COMPARATIVE TABLE
|
|
--------------------------------------------------------------------------------------------------------------------------------------------------------------
|
|
PROVISIONS
|
AMENDMENT
|
RATIONALE/REMARKS
|
|
-------------------------------------------------------------------------------------------------------------------------------------------------------------
|
|
|
|
Sect. IB 2 -
|
Amend Section IB 2 - 1e
|
For clarity. Government
|
|
|
|
|
|
|
|
|
|
|
(1) End-user group or non-
|
|
|
|
|
|
|
(2) Philippine Institute of]
|
|
|
|
|
|
(3) Philippine Institute of Civil Engineers]
|
|
|
|
|
|
|
|
|
|
|
Both representatives shall be non-
|
|
|
|
|
|
|
|
Sect. IB 3 - INVITATION
|
Modify the title into:
|
To correct the title.
|
|
TO BID, p 5
|
IB 3 - INVITATION TO
|
be titled "An Invitation
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
a. Advertisement for at least
|
The IACRCC is proposed to
|
|
|
three (3) times within a
|
be abolished and its
|
|
|
reasonable period depending upon
|
functions to be transferred
|
|
|
the size and complexity but in
|
to Construction Industry
|
|
|
no case less than (2) weeks in
|
Authority of the Philippines
|
|
|
at least two (2) newspapers of
|
(CIAP) through Philippine
|
|
|
general circulation which have
|
Contractors Accreditation
|
|
|
been regularly published for at
|
Board (PCAB).
|
|
|
least two (2) years before the
|
|
|
|
date of issuance of the Notices
|
|
|
|
or announcements and at the
|
|
|
|
same time posting copies thereof
|
|
|
|
at any conspicuous place in
|
|
|
|
the office/agency/corporation
|
|
|
|
concerned if the project cost
|
|
|
|
is more than P1,000,000.
|
|
|
|
However, for projects costing
|
|
|
|
P1,000,000 and below . . . the
|
|
|
|
invitation to bid shall be advertised
|
|
|
|
at least once within a week
|
|
|
|
in a newspaper of local circulation . . .
|
|
|
|
provided that based on the agency's
|
|
|
|
short list of contractors or referral
|
|
|
|
with the [Inter agency Committee on
|
|
|
|
Registration and Classification of
|
|
|
|
Contractors] PHILIPPINE
|
|
|
|
CONTRACTORS ACCREDITATION
|
|
|
|
BOARD there are at least four
|
|
|
|
contractors indigenous to the region
|
|
|
|
duly classified and registered to
|
|
|
|
undertake such projects.
|
|
|
|
|
|
|
Sect. IB 4 - ISSUANCE
|
Amend Section IB 4 - 1 as
|
The contents of
|
|
OF QUALIFICATION
|
follows:
|
advertisement vary depending
|
|
STATEMENTS/FORMS p. 6
|
1. The Prequalification, Bid
|
on the scope of the invitation.
|
|
|
and Award Committee (PBAC) or
|
However, a commonality
|
|
|
the Prequalification Committee, as
|
may be established as
|
|
|
the case may be shall provide
|
to the types of information
|
|
|
prospective bidders with the
|
to be reflected in the
|
|
|
Notice of Prequalification TO
|
advertisement to enable contractors
|
|
|
CONTAIN, AMONG OTHERS,
|
to assess their
|
|
|
THE FOLLOWING
|
capabilities and timetables
|
|
|
INFORMATION to guide them in
|
even by just reading the
|
|
|
evaluating their capabilities
|
advertisement.
|
|
|
and decide whether or not to
|
|
|
|
participate in the bidding of a
|
|
|
|
specific project:
|
|
|
|
|
|
|
|
A. NAME AND LOCATION OF
|
|
|
|
|
|
|
|
|
|
B. PROJECT BACKGROUND
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C. ESTIMATED PROJECT COST
|
|
|
|
|
|
|
|
|
|
D. REQUIRED PCAB REGISTRATION
|
|
|
|
|
|
|
|
|
|
|
|
|
E. COST AND PLACE OF
|
|
|
|
|
|
|
|
|
|
|
|
|
F. DATE, TIME AND PLACE OF:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Amend Section IB 4-2 as follows:
|
To plug a loophole in the
|
|
|
IRR. In practice, agencies
|
|
|
|
2. The following qualification
|
also require the contractor's
|
|
|
statements shall be required of interested
|
license issued by
|
|
|
contractors:
|
PCAB in view of the differing
|
|
|
|
validity periods of
|
|
|
a. PCAB CONTRACTOR'S LICENSE
|
PCAB license (1 year) and
|
|
|
b. Pre-C Contractor's Confidential
|
license and its
|
|
|
Prequalification Statement for the
|
corresponding classification
|
|
|
Project.
