.0 mass percent of total dry aggregates.
Tests: 1-Q, Quality Test for every 40t or 200 drums
C. Mix
Tests: Same as for Item 307
D. Hydrated Lime
Tests: Same as for Item 307
E. Mineral Filler
For every 75 Cu.M. or fraction thereof:
Tests: 1-G & P, Grading and Plasticity Tests (LL, PL, PI)
F. Compacted Pavement
Test: Same as for Item 307
Item 309-Bituminous Plant-Mix (Stockpile Maintenance Mixture)
A. Aggregates
Tests: Same as for Item 307
B. Bituminous Materials
Quantity: 4 to 10 mass % of total mix
Tests: 1-Q, Quality Test for every 40t or 200 Drums
C. Mix
Tests: Same as for Item 307
D. Hydrated Lime
Tests: Same as for Item 307
E. Mineral Filler
Tests: Same as for Item 307
F. Compacted Pavement
Tests: Same as for Item 307
Item 310-Bituminous Concrete Surface Course, Hot-Laid
A. Aggregates
Tests: Same as for Item 307
B. Bituminous Material
Quantity: 5.0 to 8.0 mass percent of total dry Aggregate
Tests: Same as for Item 307
C. Mix
Tests: Same as for Item 307
D. Hydrated Lime
Tests: Same as for Item 307
E. Mineral Filler
Tests: Same as for Item 307
F. Compacted Pavement
Tests: Same as for Item 307
Item 311-Portland Cement Concrete Pavement
A. Cement
Quantity: 9.00 bags per Cu M. (40 Kgs/bag)
Tests: For every 2,000 bags or fraction thereof:
1-Q, Quality Test
B. Fine Aggregates
Quantity: 0.50 m3/m3 concrete (if rounded coarse aggregate is used)
Quantity: 0.54 m3/m3 concrete (if angular coarse aggregate is used)
Tests: For every 1500 m3 or fraction thereof:
a) For a source not yet tested, or failed in previous quality test:
1-Q, Quality Test for: Grading, Elutriation (wash), Bulk Specific Gravity, Absorption, Mortar Strength, Soundness, Organic impurities, Unit Weight, % Clay Lumps and Shale.
b) For a source previously tested and passed quality test:
1-Q, Quality Test for: Grading Elutriation (wash), Bulk Specific Gravity, Absorption and Mortar Strength.
Tests: For every 75 m3 or fraction thereof:
1-G, Grading Test
C. Coarse Aggregate
Quantity: 0.77 m3/m3 concrete (if rounded coarse aggregate is used)
Quantity: 0.68 m3/m3 concrete (if angular coarse aggregate is used)
Tests: For every 1500 m3 or fraction thereof:
a) For a source not yet tested and or failed in previous quality test:
1-Q, Quality Test for: Grading, Bulk Specific Gravity, Absorption, Soundness and Unit Weight
b) For a source previously tested and passed Quality test:
1-Q, Quality Test for: Grading, Bulk Specific Gravity, Absorption and Abrasion.
For every 75 m3 or fraction thereof:
1-G, Grading Test
D. Water
Tests: 1-PE Cert., Certificate from Project Engineer or
1-Q, Quality Test, if source is questionable
E. Joint Filler
1. Poured Joint Filler
Tests: 1-Q, Quality Test on each type of Ingredient for each shipment
2. Premolded Joint Filler
Tests: 1-Q, Quality Test on each thickness of filler for each shipment
F. Special Curing Agents
Tests: 1-Q, Quality Test for each shipment
G. Steel Bars
Tests: For every 10,000 kg. or fraction thereof for each size:
1-Q, Quality Test, (Bending, Tension and Chemical Analysis)
H. Concrete
Tests: Flexural Strength Test on Concrete Beam Samples:
1-set consisting of 3 beam samples shall represent a 330 m2 of pavement, 230mm. depth, or fraction thereof placed each day. Volume of concrete not more than 75 m3.
I. Completed Pavement
Tests: Thickness determination by concrete core drilling on a lot basis.
Five (5) holes per km per lane or five (5) holes per 500 m2 when 2 lanes are poured concurrently.
PART F
Bridge Construction
Item 400-Piling
A. Timber Piles
Tests: 1-Inspection Report for each size and shipment of Timber
B. Concrete Piles
a) Concrete
Tests: Same as for Item 405
b) Reinforcing Steel
Tests: Same as for Item 404
C. Structural Piles
Tests: 1-Q, Quality Test/Mill Test Certificate
1-IR, Inspection Report
Item 401-Railing
A. Concrete
Tests: Same as for Item 405, Class C
B. Reinforcing Steel
Tests: Same as for Item 404
Item 402-Timber Structures
Tests:
1-Q, Quality Test or Manufacturer's Certificate for each type of materials used
1-IR, Inspection Report for each size and shipment of Timber
Item 403-Metal Structures
Tests:
1-Q, Quality Test or Mill Certificate for each type of materials used
1-IR, Inspection Report for each type and shipment of metal used
Item 404-Reinforcing Steel
A. Bar reinforcement for concrete for every 10,000 kg or Fraction thereof for each size:
1-Q, Quality Test for Bending, Tension and Chemical Analysis.
