Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects
National Emergency Memorandum Order No. 10, issued on February 28, 1990, authorizes the Secretary of Public Works and Highways (DPWH) to expedite the awarding of urgent infrastructure projects and procurement of related services and materials during national emergencies. The order allows for fast-track procedures, including implementation by administration or negotiated contracts for projects costing up to P100 million, especially in cases of failed bids, emergencies, or critical peace and order situations. A Master List of accredited constructors will be maintained for selection, ensuring that only qualified entities participate. Additionally, the DPWH can streamline the hiring of consultants and the procurement of supplies through negotiated contracts, with the order effective for the duration of the national emergency.
Quick Answers
- What is Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects about?
- National Emergency Memorandum Order No. 10, issued on February 28, 1990, authorizes the Secretary of Public Works and Highways (DPWH) to expedite the awarding of urgent infrastructure projects and procurement of related services and materials during national emergencies. The order allows for fast-track procedures, including implementation by administration or negotiated contracts for projects costing up to P100 million, especially in cases of failed bids, emergencies, or critical peace and order situations. A Master List of accredited constructors will be maintained for selection, ensuring that only qualified entities participate. Additionally, the DPWH can streamline the hiring of consultants and the procurement of supplies through negotiated contracts, with the order effective for the duration of the national emergency.
- What type of law is National Emergency Memorandum Order No. 10?
- Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects (National Emergency Memorandum Order No. 10) is a Philippine Presidential Issuances enacted by the Congress of the Philippines.
- When was Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects enacted?
- Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects (National Emergency Memorandum Order No. 10) was enacted on Feb 28, 1990.
- What is the citation for Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects?
- Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects, National Emergency Memorandum Order No. 10, Feb 28, 1990 (Philippines)
Law Information
- Reference Number
- National Emergency Memorandum Order No. 10
- Date Enacted
- Category
- Presidential Issuances
- Subcategory
- National Emergency Memorandum Orders
- Jurisdiction
- Philippines
- Enacting Body
- Congress of the Philippines
Full Law Text
February 28, 1990
NATIONAL EMERGENCY MEMORANDUM ORDER NO. 10
AUTHORIZING THE SECRETARY OF PUBLIC WORKS AND HIGHWAYS TO ADOPT FAST-TRACK PROCEDURES FOR AWARDING URGENT INFRASTRUCTURE PROJECTS AND FOR PROCURING URGENT CONSULTANCY SERVICES, SUPPLIES, MATERIALS AND EQUIPMENT, SUBJECT TO CERTAIN CONDITIONS
Pursuant to the powers vested in me by Republic Act No. 6826, and in order to expedite the execution of urgent infrastructure projects in support of the priority task of economic reconstruction, I, CORAZON C. AQUINO, President of the Philippines, do hereby authorize the Secretary of the Department of Public Works and Highways (DPWH) to undertake the following "fast-track" mode of awarding urgent infrastructure projects and for procurement of urgent consultancy services, supplies, materials and equipment:
SECTION 1. Construction Projects. —
a. Implementation of Eligible Projects by Administration or Negotiated Contract.
The DPWH Secretary may authorize the implementation by administration or negotiated contract, thru canvass bidding, of infrastructure projects not costing more than P100,000,000 and falling under the following types:
(1) Projects whose public bidding has failed for a valid cause, such as where there is no prequalified constructors or bidders, or only one constructor is prequalified or has submitted a responsive bid.
(2) Projects whose contracts have been rescinded or terminated wholly or partly.
(3) Projects that respond to emergencies arising from natural calamities where immediate action is needed to prevent imminent loss of life and/or property, particularly in calamity areas proclaimed by the President of the Philippines, such as repair of collapsed bridges, cut road sections, breached dikes, unroofed schoolbuildings, and other Priority I projects.
(4) Projects in areas where the peace and order situation is critical as certified by the Secretary of National Defense.
(5) Projects where time is of the essence, e.g., those which have to be started/completed at earliest time in order to meet deadlines set under Presidential directives or international commitments, or to take advantage of critical construction periods affected by natural phenomenon such as weather as may be determined by the Secretary of Public Works and Highways.
The DPWH may also implement, either by administration or negotiated contract, thru canvass bidding, the above types but with costs exceeding P100,000,000, subject to prior approval of the President of the Philippines.
b. Work by Administration as First Option
For the above types of projects, the DPWH shall, as a first option, consider project implementation by administration, either by the DPWH itself thru its central/field units or by the Armed Forces of the Philippines (AFP) engineering units thru Memoranda of Agreement.