|
since the IAC is proposed
|
|
|
|
to be abolished and its
|
|
|
|
functions, physical
|
|
|
|
resources and manpower
|
|
|
|
will be transferred to CIAP
|
|
|
|
through PCAB.
|
|
|
|
|
|
|
Include new section as IB 4-3
|
For clarity foreign contractor/
|
|
|
as follows:
|
joint ventures/consortia
|
|
|
|
of Filipino contractor/
|
|
|
"FOR FOREIGN CONTRACTORS/
|
partners are also supposed
|
|
|
JOINT VENTURES/CONSORTIA OF
|
to secure a special contractor's
|
|
|
FILIPINO CONTRACTORS/PARTNERS.
|
license from
|
|
|
A SPECIAL PCAB CONTRACTOR'S
|
PCAB before they may be
|
|
|
LICENSE SHALL BE REQUIRED
|
allowed to bid in any government
|
|
|
FOR PURPOSES OF
|
project
|
|
|
PREQUALIFICATION."
|
|
|
|
|
|
|
|
Amend Section IB 4 - 3 as follows
|
For consistency with the
|
|
|
and renumber as IB 4-4:
|
above proposed amendment.
|
|
|
|
|
|
|
"Pre-C shall be required by the
|
|
|
|
contracting government agency . . .
|
|
|
|
It shall be submitted not later than
|
|
|
|
the deadline set in the published
|
|
|
|
Invitation to PREQUALIFY AND
|
|
|
|
to Bid, . . ."
|
|
|
|
|
|
|
|
Amend Section IB 4 - 4 as follows
|
|
|
|
and renumber as IB 4 - 5:
|
|
|
|
|
|
|
|
"The following papers shall, among
|
To provide a listing of
|
|
|
others, comprise Pre-C:
|
Pre-C, information or
|
|
|
|
statements vis-a-vis criteria
|
|
|
CREDIT LINE ISSUED BY AN
|
necessary for prequalification
|
|
|
AUTHORIZED BANK IN AN
|
of contractors.
|
|
|
|
AVERAGE OPERATING EXPENSES
|
|
|
|
OF THE PROJECT FOR TWO
|
|
|
|
(2) MONTHS OR TEN PERCENT
|
|
|
|
(10%) OF THE TOTAL PROJECT
|
|
|
|
COST, WHICHEVER IS LESS
|
|
|
|
|
|
|
b. [An] PROPOSED organization chart
|
Modified to reflect only
|
|
|
FOR THE PROJECT [and a
|
the required document/
|
|
|
complete qualification and
|
statement.
|
|
|
experience data sheet of key
|
|
|
|
personnel].
|
|
|
|
|
|
|
|
c. LIST OF KEY PERSONNEL
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d. Statement of ALL RELEVANT
|
Information of the financial
|
|
|
completed construction projects
|
institutions from whom
|
|
|
in the 1st three years, government
|
guarantees were secured
|
|
|
and private. The statement shall
|
need not be required as part
|
|
|
include the nature and value of
|
of firm experience/track
|
|
|
the project, original and actual
|
record. Instead, the
|
|
|
project schedule, the location of
|
statement of completed projects
|
|
|
the project, AND the name and
|
may be supported by
|
|
|
address of the owner. [the
|
certificates of acceptance from
|
|
|
financial institutions from whom
|
project owners.
|
|
|
guarantees, credit lines, loans
|
|
|
|
and other financial accommodations
|
|
|
|
were secured for such
|
|
|
|
projects, and the aggregate
|
|
|
|
outstanding from each institution
|
|
|
|
in each year.] IT SHALL BE
|
|
|
|
SUPPORTED BY CERTIFICATES
|
|
|
|
OF COMPLETION AND/OR
|
|
|
|
OWNERS' ACCEPTANCE.
|
|
|
|
|
|
|
|
e. Detailed statement showing a
|
To serve as support
|
|
|
list of all ongoing construction
|
documents and to validate the
|
|
|
projects government and private,
|
submitted statements on the
|
|
|
as well as awarded and/or
|
list of all on-going construction
|
|
|
approved contracts not yet
|
projects of the contractor.
|
|
|
started. This statement shall
|
|
|
|
include the NATURE AND value
|
|
|
|
of the project, percentage of
|
|
|
|
time elapsed, percentage of
|
|
|
|
physical accomplishment, [and]
|
|
|
|
scheduled date of completion,
|
|
|
|
THE LOCATION OF THE PROJECT
|
|
|
|
AND THE NAME AND ADDRESS
|
|
|
|
OF THE OWNER. IT SHALL
|
|
|
|
BE SUPPORTED BY
|
|
|
|
CERTIFICATES OF COMPLETION
|
|
|
|
AND/OR OWNER'S ACCEPTANCE,
|
|
|
|
NOTICES OF AWARD, AND/OR
|
|
|
|
NOTICES TO PROCEED ISSUED
|
|
|
|
BY THE OWNER.
