The Department Circular No. 04-17 outlines the accreditation guidelines for Agricultural and Fisheries Machinery Testing Centers in the Philippines, established under the Agricultural and Fisheries Mechanization Law. Its main objectives are to create a reliable accreditation scheme, set standards for testing centers, and promote involvement from private sectors and higher education institutions. The guidelines detail the criteria and procedures for accreditation, including the necessary documentation, on-site assessments, and compliance requirements for maintaining accreditation. Non-compliance or fraudulent activities can lead to suspension or revocation of the Certificate of Accreditation. The circular is effective upon approval and publication, ensuring proper regulation of testing centers in the agricultural and fisheries sectors.
Quick Answers
- What is Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center about?
- The Department Circular No. 04-17 outlines the accreditation guidelines for Agricultural and Fisheries Machinery Testing Centers in the Philippines, established under the Agricultural and Fisheries Mechanization Law. Its main objectives are to create a reliable accreditation scheme, set standards for testing centers, and promote involvement from private sectors and higher education institutions. The guidelines detail the criteria and procedures for accreditation, including the necessary documentation, on-site assessments, and compliance requirements for maintaining accreditation. Non-compliance or fraudulent activities can lead to suspension or revocation of the Certificate of Accreditation. The circular is effective upon approval and publication, ensuring proper regulation of testing centers in the agricultural and fisheries sectors.
- What type of law is DA Department Circular No. 04-17?
- Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center (DA Department Circular No. 04-17) is a Philippine Other Rules and Procedures enacted by the Congress of the Philippines.
- When was Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center enacted?
- Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center (DA Department Circular No. 04-17) was enacted on May 16, 2017.
- What is the citation for Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center?
- Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center, DA Department Circular No. 04-17, May 16, 2017 (Philippines)
Law Information
- Reference Number
- DA Department Circular No. 04-17
- Date Enacted
- Category
- Other Rules and Procedures
- Subcategory
- Department of Agriculture
- Jurisdiction
- Philippines
- Enacting Body
- Congress of the Philippines
Full Law Text
May 16, 2017
DA DEPARTMENT CIRCULAR NO. 04-17
| SUBJECT | : | Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center |
Pursuant to Section 27 of the Republic Act No. 10601, otherwise known as the Agricultural and Fisheries Mechanization Law and its Implementing Rules and Regulations, this Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center is hereby prescribed and promulgated for guidance in the establishment of reliable and competent testing centers in the country.
ARTICLE I
General Provisions
SECTION 1. Objectives. —
The provisions under this Department Circular aim to achieve the following:
a) Provide and implement an accreditation scheme for agricultural and fisheries machinery testing center that is accessible, reliable, ethical and competent;
b) Set out the criteria, minimum requirements and standards for agricultural and fisheries machinery testing center; and
c) Encourage private sectors' and Higher Education Institutions' (HEIs) involvement in the testing of agricultural and fisheries machinery.
SECTION 2. Scope. —
This guidelines shall cover the rules and regulations governing the accreditation of HEIs, government, and private entities nationwide, which are independent institutions that can perform the testing and evaluation of locally and/or internationally manufactured agricultural and fisheries machinery.
The scope/s of accreditation covers the assessment of the building facility, equipment and Test Engineer or manpower including the support staff as applicable.
These guidelines shall complement with the Department Circular No. 05 otherwise known as the "National Guidelines on Testing and Evaluation of Agricultural and Fisheries Machinery." Thereby, the provisions in both guidelines shall apply.