Where the projects are, as determined by the DPWH Secretary, beyond the capabilities of the DPWH and the AFP engineering units to undertake by administration, they may be implemented by negotiated contract thru canvass bidding.
c. Eligible Constructors for Negotiated Contracts
Participation in canvass biddings for negotiated contracts shall be limited to those constructors duly accredited by the DPWH for the project category and size (subclassification) and which are included in a Master List pursuant to the uniform guidelines issued by the Inter-Agency Committee mentioned in Section IB 1.4 of the rules and regulations implementing P.D. No. 1594, and such other hurdle requirements that may be promulgated by the Secretary of Public Works and Highways to emphasize the strict requirements of good track record performance and/or capability requirements to qualify for inclusion in the Master List.
d. Procedure for Selection of Constructors and Awards of Contract
(1) Conformably to the preceding paragraph, a Special DPWH Committee composed of the following shall prepare a Master List of accredited constructors, which shall be updated regularly, who may be considered for negotiated contract thru canvass bidding:
| Undersecretary, DPWH | Chairman | |
| Assistant Secretary of Legal Affairs, DPWH | Member | |
| Director, Bureau of Construction, DPWH | Member | |
| Representative from the Office of the | ||
| President of the Philippines | Member | |
| Representative from the Construction | ||
| Industry Authority of the Philippines | Member |
(2) The DPWH central Prequalification, Bids and Awards Committee (PBAC) shall choose a minimum of three (3) accredited constructors by drawing lots from the Master List.
(3) The PBAC shall prequalify/predisqualify the chosen constructors for the subject contract in accordance with the provisions of the Implementing Rules and Regulations of Presidential Decree No. 1594. If less than the minimum of three (3) constructors prequalify, the PBAC shall draw additional names from the Master List and prequalify/predisqualify them until the required minimum of three (3) prequalified constructors is attained.
(4) The chosen prequalified constructors shall submit their sealed bids to the PBAC.
(5) The PBAC shall evaluate the bids and recommend to the DPWH Secretary the award to the lowest evaluated bid not exceeding the Approved Agency Estimate (AAE). Alternatively, the PBAC may negotiate simultaneously with the prequalified constructors to arrive at the lowest price below the AAE.
(6) The award is subject to the approval of the DPWH Secretary.
SECTION 2. Consulting Services. —
The DPWH Secretary may fast-track the process of hiring consultants for infrastructure projects where time is of the essence, as follows:
(1) The DPWH shall prepare a "long list" of accredited consultants for different types of services. These consultants may be firms or individuals.
(2) Without need of advertisement, for specific projects, the DPWH Secretary may approve a "shortlist" of at least three qualified consultants drawn from the long list who shall be invited to submit their proposals.
(3) The DPWH may award the consultancy contract to the most advantageous proposal and negotiate the terms therefor.
SECTION 3. Procurement of Supplies, Materials and Equipment. —
The procurement of supplies, materials and equipment for DPWH infrastructure projects may be fast-tracked thru a negotiated contract subject to the provisions of Executive Order No. 301, dated 26 July 1987, as amended.
This urgent Memorandum Order shall take effect two (2) days after its publication in at least two (2) national newspapers of general circulation, and shall continue to be enforced for the duration of the national emergency.
DONE in the City of Manila, this 28th day of February, in the year of Our Lord, Nineteen Hundred and Ninety.
Cite This Law
Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects, National Emergency Memorandum Order No. 10, Feb 28, 1990 (Philippines)
Authorizing the DPWH Secretary to Adopt Fast-Track Procedures for Awarding Urgent Infrastructure Projects, National Emergency Memorandum Order No. 10 (Phil. 1990)
Related Laws
- Authorizing the NHA to Fast-track Procedures for Awarding Construction of Priority Housing ProjectsNational Emergency Memorandum Order No. 31 • Jun 5, 1990 • Presidential Issuances
- Directing the Housing and Urban Development Coordinating Council (HUDCC) to Directly Oversee and Fast-Track the Implementation and Development of Housing Projects in Areas Proclaimed as Housing SitesMemorandum Order No. 102 • May 17, 2003 • Presidential Issuances
- Accelerating Infrastructure Projects to Maintain Growth Amid Export/Remittance SlowdownAdministrative Order No. 206 • Oct 30, 2007 • Presidential Issuances
- Revised Policies, Procedures and Delegation of Authority in the Release of Funds for Infrastructure Projects to Implementing Offices of the DPWHDPWH Department Order No. 220-16 • Dec 12, 2016 • Other Rules and Procedures
- Revised Guidelines for the Implementation of DPWH Projects by LGUDPWH Department Order No. 062-15 • Apr 29, 2015 • Other Rules and Procedures
- Revised Guidelines for the Implementation of DPWH Projects (By Administration or Contract) by Local Government Units (LGUs)DPWH Department Order No. 62, s. 2018 • Apr 13, 2018 • Other Rules and Procedures
Browse More Presidential Issuances
Explore other laws in the Presidential Issuances category.
View All Presidential IssuancesNeed Help Understanding This Law?
Ask our AI assistant to explain provisions, implications, or related laws.
Ask AI About This Law