|
|
|
|
|
|
|
|
f. List of [owned] RELEVANT
|
To serve as support
|
|
|
equipment OWNED and those
|
documents and to validate
|
|
|
pledged exclusively for the
|
the submitted list of
|
|
|
project SUPPORTED BY
|
equipment owned, to be leased
|
|
|
CERTIFICATE OF OWNERSHIP/
|
or purchased by the contractor.
|
|
|
REGISTRATION WITH THE LAND
|
|
|
|
TRANSPORTATION OFFICE.
|
|
|
|
|
|
|
|
g. LIST OF RELEVANT EQUIPMENT
|
|
|
|
CONTRACTED TO BE
|
|
|
|
LEASED OR PURCHASED AND
|
|
|
|
THOSE PLEDGED TO BE USED
|
|
|
|
EXCLUSIVELY FOR THE PROJECT
|
|
|
|
SUPPORTED BY CERTIFIED
|
|
|
|
COPIES OF CONTRACT/S OR
|
|
|
|
LEASE AND/OR AFFIDAVIT OF
|
|
|
|
PLEDGE/S AND PRO-FORMA
|
|
|
|
INVOICE, IF TO BE PURCHASED.
|
|
|
|
|
|
|
|
Include new section as IB 4 - 6 as
|
The standardized Pre-C
|
|
|
follows:
|
application form is
|
|
|
|
recommended to help
|
|
|
"EACH OFFICE/AGENCY/
|
minimize pre-disqualification
|
|
|
CORPORATION SHALL USE
|
decisions based on
|
|
|
THE STANDARD PRE-C
|
incomplete documentation
|
|
|
APPLICATION FORM TO
|
and to avoid confusion in
|
|
|
CONTAIN THE
|
the filling-up of Pre-C
|
|
|
AFOREMENTIONED REQUIREMENTS.
|
forms by multi-agency
|
|
|
|
contractors.
|
|
|
Transfer Section IB 4-4c and
|
|
|
|
renumber of Section IB 6-6 and
|
|
|
|
amend as follow:
|
|
|
|
|
|
|
|
"[Actual employment or contract
|
To serve as guide in the
|
|
|
to employ] THE PROPOSED BY
|
evaluation of technical
|
|
|
PERSONNEL (duly qualified project
|
personnel.
|
|
|
manager and project engineer.)
|
|
|
|
[who] MUST have managed or
|
|
|
|
supervised at least a project of
|
|
|
|
similar nature as to type and cost
|
|
|
|
(escalated)."
|
|
|
|
Renumber Section IB 6-5 to IB 6-7
|
|
|
|
and Section IB 6-6 to IB 6-5
|
|
|
|
|
|
|
Section IB 5 -
|
|
|
|
CLASSIFICATION
|
Amend Section IB 5 - 1 as follows:
|
|
|
AND REGISTRATION
|
THE [An], inter-agency committee
|
The activities of the IAC
|
|
OF CONTRACTOR
|
composed of representatives from
|
generally overlap with that
|
|
|
the Department of Public Works
|
of the PCAB. The proposal
|
|
|
and Highways, the Department of
|
to abolish the IAC and
|
|
|
Transportation and Communications,
|
transfer its functions to CIAP
|
|
|
the Office of the President in the
|
through PCAB is for
|
|
|
absence of the Department of Energy
|
purposes of efficiency and
|
|
|
and the Construction Industry
|
economy. It may be recalled
|
|
|
Authority of the Philippines
|
that the IAC was created to
|
|
|
WHICH CLASSIFIED AND
|
provide for a uniform
|
|
|
REGISTERED, OR
|
guidelines for the classification
|
|
|
PREDISQUALIFIED CONTRACTORS
|
of contractors and once this
|
|
|
BASED ON THEIR submitted
|
is achieved, it was the intention
|
|
|
ARC-C AND CLASSIFICATION
|
to abolish such IAC. To
|
|
|
FUNCTIONS, RESOURCES AND
|
date, such uniformity is
|
|
|
MANPOWER WILL BE
|
deemed achieved.
|
|
|
TRANSFERRED TO CIAP THROUGH
|
|
|
|
PCAB. THE INTER-AGENCY
|
|
|
|
COMMITTEE SHALL STILL EXIST
|
|
|
|
FOR THREE MONTHS FROM THE
|
|
|
|
DATE OF APPROVAL OF THE
|
|
|
|
PROPOSED AMENDMENTS BY THE
|
|
|
|
OFFICE OF THE PRESIDENT TO
|
|
|
|
EFFECT THE SMOOTH TRANSFER
|
|
|
|
OF THE SYSTEM.
|
|
|
|
|
|
|
|
Delete Section IB 5 - 2 to IB 5 - 11.
