Executive Order No. 645, issued on July 31, 2007, amends Section 4 of Executive Order No. 423 to streamline government procurement processes in accordance with the Government Procurement Reform Act (Republic Act No. 9184). It specifically addresses contracts amounting to at least P500 million, requiring Heads of Procuring Entities to secure approval from the Government Procurement Policy Board before using alternative procurement methods. Upon receiving this approval, they can finalize contracts, provided they certify compliance with applicable laws and regulations. The order aims to enhance procurement efficiency while maintaining regulatory oversight. All other provisions of Executive Order No. 423 remain unchanged.
Quick Answers
- What is Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts about?
- Executive Order No. 645, issued on July 31, 2007, amends Section 4 of Executive Order No. 423 to streamline government procurement processes in accordance with the Government Procurement Reform Act (Republic Act No. 9184). It specifically addresses contracts amounting to at least P500 million, requiring Heads of Procuring Entities to secure approval from the Government Procurement Policy Board before using alternative procurement methods. Upon receiving this approval, they can finalize contracts, provided they certify compliance with applicable laws and regulations. The order aims to enhance procurement efficiency while maintaining regulatory oversight. All other provisions of Executive Order No. 423 remain unchanged.
- What type of law is Executive Order No. 645?
- Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts (Executive Order No. 645) is a Philippine Presidential Issuances enacted by the Congress of the Philippines.
- When was Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts enacted?
- Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts (Executive Order No. 645) was enacted on Jul 31, 2007.
- What is the citation for Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts?
- Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts, Executive Order No. 645, Jul 31, 2007 (Philippines)
Law Information
- Reference Number
- Executive Order No. 645
- Date Enacted
- Category
- Presidential Issuances
- Subcategory
- Executive Orders
- Jurisdiction
- Philippines
- Enacting Body
- Congress of the Philippines
Full Law Text
July 31, 2007
EXECUTIVE ORDER NO. 645
AMENDING SECTION 4 OF EXECUTIVE ORDER NO. 423 DATED 18 SEPTEMBER 2003 WHICH PRESCRIBES THE RULES AND PROCEDURES ON THE REVIEW AND APPROVAL OF ALL GOVERNMENT CONTRACTS TO CONFORM TO REPUBLIC ACT NO. 9184 OTHERWISE KNOWN AS "THE GOVERNMENT PROCUREMENT REFORM ACT"
WHEREAS, Section 4 of Executive Order 423 dated 18 September 2003 prescribes that in cases where government contracts amounting to at least P500 Million, the Head of the Procuring Entity is required to obtain an opinion and approval from the Government Procurement Policy Board and the Director-General of the National Economic and Development Authority before resorting to any of the alternative methods of procurement; IAcDET
WHEREAS, it has become necessary to amend Section 4 of Executive Order No. 423 dated 18 September 2003 to streamline and expedite procurement procedures for a more effective procurement system;
WHEREAS, the Government Procurement Policy Board, in its Resolution No. 06-2006 dated 20 January 2006, recommends the issuance of this Executive Order;
NOW, THEREFORE, I, GLORIA MACAPAGAL-ARROYO, President of the Republic of the Philippines, by virtue of the powers vested in me by law, do hereby amend Section 4 of Executive Order No. 423 to read as follows:
Section 4. Approval of Government Contracts Entered Into Through Alternative Methods of Procurement
a. For Government Contracts Involving An Amount Of At Least Five Hundred Million Pesos (P500,000,000.00). — Where the Head of the Procuring Entity has made a determination that a Government contract, including Government contracts required by law to be acted upon and/or approved by the President, involving an amount of at least Five Hundred Million Pesos (P500,000,000.00) falls under any of the exceptions from public bidding described in Section 3 hereof, the Head of the Procuring Entity shall, before proceeding with the alternative methods of procurement provided by law and applicable rules and regulations, obtain the approval of the Government Procurement Policy Board (GPPB) that said Government proposed procurement undertaking falls within the exceptions from public bidding and that the proposed specific alternative mode of procurement is appropriate.
Except for Government contracts required by law to be acted upon and/or approved by the President, the Heads of the Procuring Entities, after obtaining the foregoing requirements, shall have full authority to give final approval and/or to enter into said Government contracts of their respective agencies, entered into through alternative methods of procurement allowed by law. Provided, that the Head of the Procuring Entity certifies under oath that the contract has been entered into in faithful compliance with all applicable laws and regulations.*
SECTION 2. Except for the foregoing amendment, all other provisions of Executive Order No. 423 shall remain unchanged.
SECTION 3. This Executive Order shall take effect immediately upon its publication in a national newspaper of general circulation.
DONE in the City of Manila, this 31st day of July, in the Year of Our Lord, Two Thousand and Seven. SEDaAH
Cite This Law
Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts, Executive Order No. 645, Jul 31, 2007 (Philippines)
Amendment to Sec. 4 of E.O. No. 423 s. 2003 Re: Rules and Procedures on the Review and Approval of All Government Contracts, Executive Order No. 645 (Phil. 2007)
Related Laws
- Repealing E.O. No. 109-A (s. 2003) Re: Rules and Procedures on the Review and Approval of All Government ContractsExecutive Order No. 423 • Apr 30, 2005 • Presidential Issuances
- Amendments to E.O. No. 109 (s. 2002) Re: Review and Approval of Government ContractsExecutive Order No. 109-A • Sep 18, 2003 • Presidential Issuances
- Further Amending Executive Order No. 423 (S. 2005), as AmendedExecutive Order No. 34 • Jul 17, 2017 • Presidential Issuances
- Review of All Government Contracts by the Government Corporate Counsel Prior to Approval of the PresidentLetter of Instructions No. 1096 • Dec 16, 1980 • Presidential Issuances
- Amendment to E.O. No. 252, s. 2003 Re: Transfer of Assets of Municipal Development Fund Office to Municipal Finance Corp.Executive Order No. 742 • Jul 21, 2008 • Presidential Issuances
- Repealing E.O. No. 460 s. 2005 and Reinstating E.O. No. 119 s. 2002 Re: Electric CooperativesExecutive Order No. 622 • May 9, 2007 • Presidential Issuances
Browse More Presidential Issuances
Explore other laws in the Presidential Issuances category.
View All Presidential IssuancesNeed Help Understanding This Law?
Ask our AI assistant to explain provisions, implications, or related laws.
Ask AI About This Law