SECTION 3. Definition of Terms. —
As used in this guidelines, the following terms shall be understood as follows:
3.1. Agricultural and Fisheries Machinery — refers to machinery and equipment for the production, post-production, harvesting, processing, storage, manufacture, preserving, transporting and distribution of agricultural and fisheries products and by-products. It includes, but not limited to, tractors and their attachments, power tillers, seeders, transplanters, windmills, harvesting machines, crop protection and maintenance equipment, irrigation equipment and accessories, greenhouses and other thermal conditioning equipment, livestock equipment, fishery equipment, slaughtering equipment, meat/fishery and crop processing equipment, postharvest machines such as milling machines, dryers, threshers, and fiber extraction machines;
3.2. Accreditation — the process of acquiring formal recognition from the Bureau of Agricultural and Fisheries Engineering (BAFE);
3.3. Accredited Testing Center — any private, government entities and HEIs which has the capacity to measure, examine, test, calibrate or otherwise determine the characteristics and performance of agricultural and fisheries machinery and has undergone accreditation by BAFE;
3.4. Applicant — refers to HEIs, government and private entities that have the capability to comply with the requirements for accreditation;
3.5. Building Facility — an infrastructure that follows precautionary measures for safety, and security, and wide enough to accommodate the office/s of the Test Engineer/s and the testing and sheltering of the different agricultural and fisheries machinery;
3.6. Certificate of Accreditation (CoA) — a document issued by the BAFE to testing center/s accrediting them to perform the tests and evaluations;
3.7. Revocation — refers to the complete annulment or withdrawal of the granted CoA;
3.8. Suspension — refers to the temporary invalidation of the granted CoA;
3.9. Test Engineer — licensed Agricultural and Biosystems Engineer who is accredited to perform testing and evaluation of agricultural and fisheries machinery pursuant to RA 10915.
ARTICLE II
Testing and Evaluation Accreditation Advisory Committee
SECTION 4. Testing and Evaluation Accreditation Advisory Committee as the reviewing and recommending committee. —
The Testing and Evaluation Accreditation Advisory Committee (TEAAC), as created through the Department Circular No. 5 under Section 4, is composed of representatives from concerned offices of the Department of Agriculture (DA) and other agencies namely: Bureau of Agriculture and Fisheries Standards (BAFS), Philippine Council for Agriculture and Fisheries (PCAF), Professional Regulatory Board of Agricultural and Biosystems Engineering (PRB-ABE), Philippine Society of Agricultural Engineers (PSAE), and University of the Philippines Los Baños-Agricultural Machinery Testing and Evaluation Center (UPLB-AMTEC). One of the core functions of the TEAAC is to review and recommend the granting of CoA for Agricultural and Fisheries Machinery Testing Centers. CAIHTE
ARTICLE III
Accreditation of Agricultural and Fisheries Machinery Testing Center
SECTION 5. Criteria for Accreditation. —
The following are the criteria for the accreditation of the agricultural and fisheries machinery testing center which is in accordance with the scope of accreditation applied for:
a) Must be an HEI, private or government entities,
b) Must have at least one Test Engineer,
c) Must have the building facility, equipment and manpower,
d) Must follow the PNS/PAES of agricultural and fisheries machinery, and
e) Must have a quality assurance system.
SECTION 6. Procedures for Accreditation. —
The following outlines the various stages of the accreditation process (see Annex A).
6.1. Submission of Requirements and Application Review
The applicant shall submit to the BAFE the required duly accomplished form (see Annex B) and its corresponding attachments for evaluation of the completeness and validity of the documentary requirements (see Annex C). Only valid and eligible applications shall be processed.
6.2. On-site Assessment
The BAFE shall then endorse to TEAAC the eligible applications for an on-site assessment. After the conduct of this assessment, the TEAAC shall submit the assessment report and recommendation letter to BAFE.
6.3. Evaluation and Approval of the Accreditation
The BAFE shall conduct final review and assessment of the recommended applications, prior to approval and issuance of CoA.
Applicant/s who does not meet the requirements shall be notified by the BAFE. The applicant/s shall be informed of the deficiency/non-conformity to the accreditation requirements.
6.4. Remedy in Case of Denial
Request for reconsideration together with the evidence of corrective action shall be submitted within fifteen (15) working days after the receipt of notification of denied accreditation. Otherwise, the decision of the BAFE shall be final.