|
|
|
|
|
|
|
Section IB 6 - PRE-
|
Amend Section IB 6 - 3
|
|
|
QUALIFICATION OF
|
as follows:
|
|
|
CONTRACTORS FOR
|
|
|
|
SPECIFIC CONTRACTS, p.a.
|
|
|
|
|
|
|
|
"In the evaluation of the
|
For greater clarity.
|
|
|
|
Pre-C statement, the PBAC
|
|
|
|
shall review, among other things,
|
|
|
|
the technical capability of contractor
|
|
|
|
to carry out the subject contract
|
|
|
|
as gauged by the extent and quality
|
|
|
|
of his relevant experience and
|
|
|
|
performance and track record,
|
|
|
|
the suitability of his available
|
|
|
|
RELEVANT construction equipment,
|
|
|
|
and the adequacy of his proposed . . ."
|
|
|
|
|
|
|
|
Amend Section IB 6 - 4 as follows:
|
|
|
|
|
|
|
|
"To determine the financial capacity
|
This is to clarify when the
|
|
|
of the contractor, the PBAC shall
|
cash deposit can be
|
|
|
require the contractor to submit a
|
withdrawn. Some contractors
|
|
|
statement from a bank . . . [In the
|
claim that some government
|
|
|
case of a] Cash deposit certificate
|
agencies unduly deny
|
|
|
SHALL BE RELEASED ONLY
|
requests for withdrawal of
|
|
|
WHEN THE COST OF THE
|
said cash deposit even if the
|
|
|
REMAINING WORK IS 10% OF
|
project is already
|
|
|
THE TOTAL PROJECT COST OR
|
substantially complete.
|
|
|
WHEN THE CONTRACT TIME
|
|
|
|
REMAINING IS LESS THAN
|
|
|
|
TWO MONTHS BEFORE
|
|
|
|
COMPLETION AS CERTIFIED BY
|
|
|
|
THE IMPLEMENTING AGENCY
|
|
|
|
THROUGH THE ISSUANCE OF A
|
|
|
|
STATEMENT OF WORK
|
|
|
|
ACCOMPLISHED [submitted by the bidder . . .]"
|
|
|
|
|
|
|
Section IB 10.2 - SUB-
|
Section IB 10.2 - 4 as follows:
|
|
|
MISSION, OPENING
|
|
|
|
AND ABSTRACTING OF
|
|
|
|
BIDS/TENDERS p. 13
|
"Bids shall be received on or before
|
The present provision opens
|
|
|
the designated time and date to be
|
the possibility of collusion
|
|
|
eligible for consideration. Bids may
|
among the participating
|
|
|
be withdrawn only in writing 5
|
bidders as bidders can
|
|
|
WORKING DAYS FROM THE
|
withdraw their bids at the
|
|
|
DEADLINE OF SUBMISSION OF
|
last minute.
|
|
|
BIDS [before the time set for the
|
|
|
|
opening of bids]".
|
|
|
|
|
|
|
Section 10.4.1 - BY BID
|
Amend Section 10.4.1 - 1 to
|
For clarity. If all bids
|
|
CONTRACT
|
include the following:
|
received are higher than the
|
|
|
|
AAE/AGE, this is an
|
|
|
"NO NEGOTIATION WILL BE
|
outright failure.
|
|
|
ALLOWED TO BRING DOWN THE
|
|
|
|
BID TO THE LEVEL OF THE AAE/
|
|
|
|
AGE.
|
|
|
|
|
|
|
Section IB 10.4.2 - BY
|
Modify the title as follows:
|
|
|
NEGOTIATED
|
|
|
|
CONTRACT p. 17
|
IB 10.4.2 - By Negotiated Contract
|
|
|
|
OR SIMPLIFIED PUBLIC
|
|
|
|
BIDDING
|
|
|
|
|
|
|
|
Amend Section IB 10.4.2-1a
|
|
|
|
a. In times of emergencies
|
|
|
|
arising from natural calamities
|
|
|
|
where immediate action is
|
|
|
|
necessary to prevent imminent
|
|
|
|
loss of life and/or property
|
|
|
|
OR TO RESTORE VITAL
|
|
|
|
PUBLIC SERVICES,
|
|
|
|
INFRASTRUCTURE AND UTILITIES
|
|
|
|
SUCH AS COLLAPSED BRIDGES,
|
|
|
|
CUT ROAD SECTIONS, BREACHED
|
|
|
|
DIKES, UNROOFED BUILDINGS
|
|
|
|
AND OTHER SEVERELY DAMAGED
|
|
|
|
VITAL FACILITIES.
|
|
|
|
Amend Section 10.4.2 - 1b as
|
This is to reconcile Section
|
|
|
follows:
|
IB 10.4.1 - g and this section
|
|
|
|
to indicate that there
|
|
|
b. Failure to award the contract
|
should be 2 bidding failures
|
|
|
after TWO (2) public biddings
|
before negotiated contract
|
|
|
for valid cause or causes.