B. Wire and Wire Mesh
1-Q, Quality Test
Item 405-Structural Concrete A) Cement
Quantity: (40 kg/bag)
Class A — 9.0 bags/M3 of concrete
Class B — 8.0 bags/M3 of concrete
Class C — 9.5 bags/M3 of concrete
Class P — 11.0 bags/M3 of concrete
Tests: For every 2000 bags or fraction thereof
1-Q, Quality Test
B) Fine Aggregate
Quantity: M3/M3 of concrete
|
For Rounded
|
For Angular
|
|
|
|
|
|
| Class A |
0.5
|
0.54
|
| Class B |
0.45
|
0.52
|
| Class C |
0.53
|
0.59
|
| Class P |
0.44
|
0.47
|
Tests: For every 1500 M3 or fraction thereof:
a) For a source not yet tested or failed in previous Quality test
1-Q, Quality Test for: Grading, Elutriation (Wash), Bulk Specific Gravity, Absorption, Mortar Strength, Soundness, Organic Impurities, Unit Weight, % Clay Lumps and Shale.
b) For a source previously tested and passed quality Test:
1-Q, Quality Test (Grading, Elutriation (Wash), Bulk Specific Gravity, Absorption, Mortar Strength)
Tests: For every 75 M3 or fraction thereof:
1-G, Grading Test
C) Course Aggregates
Quantity: M3/M3 of concrete
|
For Rounded CA
|
For Angular CA
|
|
| Class A |
0.77
|
0.68
|
| Class B |
0.82
|
0.73
|
| Class C |
0.7
|
0.68
|
| Class P |
0.68
|
0.65
|
Tests: For every 1500 M3 or fraction thereof:
a) For a source not yet tested or failed in previous Quality test:
1-Q, Quality Test (Grading, Bulk Specific Gravity, Absorption, Abrasion, Soundness and Unit Weight)
b) For a source previously tested and passed quality Test:
1-Q, Quality Test (Grading, Absorption, Bulk Specific Gravity and Abrasion)
Tests: For every 75 M3 or fraction thereof:
1-G, Grading Test
D) Water
Tests: 1-Q, Quality Test, if source is questionable Certificate of Project Engineer
E) Premolded Filler for expansion joints
Tests:
1-Q, Quality Test on each thickness of filler for each shipment
F) Steel Reinforcement
Tests:
1-Q, Quality Test for every 10,000 kg or fraction thereof for each size.
B. n Concrete
Tests:
Compressive strength test on concrete cylinder samples. One (1) set consisting of 3 concrete. Cylinder samples shall be taken from each day's pouring and to represent not more than 75 M3 of Concrete or fraction thereof.
Item 406-Prestressed Concrete Structures
A. Concrete
Tests: Same as for Item 405, Class P
B. Steel Reinforcement
Tests: Same as for Item 404
C. Wire Strand
Tests: 1-Q, for every 20t or fraction thereof.
Item 407-Concrete Structures
Tests: Same Test as for Items 403, 404, 405 and 411. Elastomeric Bearing Pad will be tested to determine its quality.
Item 408-Steel Bridges
Tests: Same as for Items 403 and 411
Painting:
1-Q, One 20-L can for every 100 cans or fraction thereof or
1-Q, One 4-L can for every 100 cans or fraction thereof.
Item 409-Welded Structural Steel
Tests: Same Tests as for 403 and Inspection Report
Item 410-Treated and Untreated Timber
Tests: Inspection Report for Timber
1-Q, Quality Test for preservatives
Item 411-Paint
Tests:
1-Q, One 20-L can for every 100 cans or fraction thereof or
1-Q, One 4-L can for every 100 cans or fraction thereof.
PART G
Drainage and Slope Protection Structures
Item 500-Pipe Culverts and Storm Drains
A. Pipes
Tests:
1-P, Pipe for every 50 pieces: Strength, Absorption and Dimension
Alternative Requirement
1-Set consisting of 3 concrete cylinder samples for not more than 25 pipes cast in the field and
1-Inspection Report for each size for not more than 25 pipes cast in the field
B. Clay Pipe
Tests:
1-Pipe for every 200 pieces each size, with a minimum of 2 specimens for strength, absorption and dimension.