6.5. Post Accreditation Assessment/Monitoring
After the grant of the CoA, the testing center shall be subjected to assessment every year to ensure their continued compliance with the conditions of the accreditation (Section 7.2.b) to be conducted by BAFE, with or without prior notice. Testing records, and records of calibration of test equipment conducted shall be ready for inspection at all times.
SECTION 7. Certificate of Accreditation. —
The CoA shall be specific to each type of test, thus multiple CoA can be issued to a testing center according to the scope of accreditation they were granted. The name of the accredited testing center shall be included in the Registry of Accredited Testing Centers.
7.1. Validity
The CoA is valid for a period of three (3) years unless suspended or revoked.
7.2. Conditions of Accreditation
Following the grant of accreditation, the Testing Center shall abide by the following commitments:
a) Maintenance and Calibration of Equipment
All testing equipment shall be maintained in good condition. Instruments and equipment requiring calibration or adjustment shall be calibrated and adjusted in accordance with the instructions of the manufacturer as well as quality assurance system of the testing center which reflects the external calibration of the third party.
b) Records
The accredited Testing Center/s shall provide a copy of all test reports upon its completion to the BAFE, excluding that of those agricultural and fisheries machinery undergoing research and development. They shall also maintain and make available for monitoring the records of their transaction such as follows:
• Records of the agricultural and fisheries machinery tested and evaluated,
• Records of the Test Engineer/s and other manpower responsible in the testing of the machinery,
• Records of all testing equipment, including number of units, date acquired, location and condition, and
• Copy of the schedule of fees/testing fees being imposed as prescribed by the BAFE and all the related financial transactions together with the supporting documents (e.g., official receipts)
NOTE: The accredited Testing Center/s shall provide official receipts to their clients.
c) Display
All accredited Testing Center/s shall display the official signboard, CoA, and testing fees in a place and manner conspicuous to their customers.
7.3. Renewal
Application for renewal of accreditation may be filed three (3) months prior to its expiration. The requirements for renewal are as indicated in Annex C. Test reports issued by Testing Center/s with expired CoA shall be invalid regardless of their pending renewal application.
7.4. Suspension/Revocation of CoA
In case of incapability or non-compliance of the testing center, a suspension or revocation of CoA and removal of the testing center from the certification registry shall be done accordingly (see Section 10). Moreover, other specific grounds for suspension and revocation are listed under Section 9 (Prohibited Acts) of Article V.
Reapplication in case of revocation shall be done in accordance with the terms and conditions set by the DA through BAFE and TEAAC.
ARTICLE IV
Schedule of Fees
SECTION 8. Fees and Charges. —
Fees and charges to be paid for the accreditation shall depend on the scope of the CoA granted (Annex D).
ARTICLE V
Final Provisions
SECTION 9. Prohibited Acts. —
9.1. Operating a Testing Center or engaging in agricultural and fisheries machinery testing business without proper or expired accreditation.
9.2. No employed test engineer/s or employment of test engineer/s with expired or invalid license and accreditation.
9.3. Using uncalibrated, broken or damaged equipment.
9.4. Violation of condition/s of accreditation (see Section 7.2).
9.5. Misrepresentation for purposes of securing the CoA or renewal thereof, such as giving a material false statement in the application, or submitting falsified documents.
9.6. Tampering of test results/test reports or rigging test procedures or entering false information about the agricultural and fisheries machinery being tested.
9.7. Obstructing or attempting to obstruct inspection by authorized representatives of BAFE or TEAAC.
9.8. Any act similar or analogous to the foregoing.
SECTION 10. Penalties and Sanctions. —
After due notice and hearing, the accredited Testing Center found to have committed any of the acts provided under Section 9 hereof shall be dealt with suspension or revocation of the CoA and/or with any applicable administrative penalties as imposed by the law.
The suspension of CoA of the test center issued thereof shall not exceed one year.
SECTION 11. Separability Clause. —
Should any provision of this Department Circular or any thereof be declared invalid, the other provisions, so far as they are separable, shall remain in force and effect.