|
may be entered into.
|
|
|
|
|
|
|
Amend Section IB 10.4.2 - Ic as
|
|
|
|
follows:
|
|
|
|
|
|
|
|
"Where the subject project is
|
The constructor should not
|
|
|
adjacent or contiguous to an
|
be eligible for negotiated
|
|
|
ongoing project and it could be
|
contract for a project
|
|
|
economically prosecuted by the
|
adjacent/contiguously
|
|
|
same contractor PROVIDED THAT
|
located if the contract cost
|
|
|
SUBJECT PROJECT HAS SIMILAR
|
exceeds the ceiling of the
|
|
|
OR RELATED SCOPE OF WORKS
|
constructor's class. The
|
|
|
AND IS WITHIN THE
|
constructor may not have
|
|
|
CONTRACTING CAPACITY OF THE
|
the financial and technical
|
|
|
CONTRACTOR, in which case, direct
|
capability if contract/project
|
|
|
negotiation may be undertaken . . ."
|
is beyond its class.
|
|
|
|
|
|
|
Add the following as Section IB
|
|
|
|
10.4.2-5:
|
|
|
|
"SIMPLIFIED PUBLIC BIDDING MAY
|
This is to allow negotiated
|
|
|
BE ADOPTED FOR MAJOR
|
bidding in times of
|
|
|
NATIONAL PROJECTS WHICH
|
emergencies when
|
|
|
ARE DEFINED HERE AS PROJECTS
|
immediate action is necessary
|
|
|
WITHIN THE APPROVED CORE
|
to restore damaged vital
|
|
|
PUBLIC INVESTMENT PROGRAM
|
public infrastructure,
|
|
|
(CPIP) OR FLAGSHIP PROJECTS
|
utilities, etc.
|
|
|
APPROVED BY THE PRESIDENT.
|
|
|
|
THE FOLLOWING GUIDELINES SHALL
|
|
|
|
BE FOLLOWED:
|
Simplified bidding is also
|
|
|
|
proposed to be adopted in
|
|
|
a. PARTICIPATION IN SIMPLIFIED
|
the implementation of
|
|
|
PUBLIC BIDDING FOR A PROJECT
|
major national priority projects
|
|
|
SHALL BE LIMITED TO
|
which cannot be
|
|
|
BONAFIDE CONTRACTORS DULY
|
delayed without detriment
|
|
|
ACCREDITED AND CLASSIFIED
|
to the public interest and
|
|
|
FOR THE PROJECT CATEGORY
|
whose deadlines are prescribed
|
|
|
AND SIZE AND WHO ARE
|
by Presidential
|
|
|
INCLUDED IN A SEPARATE
|
directives.
|
|
|
MASTER LIST TO BE PREPARED
|
|
|
|
BY THE PHILIPPINE
|
|
|
|
CONTRACTORS ACCREDITATION
|
|
|
|
BOARD (PCAB) PURSUANT TO
|
|
|
|
THE UNIFORM GUIDELINES
|
|
|
|
PROMULGATED BY THE PCAB. THE
|
|
|
|
GUIDELINES SHALL PUT EMPHASIS
|
|
|
|
ON STRICT REQUIREMENTS OF
|
|
|
|
GOOD TRACK RECORD PERFORMANCE
|
|
|
|
AND/OR CAPABILITY
|
|
|
|
REQUIREMENTS, AMONG OTHERS.
|
|
|
|
|
|
|
|
b. THE PCAB SHALL UPDATE THE
|
|
|
|
MASTER LIST QUARTERLY AND
|
|
|
|
SHALL DISSEMINATE THE
|
|
|
|
SAME TO CONCERNED
|
|
|
|
AGENCIES. THE MASTER
|
|
|
|
LIST SHALL INCLUDE THE
|
|
|
|
DELETION OF CONTRACTORS
|
|
|
|
WITH UNJUSTIFIED NEGATIVE
|
|
|
|
SLIPPAGES OR POOR PERFORMANCE
|
|
|
|
RECORD IN ANY GOVERNMENT
|
|
|
|
PROJECT.
|
|
|
|
|
|
|
|
c. FOR SPECIFIC PROJECT TO BE
|
|
|
|
BID OUT, THE PBAC OF THE
|
|
|
|
DEPARTMENT CONCERNED SHALL
|
|
|
|
INVITE ALL CONTRACTORS
|
|
|
|
INCLUDED IN THE MASTER LIST
|
|
|
|
WHICH ARE ACCREDITED AND
|
|
|
|
CLASSIFIED BY THE PCAB FOR
|
|
|
|
THE RELEVANT PROJECT CATEGORY
|
|
|
|
AND SIZE TO SUBMIT
|
|
|
|
TO THE PBAC NOT LATER THAN
|
|
|
|
A SPECIFIED DATE AND TIME
|
|
|
|
THE FOLLOWING: (A) THEIR
|
|
|
|
PREQUALIFICATION STATEMENTS,
|
|
|
|
AND (B) THEIR PRICE PROPOSALS
|
|
|
|
FOR THE SUBJECT
|
|
|
|
PROJECT. THE INVITATION
|
|
|
|
SHALL ALSO INDICATE THE
|
|
|
|
PROJECT DESCRIPTION, MAXIMUM
|
|
|
|
CONTRACT DURATION,
|
|
|
|
AND DESIRABLE STARTING DATE,
|
|
|
|
AMONG OTHERS.