Item 502-Manholes, Inlets and Catch Basins
A. Concrete
Tests: Same as for Item 405, Class A
B. Lids, Cast Iron Frames and Grating
Tests: Inspection Report
Item 503-Cleaning and Reconditioning
Existing Drainage Structures
Tests: Inspection Report
Item 504-Riprap and Grouted Riprap
Tests: Same as for Item 505
Item 505-Stone Masonry
A. Cement
Quantity: 2 bags/M3 of concrete
Tests: For every 2,000 bags or fraction thereof:
1-Q, Quality Test
B. Fine Aggregates
Quantity: 0.17 M3/M3 of concrete
Tests: For every 1,500 M3 or fraction thereof:
1-Q, Quality Test (Same as for Item 405)
For every 75 M3 or fraction thereof:
1-G, Grading Test
C. Stone
Tests: Inspection Report
D. Water
Tests: 1-PE Cert., Project Engineer's Certificate or
1-Q, Quality Test, if source is questionable
Item 506-Hand-Laid Rock Embankment
Tests: Inspection Report
Item 507-Sheet Piles
A. Timber Sheet Piles
Tests: Inspection Report
B. Concrete Sheet Piles
Tests: Same as for Item 400
C. Steel Sheet Piles
Tests: Same as for Item 403
Item 508-Concrete Slope Protection
A. Bed Course
Tests: Same as for Item 200
B. Steel Reinforcement
Tests: Same as for Item 404
C. Concrete
Tests: Same as for Item 405
Item 509-Gabions
Tests:
1-Q, Quality Test for each shipment
PART H
Miscellaneous Structures
Item 600-Curb and/or Gutter
A. Concrete
| Quantity: 0.078 M3/M (Curb Only) | |
| 0.092 M3/M (Curb and Gutter, Type A) | |
| 0.149 M3/M (Curb and Gutter, Type B) | |
| 0.074 M3/M (Curb and Gutter, Type C) |
Tests: Same as for Item 405
B. Joint Filler
Tests: Same as for Item 311
Item 601-Sidewalk
A. Concrete
Tests: Same as for Item 405 Class A
B. Pre-molded Expansion Joint Filler
Tests: Same as for Item 311
Item 602-Monuments, Markers and Guide Posts
A. Concrete
Tests: Same as for Item 405
B. Reinforcing Steel
Tests: Same as for Item 404
C. Timber
Tests: Same as for Item 410
D. Paint
Tests: Same as for Item 411
Item 603-Guardrail
A. Steel Posts
Tests: Same as for Item 403
B. Timber Posts
Tests: Same as for Item 410
C. Concrete
Tests: Same as for Item 405
D. Reinforcing Steel
Tests: Same as for Item 404
E. Rail
Tests: Inspection Report
F. Paint
Tests: Same as for Item 411
ANNEX T
List of Documentary Requirements
A. Release of First Tranche
1. BASIC SUPPORTING DOCUMENTS
1.1 Letter Request — a letter signed by the LCE requesting for the approval of the Subproject Proposal or Simplified Feasibility Study for Water Supply Subprojects and submitting the required documents
1.2 Annual Investment Plan (AIP) or Annual Budget showing the budgeted amount for the required equity or the subproject/s (if any) of the Proponent LGU
1.3 Subproject Implementation Schedule showing the activities and timelines for each activity (from DED preparation up to completion). See Annex D for the Subproject Implementation Schedule Format
1.4 Certification from the Treasurer if they have existing Trust Account or Bank Certificate for new TrustAccount of the Implementing Partner DcHSEa
2. Subproject Specific Documents
2.1 Geo-resistivity Study for new construction with underground water source to determine the availability and quantity of the water source
2.2 Certification from Municipal Engineer that the source is adequate to serve the intended service area. The Proponent LGU may engage accredited technical service provider to conduct the source validation
2.3 Copy of the receipt issued by the water testing center/laboratory accredited by DOH as proof of conduct of water potability test
3. Other Supporting Documents
3.1 Sangguniang Panlalawigan/Bayan (SP/SB) Resolution authorizing the LCE to enter into MOA with DILG
3.2 Perfected Memorandum of Agreement (MOA) already signed by the LCE and RD
B. Approval Technical Design, Detailed Engineering and of Technical Equipment/Goods Specification
1. TECHNICAL SPECIFICATION and/or DETAILED ENGINEERING DESIGN
1.1 Official Letter submitting the required documents signed by the LCE
1.2 Program of Works (POW) signed by the Municipal Engineer and approved by the concerned LCE
1.3 Detailed Engineering Designs (DED), plans and drawings signed and sealed by the approving authorities or Technical Drawings signed by the approving authorities