SECTION 12. Effectivity. —
This Circular shall take effect upon approval of the DA Secretary and fifteen (15) days after publication by DA-BAFE. Three (3) copies of this circular shall be sent to the University of the Philippines Law Center. DETACa
Approved and promulgated this 16th day of May 2017.
(SGD.) EMMANUEL F. PIÑOL
Secretary
ANNEX A
(Informative)
ANNEX B
(normative)Application/Assessment Form
ANNEX C
(informative)
The following are the documentary requirements for the official accreditation:
1) General Requirements for Application
• Duly accomplished Application Form/Letter (Annex B)
• Organizational Structure
• Company Profile
• Staff Complement and Profile
• Proof of quality assurance system
• Building Lay-out/Floor Plan/Shop Lay-out
• Location Map
• Fire Safety Certificate
a) Private Entities
• BIR Registration and TIN
• Business Permits (e.g., Mayor's Permit)
• DTI/SEC registration
b) Government Entities
• Certificate of registration or other related permits
2) Renewal Requirements
• Existing Certificate of Accreditation
• Updated floor map (if applicable)
• Revised quality assurance system (if applicable)
• Copy of results of post accreditation assessment
NOTE: This includes such other documents that the BAFE may require from time to time protecting the interest of the government and the public.
ANNEX D
(normative)
The following are the prescribed fees relative to the Accreditation of the Agricultural and Fisheries Machinery Testing Center which shall be payable to the BAFE.
|
A |
Application Fee (Non-refundable, payable upon submission of application form) |
Php500.00 |
|
B |
Assessment Fee (Payable upon receipt of notification of endorsement for an on-site assessment to TEAAC) *Plane fares/travelling expenses of the assessors should be shouldered by the applicant |
Php7,000.00 |
|
C |
Re-assessment Fee (In case of denial and/or changes in application) |
Php3,500.00 |
|
D |
Basic Accreditation Fee (Payable after on-site assessment and approval of grant of CoA) |
Php1,000.00 |
|
E |
Other Fees Certified copy of the certificate of accreditation |
Php50.00 |
Cite This Law
Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center, DA Department Circular No. 04-17, May 16, 2017 (Philippines)
Accreditation Guidelines for Agricultural and Fisheries Machinery Testing Center, DA Department Circular No. 04-17 (Phil. 2017)
Related Laws
- Guidelines for the Classification and Accreditation of Agricultural and Fisheries Machinery Assemblers, Manufacturers, Importers, Distributors and DealersDA Department Circular No. 17, s. 2018 • Nov 16, 2018 • Other Rules and Procedures
- Guidelines on the DA Procurement of Agricultural and Fisheries Machinery and EquipmentDA Administrative Order. 06-17 • Jul 14, 2017 • Other Rules and Procedures
- National Guidelines on the Issuance of Certificate of Conformity for Agricultural and Fisheries MachineryDA Department Circular No. 19, s. 2018 • Dec 18, 2018 • Other Rules and Procedures
- Guidelines for the Organization of the National Agricultural and Fishery Machinery Assemblers, Manufacturers, Importers, Suppliers, Distributors and Dealers Accreditation BoardDA Memorandum Circular No. 01-17 • Jan 6, 2017 • Other Rules and Procedures
- National Guidelines for the Registration of Ownership of Agricultural and Fisheries Machinery and EquipmentDA-DILG Joint Memorandum Circular No. 1, s. 2018 • Jul 5, 2018 • Other Rules and Procedures
- National Guidelines for the Registration of Ownership of Agricultural and Fisheries Machinery and EquipmentDA-DILG Joint Memorandum Circular No. 2, s. 2018 • Aug 2, 2018 • Other Rules and Procedures
Browse More Other Rules and Procedures
Explore other laws in the Other Rules and Procedures category.
View All Other Rules and ProceduresNeed Help Understanding This Law?
Ask our AI assistant to explain provisions, implications, or related laws.
Ask AI About This Law