|
|
|
|
|
|
|
|
d. ALL SUCH ACCREDITED AND
|
|
|
|
CLASSIFIED CONTRACTORS THAT
|
|
|
|
ARE INTERESTED IN BIDDING
|
|
|
|
FOR THE PROJECT SHALL
|
|
|
|
SECURE FROM THE PBAC,
|
|
|
|
UPON PAYMENT OF A
|
|
|
|
NON-REFUNDABLE FEE, COPIES OF
|
|
|
|
THE BID DOCUMENTS,
|
|
|
|
INCLUDING PLANS, SPECIFICATIONS,
|
|
|
|
DRAFT CONTRACT
|
|
|
|
WITH TERMS AND CONDITIONS,
|
|
|
|
INSTRUCTIONS TO
|
|
|
|
BIDDERS, AND PROPOSAL
|
|
|
|
BOOK WITH BILL OF QUANTITIES,
|
|
|
|
AMONG OTHERS.
|
|
|
|
|
|
|
|
e. SAID CONTRACTORS SHALL
|
|
|
|
SUBMIT TO THE PBAC, AT THE
|
|
|
|
DESIGNATED TIME AND DATE,
|
|
|
|
IN TWO SEPARATE SEALED
|
|
|
|
ENVELOPES: (A) THEIR
|
|
|
|
ACCOMPLISHED PREQUALIFICATION
|
|
|
|
STATEMENTS, AND
|
|
|
|
(B) THEIR PRICE PROPOSALS
|
|
|
|
FOR THE SUBJECT PROJECT
|
|
|
|
USING THE BID FORMS IN THE
|
|
|
|
PROPOSAL BOOK.
|
|
|
|
|
|
|
|
f. THE PBAC SHALL, IN
|
|
|
|
THE PRESENCE OF THE
|
|
|
|
CONTRACTORS AND REPRESENTATIVES
|
|
|
|
OF COA, DEPOSIT ALL
|
|
|
|
THE SEALED ENVELOPES
|
|
|
|
CONTAINING THE PRICE
|
|
|
|
PROPOSALS IN A DESIGNATED
|
|
|
|
SECURED CONTAINER (E.G.,
|
|
|
|
STEEL CABINET) AND SHALL
|
|
|
|
LOCK THIS USING TWO PADLOCKS,
|
|
|
|
ONE OF WHOSE KEYS
|
|
|
|
SHALL BE KEPT BY THE PBAC
|
|
|
|
CHAIRMAN AND THE OTHER
|
|
|
|
BY THE REPRESENTATIVE OF
|
|
|
|
THE COA IN THE PBAC.
|
|
|
|
|
|
|
|
g. THE PBAC SHALL WITHIN
|
|
|
|
ONE WEEK FROM THE SUBMISSION
|
|
|
|
OF SEALED ENVELOPES
|
|
|
|
THEN EVALUATE THE
|
|
|
|
PRE-QUALIFICATION STATEMENT
|
|
|
|
OF EACH OF THE BIDDERS.
|
|
|
|
|
|
|
|
h. WITHIN THE SAME PERIOD,
|
|
|
|
THE PBAC SHALL NOTIFY THE
|
|
|
|
PREQUALIFIED AS WELL AS
|
|
|
|
THE PREDISQUALIFIED
|
|
|
|
CONTRACTORS OF THE RESULTS
|
|
|
|
OF THE EVALUATION OF
|
|
|
|
THE PREQUALIFICATION
|
|
|
|
STATEMENTS. IN CASE OF A
|
|
|
|
PRE-DISQUALIFICATION, THE REASON
|
|
|
|
FOR SAME SHALL BE INDICATED.
|
|
|
|
|
|
|
|
i. THE PBAC SHALL ALLOW
|
|
|
|
ONE (1) WEEK AFTER THE
|
|
|
|
NOTICE MENTIONED IN PARAGRAPH
|
|
|
|
2.8 ABOVE HAVE BEEN
|
|
|
|
TRANSMITTED WITHIN WHICH
|
|
|
|
TO EVALUATE REQUESTS FOR
|
|
|
|
RECONSIDERATION, IF ANY,
|
|
|
|
FROM PREDISQUALIFIED
|
|
|
|
CONTRACTORS, AND SHALL NOTIFY
|
|
|
|
THEM ACCORDINGLY OF THE
|
|
|
|
RESULTS OF SUCH RE-EVALUATION
|
|
|
|
WITHIN THE SAME PERIOD.