1.4 Bill of Quantities including detailed computation (signed and sealed by the approving authorities)
1.5 Reviewed Detailed Design Report
1.5.1 Water demand projection
1.5.2 Hydraulic analysis taking into account the network diagram report and, if necessary, geo-resistivity report
2. NECESSARY PERMITS, LICENSES, CERTIFICATES and/or CLEARANCES
2.1 Application for the issuance of Water Permits from deputized agencies of National Water Resources Board (NWRB).
C. Release for the Second Tranche
1. BASIC SUPPORTING DOCUMENTS
1.1 Request Letter from the Implementing Partner
1.2 Summary of Works Accomplishment (SWA) showing 50% Physical Accomplishment and Updated Construction Schedule duly signed by the Municipal Engineer and approved by the Mayor or his duly authorized representative as applicable
1.3 Report of Disbursement/Liquidation (ROD) duly signed by the Treasurer/Accountant and stamped-received by the concerned COA Auditor attesting that 20% 1st Tranche release and the LGU Counterpart has been fully disabused
1.4 Pictures of the Physical Accomplishments on the Projects and Updated Subproject Billboard.
1.5. Certified true copies of other bidding documents and evaluation report, as may be require
D. Subproject Completion Report
1. Subproject Completion Report (SPCR)
2. As-Built Plans and Detail MOA between LGU and DILG Actual Subproject Cost
3. Summary of Subproject Report on Disbursement/Liquidation showing 100% liquidation of DILG Funds and LGU Equity
4. Certificate of acceptance of the subproject issued or signed by the recipient or beneficiaries;
5. Sustainability Plan
6. Pictures of the Completed Subprojects
7. Others, as deemed necessary
ANNEX U
Pro-forma Report or Disbursement (ROD)
Report of Disbursement/Liquidations
Amount Received per NTA No. ___
Less: Disbursement
Balance as of ___________________
|
Payee
|
Nature of Payment
|
Check No.
|
Date
|
Amount
|
Remarks
|
|
|
|
|
|
|
|
|
________
|
________________
|
___________
|
__________
|
___________
|
_________
|
| Certified Correct: | Approved by: | Verified by: | |||
|
______________
|
|
_______________
|
|
_________________
|
|
|
Accountant
|
|
Regional Director
|
|
Regional COA Auditor
|
ANNEX V
Pro-forma Consolidated Report of Disbursement (CROD)
Regional Consolidated Fund Utilization Report1
ANNEX W
Illustrative Entries for Fund Transfer
n Note from the Publisher: Copied verbatim from the official copy.
n Note from the Publisher: Copied verbatim from the official copy.
Cite This Law
Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016, DILG Memorandum Circular No. 049-16, Apr 6, 2016 (Philippines)
Guidelines for Implementation of Provision of Potable Water Supply-Sagana at Ligtas na Tubig sa Lahat Program for FY 2016, DILG Memorandum Circular No. 049-16 (Phil. 2016)
Related Laws
- Guidelines for the Implementation of the Provision of Potable Water Supply Local Government Support Fund — Sagana at Ligtas na Tubig sa Lahat (LGSF-SALINTUBIG) Program for FY 2018DILG Memorandum Circular No. 047-18 • Apr 5, 2018 • Other Rules and Procedures
- Policy Guidelines for the Implementation of the Provision of Potable Water Supply — Sagana at Ligtas na Tubig sa Lahat (SALINTUBIG) Program for FY 2017DILG Memorandum Circular No. 073-17 • Jun 7, 2017 • Other Rules and Procedures
- Guidelines on the Release of Funds from DILG-Regions VI and VII to DILG-NIR for Implementation of FY 2017 Salintubig ProgramDILG Memorandum Circular No. 083-17 • Jun 28, 2017 • Other Rules and Procedures
- Procedural Guidelines on the Conduct of Regional Development Council (RDC) Dialogues on Proposed Programs/Projects for FY 2019DBM Circular Letter No. 05-18 • Feb 20, 2018 • Other Rules and Procedures
- Guidelines for the Implementation of Provision of Potable Water Supply, Local Access Road and Other Local Infrastructure Projects Under the Bottom-Up Budgeting (BuB)DILG Memorandum Circular No. 045-15 • Apr 23, 2015 • Other Rules and Procedures
- Policy Guidelines and Procedures in the Implementation of the FY 2017 Local Government Support Fund-Assistance to Disadvantaged Municipalities (LGSF-ADM) ProgramDILG-DBM Joint Memorandum Circular No. 003-17 • May 23, 2017 • Other Rules and Procedures
Browse More Other Rules and Procedures
Explore other laws in the Other Rules and Procedures category.
View All Other Rules and ProceduresNeed Help Understanding This Law?
Ask our AI assistant to explain provisions, implications, or related laws.
Ask AI About This Law