The DPWH Department Order No. 038-10, issued on August 6, 2010, establishes a comprehensive disaster preparedness and response mechanism for typhoons and natural calamities affecting national roads and bridges in the Philippines. Regional Directors are required to submit situational reports every six hours detailing the status of major road sections, actions taken for repairs, and preliminary cost estimates. The order prioritizes damage reporting into three categories, with immediate action required for collapsed infrastructure, followed by ordinary and minor repairs. Additionally, designated inspectors must assess damage promptly and report findings to ensure timely restoration efforts. This directive supersedes all previous related issuances and emphasizes accountability for accurate damage assessments.
Quick Answers
- What is Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities about?
- The DPWH Department Order No. 038-10, issued on August 6, 2010, establishes a comprehensive disaster preparedness and response mechanism for typhoons and natural calamities affecting national roads and bridges in the Philippines. Regional Directors are required to submit situational reports every six hours detailing the status of major road sections, actions taken for repairs, and preliminary cost estimates. The order prioritizes damage reporting into three categories, with immediate action required for collapsed infrastructure, followed by ordinary and minor repairs. Additionally, designated inspectors must assess damage promptly and report findings to ensure timely restoration efforts. This directive supersedes all previous related issuances and emphasizes accountability for accurate damage assessments.
- What type of law is DPWH Department Order No. 038-10?
- Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities (DPWH Department Order No. 038-10) is a Philippine Other Rules and Procedures enacted by the Congress of the Philippines.
- When was Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities enacted?
- Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities (DPWH Department Order No. 038-10) was enacted on Aug 6, 2010.
- What is the citation for Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities?
- Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities, DPWH Department Order No. 038-10, Aug 6, 2010 (Philippines)
Law Information
- Reference Number
- DPWH Department Order No. 038-10
- Date Enacted
- Category
- Other Rules and Procedures
- Subcategory
- Department of Public Works and Highways
- Jurisdiction
- Philippines
- Enacting Body
- Congress of the Philippines
Full Law Text
August 6, 2010
DPWH DEPARTMENT ORDER NO. 038-10
| SUBJECT | : | Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities |
For immediate compliance and guidance of all concerned, all Regional Directors are hereby directed to submit to the Office of the Secretary, this Department, copy furnished the Bureau of Maintenance, their situational reports during calamities on major/secondary national roads and bridges within their respective areas of jurisdiction, using the prescribed format (BOM Form 01) every six (6) hours, i.e., at 8 am, 2 pm, 8 pm and 2 am and shall contain the following information:
1. The name/location of the major road sections.
2. Situation of the affected major road section indicating whether passable or not passable.
3. Action taken on damaged sections (e.g., clearing, rehabilitation, restoration, etc.).
4. Preliminary cost estimate to repair/restore the damaged section.
5. Remarks, indicating whether the damaged section is open or not to all types of vehicle, detour routes available, and estimated time of repair, etc.
In the Central Office, the Bureau of Maintenance shall consolidate the situational reports coming from the Regional Offices and submit to the Office of the Secretary, copy furnished the National Disaster Risk Reduction and Management Council (NDRRMC, formerly NDCC) and the Presidential Management Staff (PMS). DAaEIc
Additionally, in order to effect timely and expeditious response during calamities, you are further directed to strictly observe the following guidelines in reporting damages to various infrastructure facilities, as follows:
1. Reports on damages should be categorized into three (3)
a. Priority I — Involves immediate rehabilitation of collapsed bridges, cut road sections, breached seawalls and dikes to quickly restore mobility and ensure the safety of the affected areas.
b. Priority II — Involves ordinary repair works such as patching potholes, resurfacing of washed-out roads and slightly destroyed flood control structures. IHDCcT
c. Priority III — Involves minor repair work and/or improvement to prevent further deterioration such as repair of road section.
2. A system should be set up in the District where road sections prone to damages caused by calamities are identified and then assigned permanent inspectors who are capable of assessing damages and estimating with a high degree of accuracy the cost of restoration work.
3. At the first warning (by radio, tv, press, etc.) or indication of an impending typhoon, the designated inspectors will immediately proceed to their assigned damage-prone sections/areas to:
3.1 direct emergency work during the calamity, and
3.2 immediately assess the damages on at least the Priority I group of priorities as described in Item I above and submit/relay within 4 hours after the calamity, a report of such initial assessment by text messaging, facsimile or by courier to the District Engineer.
4. Within 6 hours after the calamity, the Regional Director/District Engineer should transmit the initial assessment of the damages to the Secretary of Public Works and Highways, thru the Bureau of Maintenance, by e-mail, fax, telephone or courier covering at least the Priority I group of priorities for NDRRMC reporting and should now be indicated in Column 6 of BOM Form 01.
5. Within twelve (12) hours, the report of damages to be submitted especially for the high Priority I group must also reflect the initial cost estimates, which should be subsequently updated every six (6) hours using BOM Form 02. CHDAEc
6. Within forty eight (48) hours, the Regional Director shall submit a more detailed report on the damages using BOM Form 03 for all three (3) Priority groups as described in Item I above with pictures, including the realistic cost estimates for the restoration of the damaged facilities.
7. The Regional Director shall review and validate the damages covered by the final report in Item 6 prior to the submission to the Secretary of Public Works and Highways thru the Bureau of Maintenance.
8. The concerned Regional Directors and District Engineers are held responsible as to the factual and reasonable estimates on the cost of damages.
This supercedes all previous Memorandum Circulars, Orders and other issuances issued contrary hereto. CcHDaA
For compliance.
(SGD.) ROGELIO L. SINGSONSecretary
ATTACHMENT
BOM Form 01
BOM Form 02
BOM Form 03
Cite This Law
Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities, DPWH Department Order No. 038-10, Aug 6, 2010 (Philippines)
Disaster Preparedness and Response Mechanism During Typhoons and Other Natural Calamities, DPWH Department Order No. 038-10 (Phil. 2010)
Related Laws
- Disaster Preparedness Measures for SchoolsDepEd Order No. 083-11 • Oct 28, 2011 • Other Rules and Procedures
- Disaster Response Operations GuidelinesDSWD Administrative Order No. 03-15 • Apr 4, 2015 • Other Rules and Procedures
- Disaster Risk Reduction and Management Coordination and Information Management ProtocolDepEd Order No. 021-15 • Jun 1, 2015 • Other Rules and Procedures
- Guidelines in Ensuring Public Safety During Man-Made and Natural DisastersDILG Memorandum Circular No. 035-12 • Feb 21, 2012 • Other Rules and Procedures
- National Policy on Disaster Risk Reduction and Management in Health (DRRM-H)DOH Administrative Order No. 2019-0046 • Oct 29, 2019 • Other Rules and Procedures
- Rules and Regulations on Leasehold Operations in Tenanted Coconut Lands Affected by Fortuitous Events, Natural Disasters or CalamitiesDAR Administrative Order No. 02-14 • Feb 26, 2014 • Other Rules and Procedures
Browse More Other Rules and Procedures
Explore other laws in the Other Rules and Procedures category.
View All Other Rules and ProceduresNeed Help Understanding This Law?
Ask our AI assistant to explain provisions, implications, or related laws.
Ask AI About This Law