|
|
|
|
|
|
|
|
j. THE PBAC SHALL INFORM
|
|
|
|
ALL PREQUALIFIED CONTRACTORS
|
|
|
|
OF THE DATE AND TIME OF THE
|
|
|
|
OPENING OF BIDS AND INSTRUCT
|
|
|
|
THEM TO SUBMIT THEIR RESPECTIVE
|
|
|
|
BID SECURITIES BEFORE SUCH DATE
|
|
|
|
IN AN AMOUNT PRESCRIBED UNDER
|
|
|
|
CLAUSE IB 10.1 HEREIN.
|
|
|
|
|
|
|
|
k. THE FAILURE OR REFUSAL OF
|
|
|
|
THE CONTRACTOR TO SUBMIT
|
|
|
|
SAID BID SECURITY SHALL
|
|
|
|
AUTOMATICALLY CAUSE THE
|
|
|
|
DELETION OF THE CONTRACTOR
|
|
|
|
FROM THE MASTER LIST.
|
|
|
|
|
|
|
|
l. AT THE DESIGNATED DATE AND
|
|
|
|
TIME, THE PBAC SHALL RECEIVE
|
|
|
|
THE BID SECURITIES OF THE
|
|
|
|
BIDDERS. THEREAFTER, THE PBAC
|
|
|
|
SHALL, IN THE PRESENCE OF
|
|
|
|
REPRESENTATIVES OF THE
|
|
|
|
COA, PUBLICLY OPEN THE
|
|
|
|
CONTAINER WHERE THE
|
|
|
|
SEALED ENVELOPES CONTAINING
|
|
|
|
THE PRICE PROPOSALS WHERE
|
|
|
|
DEPOSITED. ALL BIDDERS
|
|
|
|
SHALL BE INVITED TO HAVE
|
|
|
|
THEIR RESPECTIVE DULY
|
|
|
|
AUTHORIZED REPRESENTATIVES
|
|
|
|
PRESENT TO WITNESS
|
|
|
|
THE OPENING OF THE
|
|
|
|
PRICE PROPOSALS.
|
|
|
|
|
|
|
|
m. THE PBAC SHALL RETURN
|
|
|
|
TO THE PREDISQUALIFIED
|
|
|
|
CONTRACTORS THEIR
|
|
|
|
RESPECTIVE SEALED ENVELOPES
|
|
|
|
CONTAINING THEIR PRICE
|
|
|
|
PROPOSALS.
|
|
|
|
|
|
|
|
n. THE PBAC SHALL OPEN THE
|
|
|
|
SEALED ENVELOPE OF EACH
|
|
|
|
OF THE BIDDERS, EXAMINE
|
|
|
|
ITS CONTENTS AND
|
|
|
|
DETERMINED IF THE
|
|
|
|
CORRESPONDING BID SECURITY IS
|
|
|
|
ADEQUATE IN AMOUNT AND
|
|
|
|
IN THE PROPER FORM. THE
|
|
|
|
PBAC SHALL THEN OPEN,
|
|
|
|
READ AND RECORD THE
|
|
|
|
APPROVED AGENCY ESTIMATE.
|
|
|
|
IT SHALL THEREAFTER READ
|
|
|
|
AND RECORD THE PRICE
|
|
|
|
PROPOSALS OF EACH BIDDER.
|
|
|
|
|
|
|
|
o. THE PBAC SHALL HAVE TWO
|
|
|
|
(2) WEEKS FROM OPENING
|
|
|
|
OF THE SEALED ENVELOPES
|
|
|
|
CONTAINING THE FINANCIAL
|
|
|
|
PROPOSALS WITHIN WHICH
|
|
|
|
TO EVALUATE THE BIDS
|
|
|
|
IN DETAIL, PREPARE THE
|
|
|
|
RESOLUTION OF AWARD AND
|
|
|
|
SUBMIT THE SAME TO THE
|
|
|
|
APPROVING AUTHORITY.
|
|
|
|
|
|
|
Section IB 10.5 -
|
Amend Section IB 10.5-1 as follows:
|
|
|
ADMINISTRATIVE
|
|
|
|
SANCTIONS, p. 18
|
|
|
|
|
1. The following administrative
|
Item C below includes the
|
|
|
sanctions shall be imposed for
|
"award" process.
|
|
|
offenses/violations [of] COMMITTED
|
|
|
|
BY contractors [in] DURING the
|
|
|
|
prequalification [and], bidding
|
|
|
|
AND AWARD:
|
|
|
|
|
|
|
|
a. Suspension of one (1) year for
|
Various offenses or violations
|
|
|
first offense, disqualification for
|
may be committed by
|
|
|
two (2) years for the second
|
the contractors.
|
|
|
offense and perpetual disqualification
|
|
|
|
for succeeding offenses[s]
|
|
|
|
ON ANY OF THE FOLLOWS:
|
|
|
|
|
|
|
|
(1) Misrepresentation [of any
|
To give specifics or examples
|
|
|
information] on concealment
|
on the term "misrepresentation
|
|
|
of ANY[s] material fact OR
|
or concealment of
|
|
|
INFORMATION in the sworn
|
material fact".
|
|
|
prequalification statements and/or
|
|
|
|
bids, INCLUDING BUT NOT
|
|
|
|
LIMITED TO:
|
|
|
|
|
|
|
|
1.1 FALSIFICATION OF PUBLIC
|
|
|
|
DOCUMENTS;
|
|
|
|
1.2 SUBMISSION OF BORROWED
|
|
|
|
LICENSE (LICENSE LENDING)
|
|
|
|
|
|
|
|
(2) Submission of bids and/or detailed
|
|
|
|
estimates that are identical to each
|
|
|
|
other or to the Approved Agency
|
|
|
|
Estimates (AAE) WHICH
|
|
|
|
MANIFESTLY INDICATE RIGGING
|
|
|
|
OR COLLUSION.
|
|
|
|
|
|
|
|
(3) Other acts of the contractors
|
|
|
|
which directly or indirectly tend
|
|
|
|
to defeat the purpose of public
|
|
|
|
bidding.
|
|
|
|
|
|
|
|
b. SUSPENSION FOR SIX (6)
|
With reference to DPWH
|
|
|
MONTHS FOR FIRST OFFENSE.
|
D.O. #2 s. 1989 dated 04
|
|
|
DISQUALIFICATION FOR ONE
|
January 1989 and D.O. #87
|
|
|
(1) YEAR FOR SECOND OFFENSE,
|
s. 1988 dated 05 October
|
|
|
DISQUALIFICATION FOR TWO
|
1988, non-submission of
|
|
|
(2) YEAR FOR THIRD OFFENSE
|
bids by prequalified
|
|
|
AND PERPETUAL
|
contractors often result in
|
|
|
DISQUALIFICATION FOR
|
the failure of biddings.
|
|
|
SUCCEEDING OFFENSE:
|
This practice need to be
|
|
|
|
curtailed as it negates the
|
|
|
(1) NON SUBMISSION OF
|
objective of public bidding.
|
|
|
BIDS BY PREQUALIFIED
|
|
|
|
CONTRACTORS.
|
|
|
|
c. Forfeiture of bid security for first
|
|
|
|
offense, and suspension of one
|
|
|
|
(1) year for second offense, and
|
|
|
|
perpetual disqualification for
|
|
|
|
succeeding offense [for refusal or
|
|
|
|
failure of the proposed awardee to
|
|
|
|
enter into contract, or failure to
|
|
|
|
pose the required performance
|
|
|
|
security, within the prescribed time]
|
|
|
|
ON ANY OF THE FOLLOWING:
|
|
|
|
|
|
|
|
(1) UNJUSTIFIED FAILURE OR
|
To cite specific cases of
|
|
|
UNREASONABLE REFUSAL
|
refusal or failure of proposed
|
|
|
OF THE WINNING BIDDER
|
awardee to enter
|
|
|
TO ACCEPT OR SIGNIFY
|
into contract.
|
|
|
CONFORME TO THE NOTICE
|
|
|
|
OF AWARD (NOA).
|
|
|
|
|
|
|
|
(2) NON-SUBMISSION BY THE
|
|
|
|
PROPOSED AWARDEE WITHIN
|
|
|
|
THE PRESCRIBED TIME OF
|
|
|
|
THE PERFORMANCE SECURITY
|
|
|
|
AND OTHER REQUIREMENTS
|
|
|
|
NECESSARY FOR CONTRACT
|
|
|
|
PREPARATION, I.E., CONTRACTOR
|
|
|
|
IS ALL RISK (CAR)
|
|
|
|
INSURANCE, AFFIDAVIT OF NO
|
|
|
|
PENDING CASE FOR
|
|
|
|
NON-PAYMENT OF TAX CONSTRUCTION
|
|
|
|
SCHEDULE, CASH
|
|
|
|
FLOW AND OTHER REQUIREMENTS
|
|
|
|
NECESSARY FOR THE
|
|
|
|
FORMALIZATION OF THE
|
|
|
|
CONTRACT.
|
|
|
|
(3) UNJUSTIFIED REFUSAL OR
|
|
|
|
FAILURE OF THE PROPOSED
|
|
|
|
AWARDEE TO ENTER OR
|
|
|
|
SIGN THE PREPARED CONTRACT
|
|
|
|
WITHIN THE AGENCY PRESCRIBED
|
|
|
|
TIME.
|
|